The design period of sewage treatment works in normally A. 5 – 10 years B. 15 – 20 years C. 30 – 40 years D. 40 – 50 years

1 Answer

Answer :

ANS: B

Related questions

Description : The spacing of bars for perforations in coarse screens used for the treatment of sewage, is A. 20 mm B. 30 mm C. 40 mm D. 50 mm

Last Answer : ANS: D

Description : In a grit chamber of a sewage treatment plant, A. Flow velocity 0.15 m to 0.3 m/sec is kept B. Depth of 0.9 m to 1.20 m is kept C. One minute of detention period is kept D. All the above

Last Answer : ANS: D

Description : A cylindrical ejector having its height 2 m fills after every 10 minutes with a peak sewage discharge of 0.0157 cumec. The diameter of the ejector chamber, is A. 2.30 m B. 2.40 m C. 2.45 m D. 2.50 m

Last Answer : ANS: C

Description : Q No: 191 Design period of 40 to 50 years is adopted for A. Branch sewers B. Main sewers C. Trunk sewers D. All the above

Last Answer : ANS: D

Description : In a city the ratio of the drainage to sewage is 20, the percentage discharge passing through non-monsoon periods, is A. 5 B. 10 C. 15 D. 20

Last Answer : ANS: D

Description : The bottom of the sewage inlet chamber of septic tanks, is provided an outward slope A. 1 in 5 B. 1 in 10 C. 1 in 15 D. 1 in 20

Last Answer : ANS: B

Description : The Brake Horse power of the motor (efficiency 60%) required for a pump of capacity 0.075 cumec for a total lift of 12 m, is A. 10 B. 15 C. 20 D. 25 Q No: 44 Aerobic bacterias A. ... presence of free oxygen B. Consume organic matter as their food C. Oxidise organic matter in sewage D. All the above

Last Answer : ANS: D

Description : When drainage to sewage ratio is 20, the peak dry weather flow is A. 20% of the design discharge B. Slightly less than 5% of the design discharge C. Slightly more than 5% of the design discharge D. None of these

Last Answer : ANS: B

Description : The spacing of bars of perforations of fine screens used for the treatment of sewage, is A. 2 to 3 mm B. 3 to 5 mm C. 5 to 8 mm D. 8 to 10 mm

Last Answer : ANS: A

Description : The design period in years for pumping plants, is A. 1 B. 2 to 3 C. 3 to 5 D. 5 to 10

Last Answer : ANS: D

Description : For design of sewers, percentage of sewage discharge is assumed A. 65 to 70% B. 70 to 75% C. 75 to 80% D. 85%

Last Answer : ANS: C

Description : The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is A. 0.05552 cumec B. 0.05554 cumec C. 0.05556 cumec D. 0.0556 cumec

Last Answer : ANS: C

Description : The width of a settling tank with 2 hour detention period for treating sewage 378 cu m per hour, is A. 5 m B. 5.5 m C. 6.5 m D. 7 m

Last Answer : ANS: D

Description : Aerobic activity is maximum A. In freshly produced sewage B. At sewer pipes C. In sewer treatment plants D. None of these

Last Answer : ANS: A

Description : The sewer which transports the sewage to the point of treatment, is called A. House sewer B. Out-fall sewer C. Branch sewer D. Main sewer

Last Answer : ANS: B

Description : The sewage discharge in a detritus tank of a treatment plant is 576 litres/sec with flow velocity of 0.2 m/sec. If the ratio of width to depth is 2, the depth is A. 100 cm B. 110 cm C. 120 cm D. 150 cm

Last Answer : ANS: C

Description : Q No: 291 The coagulant widely used for sewage treatment, is A. Alum B. Ferric chloride C. Ferric sulphate D. Chlorinated copperas

Last Answer : ANS: B

Description : The sewage treatment in septic tanks is due to A. Anaerobic decomposition B. Aerobic decomposition C. Parasitic decomposition D. None of these

