You are a project manager for Picture Shades, Inc. It manufactures window shades
that have replicas of Renaissance-era paintings on the inside for hotel chains. Picture
Shades is taking its product to the home market, and you’re managing the new project. It
will offer its products at retail stores as well as on its website. You’re developing the
project schedule for this undertaking. Looking at the following graph, which path is the
critical path?
A. A-B-C-E-H
B. A-D-E-H
C. A-F-G-H
D. A-F-G-E-H
that have replicas of Renaissance-era paintings on the inside for hotel chains. Picture
Shades is taking its product to the home market, and you’re managing the new project. It
will offer its products at retail stores as well as on its website. You’re developing the
project schedule for this undertaking. Looking at the following graph, which path is the
critical path?
A. A-B-C-E-H
B. A-D-E-H
C. A-F-G-H
D. A-F-G-E-H