When calculating EVM, Peter noticed that the cumulative planned value is 150%
of the cumulative earned value. What does this mean?
Select one:
a. SPI<1, so the project is behind schedule.
b. SPI>1, so the project is OK to complete on time.
c. SPI<1, so the project is ahead of time.
d. SPI>1, so the project is behind schedule.
e. SPI>1, so the project is on schedule.