Last Answer : ANS: A

Description : Primary treatment of sewage consists of removal of A. Large suspended organic solids B. Oil and grease C. Sand and girt D. Floating materials

Last Answer : ANS: A

Description : The grit chambers of sewage treatment plants, are generally cleaned after A. 2 days B. 7 days C. 12 days D. 14 days

Last Answer : ANS: D

Description : Dried sewage after treatment is used as A. Fertilizer B. Building material C. Chemical for lowering B.O.D. D. Base material for paints

Last Answer : ANS: A

Description : For treating the sewage of a large city, you will recommend A. A sedimentation tank and an activated sludge treatment plant B. A plant consisting of Imhoff tanks with low rate trickling filters C. Sedimentation tanks with high rate trickling filters D. None of these

Last Answer : ANS: A

Description : The sewage treatment units in which anaerobic decomposition of organic matter is used, are called A. Imhoff tanks B. Trickling filters C. Sludge sedimentation tanks D. None of these

Last Answer : ANS: B

Description : During preliminary treatment of a sewage A. Oil and grease are removed from skimming tanks B. Floating materials are removed by screening C. Girt and sand are removed by girt chambers D. All the above

Last Answer : ANS: D

Description : The sewer that unloads the sewage at the point of treatment is called A. Main sewer B. Outfall sewer C. Branch sewer D. House sewer

Last Answer : ANS: B

Description : No treatment of the sewage is given if dilution factor is A. Less than 150 B. Between 150 to 200 C. Between 200 to 300 D. More than 500

Last Answer : ANS: D

Description : The dimensions of a rectangular settling tank are: length 24 m, width 6 m and depth 3 m. If 2 hour detention period for tanks is recommended, the rate of flow of sewage per hour, is A. 204 cu.m B. 208 cu.m C. 212 cu.m D. 216 cu.m

Last Answer : ANS: D

Description : WASTE WATER ENGINEERING Objective Questions with Answers Q No: 161 The quantity of liquid waste which flows in sewers during the period of rainfall, is known A. Sanitary sewage B. Industrial waste C. Storm sewage D. None of these

Last Answer : ANS: C

Description : If the depletion of oxygen is found to be 2.5 mg/litre after incubating 2.5 ml of sewage diluted to 250 ml for 5 days at 20°C, B.O.D. of the sewage is A. 50 mg/l B. 100 mg/l C. 150 mg/l D. 250 mg/l

Last Answer : ANS: D

Description : If the depletion of oxygen is found to be 5 ppm after incubating a 2.5% solution of sewage sample for 5 days at 21°C, B.O.D. of the sewage is A. 50 ppm B. 100 ppm C. 150 ppm D. 200 ppm

Last Answer : ANS: D

Description : If q is the average sewage flow from a city of population P, the maximum sewage flow A. Q = [(4 + )/(18 + )] q B. Q = [(18 + P)/(4 + )] q C. Q = [(18 + )/(4 + )] q D. Q = [(5 + )/((15 + )] q

Last Answer : ANS: C

Description : To prevent settling down of sewage both at the bottom and on the sides of a large sewer, self-cleaning velocity recommended for Indian conditions, is A. 0.50 m/sec B. 0.60 m/sec C. 0.70 m/sec D. 0.75 m/sec

Last Answer : ANS: D

Description : In normal conditions, the period for sludge digestion, is A. 10 days B. 20 days C. 30 days D. 60 days

Last Answer : ANS: C

Description : The drainage area of a town is 12 hectares. Its 40% area is hard pavement ( K = 0.85), the 40% area is unpaved streets (K = 0.20) and the remaining is wooded areas (K = 0.15). Assuming the time of concentration ... 60) the maximum run off is A. 0.10 cumec B. 0.12 cumec C. 0.15 cumec D. 0.20 cumec

