A cylindrical ejector having its height 2 m fills after every 10 minutes with a peak sewage discharge of 0.0157 cumec. The diameter of the ejector chamber, is A. 2.30 m B. 2.40 m C. 2.45 m D. 2.50 m

1 Answer

Answer :

ANS: C

Related questions

Description : For a peak discharge of 0.0157 cumec, with a velocity of 0.9 m/sec, the diameter of the sewer main, is A. 10 cm B. 12 cm C. 15 cm D. 18 cm

Last Answer : ANS: C

Description : The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is A. 0.05552 cumec B. 0.05554 cumec C. 0.05556 cumec D. 0.0556 cumec

Last Answer : ANS: C

Description : The Brake Horse power of the motor (efficiency 60%) required for a pump of capacity 0.075 cumec for a total lift of 12 m, is A. 10 B. 15 C. 20 D. 25 Q No: 44 Aerobic bacterias A. ... presence of free oxygen B. Consume organic matter as their food C. Oxidise organic matter in sewage D. All the above

Last Answer : ANS: D

Description : The drainage area of a town is 12 hectares. Its 40% area is hard pavement ( K = 0.85), the 40% area is unpaved streets (K = 0.20) and the remaining is wooded areas (K = 0.15). Assuming the time of concentration ... 60) the maximum run off is A. 0.10 cumec B. 0.12 cumec C. 0.15 cumec D. 0.20 cumec

Last Answer : ANS: C

Description : For a grit chamber, if the recommended velocity of flow is 0.2 m/sec and detention period is 2 minutes, the length of the tank, is A. 16 m B. 20 m C. 24 m D. 30 m

Last Answer : ANS: C

Description : When drainage to sewage ratio is 20, the peak dry weather flow is A. 20% of the design discharge B. Slightly less than 5% of the design discharge C. Slightly more than 5% of the design discharge D. None of these

Last Answer : ANS: B

Description : The non-clog pump which permits solid matter to pass out with the liquid sewage, is A. Centrifugal pump B. Reciprocating pump C. Pneumatic ejector D. None of these

Last Answer : ANS: A

Description : Q No: 131 The most widely used pump for lifting sewage is A. Centrifugal pump B. Reciprocating pump C. Pneumatic ejector D. Air pressure pump

Last Answer : ANS: A

Description : Which of the following pumps in used to pump sewage solids with liquid sewage without clogging the pump is? A. Centrifugal pump B. Pneumatic ejector C. Reciprocating pump D. None of these

Last Answer : ANS: A

Description : In a grit chamber of a sewage treatment plant, A. Flow velocity 0.15 m to 0.3 m/sec is kept B. Depth of 0.9 m to 1.20 m is kept C. One minute of detention period is kept D. All the above

Last Answer : ANS: D

Description : The expected discharge to be obtained from an open well sunk in coarse sand is 0.0059 cumec. If  the working depression head of the well is 3 m, the minimum diameter of the well, is  (A) 2 m  (B) 2.25 m  (C) 2.50 m  (D) 3.00 m 

Last Answer : (D) 3.00 m 

Description : The design period of sewage treatment works in normally A. 5 – 10 years B. 15 – 20 years C. 30 – 40 years D. 40 – 50 years

Last Answer : ANS: B

Description : The sewage discharge in a detritus tank of a treatment plant is 576 litres/sec with flow velocity of 0.2 m/sec. If the ratio of width to depth is 2, the depth is A. 100 cm B. 110 cm C. 120 cm D. 150 cm

Last Answer : ANS: C

Description : The spacing of bars for perforations in coarse screens used for the treatment of sewage, is A. 20 mm B. 30 mm C. 40 mm D. 50 mm

Last Answer : ANS: D

Description : Pick up the correct statement from the following: A. The maximum rate of storm runoff is called peak drainage discharge B. Rational method of estimating peak run off, may be used precisely for ... entire area starts contributing to the runoff, is called the time of concentration D. All the above

Last Answer : ANS: D

Description : The bottom of the sewage inlet chamber of septic tanks, is provided an outward slope A. 1 in 5 B. 1 in 10 C. 1 in 15 D. 1 in 20

Last Answer : ANS: B

Description : The maximum spacing of manholes specified by Indian standard in sewers upto 0.3 m diameter is A. 20 m B. 30 m C. 45 m D. 75 m

