The project you are managing has nine stakeholders. How many channel of communications 

are there between these stakeholders?

a. 9

b. 8

c. 45

d. 36

2 Answers

Answer :

d. 36

Answer :

36

Related questions

Description : The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

Last Answer : d. 36

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : Which one is a true statement relating to project communications? a. A project sponsor is responsible for all communication methods and media. b. Different stakeholders typically have different communication needs ... project. d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : Which one is a true statement relating to project communications?  A. A project sponsor is responsible for all communication methods and media.  B.Different stakeholders typically have different communication ... project.  D. Email is the only way to communicate with large numbers of people

Last Answer : B.Different stakeholders typically have different communication needs

Description : Which one is a true statement relating to project communications?  a. A project sponsor is responsible for all communication methods and media.  b. Different stakeholders typically have different communication ... project.  d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.

Last Answer : a. informing stakeholders about the project.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.

Last Answer : a. The cost associated at the beginning of the project is highest.

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description :  You need to convey some very complex, detailed information to the project  stakeholders. What is the best method for communicating this kind of information?  A. Verbal  B. Vertical  C. Horizontal  D. Written

Last Answer : D. Written

Description : Why is it important to understand your Stakeholders?  A. They may work in a different department or company B. They may have different technical backgrounds C. They may not care about the project D. They can be a positive or negative influence on the project (Ans.)

Last Answer : D. They can be a positive or negative influence on the project (Ans.)

Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.

Last Answer : a. The cost associated at the beginning of the project is highest.

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.

Description : Project reporting can best be defined as:  a. informing stakeholders about the project.  b. storing and archiving of project information. c. gathering stakeholder feedback.  d. collecting project information.

Last Answer : a. informing stakeholders about the project

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : A communication management plan identifies the relevant information that should be  communicated to:  a. the project team.  b. the project stakeholders.  c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : The PM distributed a document to the stakeholders, which described the software to be  developed, the functionality, the users it would serve and the installation timeline. The document  was an example of: ... scope  4. It was not complete enough to be either a product or a project scope document

Last Answer : 4. It was not complete enough to be either a product or a project scope document

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : Who among the following are less able to influence a project? (A) Consultants (B) Contractors (C) Stakeholders (D) Project team

Last Answer : (B) Contractors

Description : . A key aspect of managing a project involves: a. defining which operational systems to put in place. b. identifying routine tasks. c. ensuring ongoing operations are maintained. d. planning to achieve defined objectives

Last Answer : d. planning to achieve defined objectives.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : Which one of the following best describes a project stakeholder? a. A party who is concerned about the project going ahead. b. A party with an interest or role in the project or is impacted by ... of the project. d. A party who has a financial stake in the organization managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : What are the 5 major processes of project management?  A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)  B. Starting, Closing, Managing, Planning, ... Finishing, Monitoring and Controlling, Executing, Planning D. Starting, Finishing, Executing, Managing, Closing

Last Answer : A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)

Description : A key aspect of managing a project involves:  a. defining which operational systems to put in place. b. identifying routine tasks.  c. ensuring ongoing operations are maintained.  d. planning to achieve defined objectives.

Last Answer : d. planning to achieve defined objectives.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Project risk management is best described as:  a. managing responses to threats.  b. identifying and acknowledging threats and opportunities.  c. planning responses to threats.  d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____.  a. data communications, time tradeoffs, and ... programming language  d. reports printed and PCA  e. x-rays, extensibility, and operational conversion

Last Answer : b. end-user efficiency, data communications, and reusability

Description : A Communications Management Plan does the following:  A. Coordinates an effort to communicate in meetings effectively B. Lays out a plan on how to communicate with your Project ... and  efficiently. D. Coordinates the communication between project leaders and uninterested project  members

Last Answer : C. Lays out the approach and method for delivering information effectively and  efficiently.

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description : The most formal definition of marketing is ________. A. Meeting needs profitably B. Identifying and meeting human and social needs C. The four Ps (product, price, place, promotion) D. ... ways that benefit the organization and its stakeholders. E. Improving the quality of life for consumers

Last Answer : D. An organizational function and a set of processes for creating, communicating, and delivering value to customers and for managing customer relationships in ways that benefit the organization and its stakeholders.