The maximise criteria is ...........................
a. Optimistic
b. Pessimistic
c. Neutral
d. None of these

1 Answer

Answer :

b. Pessimistic

Related questions

Description : Which of the following is an assumption of game theory? a. The players act rationally and intelligently b. Each payer has a finite set of possible courses of action c. The players attempt to maximise gains or minimises losses d. All of the above

Last Answer : d. All of the above

Description : In a maximisation assignment problem, the objective is to maximise ............................. a. Profit b. Cost c. Optimisation d. None of these

Last Answer : a. Profit

Description : The assignment problem is: a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximise resource d. All the above

Last Answer : d. All the above

Description : Are you pessimistic or optimistic for the economic future of your country?

Last Answer : answer:I agree with David Suzuki that economics is a mental illness. From inside that illness, I think that things may go up or down but that it will eventually get worse and worse, unless/until many things change that are outside the mental box of that illness.

Description : Are humans naturally optimistic or pessimistic?

Last Answer : neither, we are neutral at birth and the effects of life change us to think one way or the other.

Description : Are you optimistic or pessimistic about our future? (Immediate and Long-term)

Last Answer : Well, lloydbird honey, I don't know how much of a future we have since I'm a happily married woman . . . Oh, wait, us? Humanity? I think the future looks bright. While I don't ... the importance of saving our planet and its resources. Fluther gives me hope, especially the posts of the young people.

Description : What situation best describes a difference in interpretation A.One painter's life work shows an optimistic outlook while another painter's life work shows a deeply pessimistic outlook. B.One noveli?

Last Answer : What is the answer ?

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (A) (a + m + b)/6 (B) (a + 2m + b)/6 (C) (a + 4m + b)/6 (D) (a + 5m + b)/6

Last Answer : (C) (a + 4m + b)/6

Description : The area under the Beta distribution curve is divided into two equal parts by (A) Most likely time (B) Optimistic time (C) Pessimistic time (D) Expected time

Last Answer : (D) Expected time

Description : If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively (A) 3.5 and 5/6 (B) 5 and 25/36 (C) 3.5 and 25/36 (D) 4 and 5/6

Last Answer : (C) 3.5 and 25/36

Description : Pick up the correct statement from the following: (A) Optimistic time estimate refers to activities (B) Pessimistic time estimate refers to activities (C) Most likely time estimate refers to activities (D) All the above

Last Answer : (D) All the above

Description : For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is (A) 8 days (B) 9 days (C) 10 days (D) 15 days

Last Answer : (B) 9 days

Description : If a simplex table shows the values 2, -3, 0 against “θ”, which should be taken as the replacement ratio. a. 2 b. -3 c. 0 d. None of these

Last Answer : c. 0

Description : Controllable variables are also called.................................. a. Slack variables b. Surplus variables c. Artificial variable d. Decision variables

Last Answer : d. Decision variables

Description : The variables which cannot be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : b. Uncontrollable variables

Description : The variables which can be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : a. Controllable variables

Description : The outlet where the services are being provided to the customers is called................. a. Waiting line b. Service facility c. Idle facility d. Traffic intensity

Last Answer : b. Service facility

Description : .................... is the popular method for solving an assignment problem. a. Hungarian Method b. Enumeration Method c. Simplex Method d. None of the above

Last Answer : a. Hungarian Method

Description : Hungarian method was developed by ........................ a. T C Koopman b. F L Hitchcock c. D Konig d. George B Dantzig

Last Answer : c. D Konig

Description : Which of the following methods is used to solve an assignment problem: a. Enumeration Method b. Hungarian Method c. Simplex Method d. All of the above

Last Answer : d. All of the above

Description : VAM is also called........................ a. Matrix Minima Method b. Penalty Method c. MODI Method d. None of these

Last Answer : b. Penalty Method

Description : Transportation model was first introduced by ........................ in the year 1941. a. T C Koopman b. George B Dantzig c. Von-neumann d. F L Hitchcock