Last Answer : ANS: C

Description : If the peak discharge of a storm water drain (S.W. Drain) is expected to exceed 150 cumecs, the free board to be provided, is A. 100 cm B. 90 cm C. 80 cm D. 50 cm

Last Answer : ANS: A

Description : For sewer mains of 0.5 to 1 m diameter, the ratio of maximum daily sewage flow to the average daily sewage flow is assumed A. 1.5 B. 2.0 C. 2.5 D. 3.0

Last Answer : ANS: B

Description : For trunk sewers more than 1.25 m in diameter, the ratio of the maximum daily sewage flow to the average daily sewage flow is assumed A. 1.5 B. 2.0 C. 2.5 D. 3.0

Last Answer : ANS: A

Description : The ratio of maximum sewage flow to average sewage flow for mains up to 1 m in diameter, is A. 1.5 B. 2.0 C. 3.0 D. 4.0

Last Answer : ANS: B

Description : A sewer pipe contains 1 mm sand particles of specific gravity 2.65 and 5 mm organic particles of specific gravity 1.2, the minimum velocity required for removing the sewerage, is A. 0.30 m/sec B. 0.35 m/sec C. 0.40 m/sec D. 0.45 m/sec

Last Answer : ANS: D

Description : In a city the ratio of the drainage to sewage is 20, the percentage discharge passing through non-monsoon periods, is A. 5 B. 10 C. 15 D. 20

Last Answer : ANS: D

Description : If the discharge of a sewer running half is 628 1.p.s., i = 0.001, and n = 0.010, the diameter of the sewer, is A. 1.39 m B. 1.49 m C. 1.59 m D. 1.69 m

Last Answer : ANS: D

Description : Pick up the correct statement from the following: A. The sewer pipes of sizes less than 0.4 m diameter are designed as running full at maximum discharge B. The sewer pipes of sizes greater than 0.4 m ... discharge C. The minimum design velocity of sewer pipes is taken as 0.8 m/sec D. All the above

Last Answer : ANS: D

Description : To prevent settling down of sewage both at the bottom and on the sides of a large sewer, self-cleaning velocity recommended for Indian conditions, is A. 0.50 m/sec B. 0.60 m/sec C. 0.70 m/sec D. 0.75 m/sec

Last Answer : ANS: D

Description : Two identical pumps, each capable of delivering 0.2 cumec, against a head of 30 m, are connected in parallel. The resulting discharge is : a) 0.4 cumec against a head of 30 m b) 0.4 cumec against a head of 60 m c) 0.2 cumec against a head of 30 m d) 0.2 cumec against a head of 60 m

Last Answer : a) 0.4 cumec against a head of 30 m

Description : For design of sewers, percentage of sewage discharge is assumed A. 65 to 70% B. 70 to 75% C. 75 to 80% D. 85%

Last Answer : ANS: C

Description : The sewer pipes A. Carry sewage as gravity conduits B. Are designed for generating self-cleansing velocities at different discharge C. Should resist the wear and tear caused due to abrasion D. All the above

Last Answer : ANS: D

Description : The ratio of maximum sewage flow to average sewage flow for trunk mains having diameters more than 1.25 m, is A. 1.5 B. 2.0 C. 3.0 D. 4.0

Last Answer : ANS: A

Description : The detention time of a circular tank of diameter d and water depth H, for receiving the sewage Q per hour, is A. d² (0.011d + 0.785H)/Q B. d (0.022d + 0.085H)/Q C. d (0.785d + 0.011H)/Q D. d (0.285d + 0.011H)/Q

Last Answer : ANS: A

Description : The rational formula for peak drainage discharge, was evolved by A. Fruhling B. Lloyd David C. Kuichling D. All of these

Last Answer : ANS: D

Description : The disintegrating pump in which solid matter is broken up before passing out, is A. Centrifugal pump B. Reciprocating pump C. Pneumatic ejector D. None of these

Last Answer : ANS: A

Description : The settling velocity of the particles larger than 0.06 mm in a settling tank of depth 2.4 is 0.33 m per sec. The detention period recommended for the tank, is A. 30 minutes B. 1 hour C. 1 hour and 30 minutes D. 2 hours