Last Answer : ANS: C

Description : The angle subtended by the surface of sewer water with partial flow, at sewer centre is 120°, the depth of sewerage is A. 20 cm B. 25 cm C. 40 cm D. 50 cm

Last Answer : ANS: D

Description : 11. Acid regression stage of sludge digestion at a temperature 21°C extends over a period of A. 15 days B. 30 days C. 60 days D. 90 days

Last Answer : ANS: D

Description : Bottom openings 15 cm × 15 cm in the standing baffle wall are provided A. 15 cm c/c B. 22.5 cm c/c C. 30 cm c/c D. 50 cm c/c

Last Answer : ANS: B

Description : For a grit chamber, if the recommended velocity of flow is 0.2 m/sec and detention period is 2 minutes, the length of the tank, is A. 16 m B. 20 m C. 24 m D. 30 m

Last Answer : ANS: C

Description : In 1000 kg of sewage, the total solids approximate A. 0.5 to 1.0 kg B. 1 kg to 2.0 kg C. 5 kg to 7.5 kg D. 7.5 kg to 10 kg

Last Answer : ANS: A

Description : The normal values of over flow rates for secondary sedimentation tanks, ranges between A. 25,000 to 35,000 litres/sqm/day B. 40,000 to 50,000 litres/sqm/day C. 50,000 to 60,000 litres/sqm/day D. 80,000 to 10,000 litres/sqm/day

Last Answer : ANS: A

Description : In sewage treatment, the detention period allowed for oxidation ponds ranges from __________ weeks. (A) 1 to 2 (B) 4 to 5 (C) 9 to 10 (D) 15 to 20

Last Answer : (B) 4 to 5

Description : 3.0 ml of raw sewage is diluted to 300 ml. The D.O. concentration of the diluted sample at the beginning of the test was 8 mg/l. After 5 dayincubation at 20°C, the D.O. concentration was 5 mg/l. The BOD of raw sewerage is A. 100 mg/l B. 200 mg/l C. 300 mg/l D. 400 mg/l

Last Answer : ANS: C

Description : For sewer mains of 0.5 to 1 m diameter, the ratio of maximum daily sewage flow to the average daily sewage flow is assumed A. 1.5 B. 2.0 C. 2.5 D. 3.0

Last Answer : ANS: B

Description : The ratio of maximum sewage flow to average sewage flow for trunk mains having diameters more than 1.25 m, is A. 1.5 B. 2.0 C. 3.0 D. 4.0

Last Answer : ANS: A

Description : For trunk sewers more than 1.25 m in diameter, the ratio of the maximum daily sewage flow to the average daily sewage flow is assumed A. 1.5 B. 2.0 C. 2.5 D. 3.0

Last Answer : ANS: A

Description : A five day B.O.D. at 15°C of the sewage of a town is 100 kg/day. If the 5 day B.O.D. per head at 15°C for standard sewage is 0.1 kg/day, the population equivalent is A. 100 B. 1000 C. 5000 D. 10000

Last Answer : ANS: D

Description : The ratio of maximum sewage flow to average sewage flow for mains up to 1 m in diameter, is A. 1.5 B. 2.0 C. 3.0 D. 4.0

Last Answer : ANS: B

Description : If 2% solution of a sewage sample is incubated for 5 days at 20°C and depletion of oxygen was found to be 5 ppm, B.O.D. of the sewage is A. 200 ppm B. 225 ppm C. 250 ppm D. None of these

Last Answer : ANS: C

Description : If a 2% solution of sewage sample is incubated for 5 days at 20°C and the dissolved oxygen depletion was found to be 8 mg/l. The BOD of the sewage is A. 100 mg/l B. 200 mg/l C. 300 mg/l D. 400 mg/l

Last Answer : ANS: D

Description : Before discharging the foul sewage into rivers, it is generally treated by A. Screening B. Sedimentation C. Oxidation D. All the above

Last Answer : ANS: D