Which one of the following statements is true?
a. An increase in project scope is likely to increase project cost.
b. A decrease in the project time is likely to increase project quality.
c. An increase in the project quality requirements is likely to decrease project cost.
d. A decrease in the project cost is likely to decrease project time.