Last Answer : ANS: D

Description : If the depletion of oxygen is found to be 2.5 mg/litre after incubating 2.5 ml of sewage diluted to 250 ml for 5 days at 20°C, B.O.D. of the sewage is A. 50 mg/l B. 100 mg/l C. 150 mg/l D. 250 mg/l

Last Answer : ANS: D

Description : If the depletion of oxygen is found to be 5 ppm after incubating a 2.5% solution of sewage sample for 5 days at 21°C, B.O.D. of the sewage is A. 50 ppm B. 100 ppm C. 150 ppm D. 200 ppm

Last Answer : ANS: D

Description : Assertion A.: A free board of 0.3 m is provided above the top sewage line in septic tanks. Reason (R): It helps to accommodate the scum in the septic tank. A. Both A and R is true and R is the correct ... is not a correct explanation of A C. A is true but R is false D. A is false but R is true

Last Answer : ANS: A

Description : The gradient of sewers depends upon A. Velocity of flow B. Diameter of the sewer C. Discharge D. All the above

Last Answer : ANS: D

Description : If the depth of partial flow in a sewer of diameter 2 m, is 50 cm, its wetted perimeter is A. B. /2 C. /3 D. 2 /3

Last Answer : ANS: D

Description : The dimensions of a rectangular settling tank are: length 24 m, width 6 m and depth 3 m. If 2 hour detention period for tanks is recommended, the rate of flow of sewage per hour, is A. 204 cu.m B. 208 cu.m C. 212 cu.m D. 216 cu.m

Last Answer : ANS: D

Description : The width of a settling tank with 2 hour detention period for treating sewage 378 cu m per hour, is A. 5 m B. 5.5 m C. 6.5 m D. 7 m

Last Answer : ANS: D

Description : In sewage having fully oxidised organic matter, the nitrogen exists in the form of A. Nitrites B. Nitrates C. Free ammonia D. Aluminoid nitrogen

Last Answer : ANS: B

Description : Dilution method of disposing of sewage, is not preferred to A. When sewage is fresh B. When diluting water has high dissolved oxygen content C. When diluting water is used for water supply near the point of sewage disposed D. When the diluting water is having flow currents

Last Answer : ANS: C

Description : In 1000 kg of sewage, the total solids approximate A. 0.5 to 1.0 kg B. 1 kg to 2.0 kg C. 5 kg to 7.5 kg D. 7.5 kg to 10 kg

Last Answer : ANS: A

Description : 3.0 ml of raw sewage is diluted to 300 ml. The D.O. concentration of the diluted sample at the beginning of the test was 8 mg/l. After 5 dayincubation at 20°C, the D.O. concentration was 5 mg/l. The BOD of raw sewerage is A. 100 mg/l B. 200 mg/l C. 300 mg/l D. 400 mg/l

Last Answer : ANS: C

Description : A cylindrical pillar is 50 cm in diameter and 3.5 m in height. Find the cost of painting the curved surface of the pillar at the rate of ₹12.50 per m2 . -Maths 9th

Last Answer : Diameter of the pillar = 50 cm ∴ Radius (r) = 502m = 25 m = 14m and height (h) = 3.5m Curved surface area of a pillar = 2πrh ∴ Curved surface area to be painted = 112m2 ∴ Cost of painting of 1 m2 pillar = Rs. 12.50 ∴ Cost of painting of 112 m2 pillar = Rs. ( 112 x 12.50 ) = Rs. 68.75.

Description : In detritus tanks, A. Flow velocity is kept 0.09 m/sec B. Detention period is kept 3 to 4 minutes C. Organic and inorganic materials are separated D. All the above

Last Answer : ANS: D

Description : For efficient working of a sewer, it must be ensured that A. Minimum velocity of 0.45 m/sec, is maintained at its minimum flow B. A maximum velocity of 0.90 m/sec, is maintained at its maximum flow C. Both A. and B. D. Neither A. nor B.

Last Answer : ANS: C

Description : The spacing of bars of perforations of fine screens used for the treatment of sewage, is A. 2 to 3 mm B. 3 to 5 mm C. 5 to 8 mm D. 8 to 10 mm

Last Answer : ANS: A

Description : A five day B.O.D. at 15°C of the sewage of a town is 100 kg/day. If the 5 day B.O.D. per head at 15°C for standard sewage is 0.1 kg/day, the population equivalent is A. 100 B. 1000 C. 5000 D. 10000

Last Answer : ANS: D