Last Answer : d. F L Hitchcock

Description : ................................is that element of the simplex table which lis both in the key row and key column. a. Key element b. Pivot element c. Both a and b d. None of these

Last Answer : c. Both a and b

Description : Shadow price is also called ...................... a. Dual price b. Unit price c. Total cost d. None of these

Last Answer : a. Dual price

Description : Which of the following is a characteristic of a dual problem: a. Dual of a dual is primal b. If dual has a finite optimal solution, then the primal also has finite optimal solution c. If dual has no feasible solution, then the primal also has no feasible solution d. All of the above

Last Answer : d. All of the above

Description : Game theory became popular when the book “Theory of Games and Economic Behaviour” was published in 1944 by .............................. a. Von Neumann b. Mc Closky c. Von-Neumann and Mc Closky d. Von-neumann and Morgenstern

Last Answer : d. Von-neumann and Morgenstern

Description : Traffic intensity is computed by using the formula: a. λ/μ b. μ/λ c. 1- λ/μ d. 1- μ/λ

Last Answer : a. λ/μ

Description : Traffic intensity in Queuing Theory is also called........................... a. Service factor b. Arrival factor c. Utilisation factor d. None of these

Last Answer : c. Utilisation factor

Description : ..............................was the first person who developed a viable queueing theory a. Von Neumann b. Morgenstern c. H M Wagner d. Simeon Dennis Poisson

Last Answer : d. Simeon Dennis Poisson

Description : Excess of service facilities over and above the number of customers results: a. Idleness of service capacity b. Queues c. Both a and b d. None of these

Last Answer : a. Idleness of service capacity

Description : ............................refers to the manner in which the customers behave while being in the queue. a. Service pattern b. Service pattern c. Queue discipline d. None of these

Last Answer : c. Queue discipline

Description : MODI Method to test the optimality of a feasible solution to TP is also called............... a. Stepping Stone Method b. u. v. Method c. both a and b d. none of these

Last Answer : b. u. v. Method

Description : Matrix Minima Method to find initial feasible solution to a TP is also called ....................... a. NWCM b. LCM c. VAM d. None of these

Last Answer : c. VAM

Description : In Transportation Problem, LCM stands for ............................. a. Lowest Common Multiplier b. Least Cost Method c. Lowest Cell Method d. None of these

Last Answer : b. Least Cost Method

Description : In Transportation Problem, NWCM stands for ............................. a. North West Cost Method b. Net Worth Corner Method c. North West Corner Method d. None of these

Last Answer : c. North West Corner Method

Description : Initial feasible solution to a transportation problem arrived through which of the following method is very near to the optimal solution: a. NWCM b. LCM c. VAM d. None of these

Last Answer : c. VAM

Description : In queuing theory, FCFS stand for .............................. a. First Cum First Served b. First Customer Fist Served c. Fast Channel First Served

Last Answer : a. First Cum First Served

Description : ...................... is a method of analysing the current movement of the some variable in an effort to predict the future movement of the same variable. a. Goal programming b. Queuing theory c. Markov Analysis d. Replacement theory

Last Answer : c. Markov Analysis

Description : In queuing theory, ............................ stands for mean service rate. a. μ b. λ c. t d. none of these

Last Answer : a. μ

Description : In queuing theory, ............................ stands for mean arrival rate of customers. a. μ b. λ c. t d. none of these

Last Answer : b. λ

Description : A customer’s behaviour of jumping from one queue to another is called ............................ a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : a. Jockying

Description : A customer’s behaviour of leaving the queue due to impatience is called ....................... a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : b. Reneging

Description : a customer’s behaviour of leaving the queue when he does not like to wait in the queue due to lack of time or space is called ..................... a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : d. Balking

Description : Commonly assumed probability distribution of service pattern are ....................... a. Poisson distribution b. Exponential distribution c. Erlang distribution d. b and c

Last Answer : d. b and c

Description : Commonly assumed probability distribution of arrival pattern is ....................... a. Poisson distribution b. Binomial distribution c. Normal distribution d. None of these

Last Answer : a. Poisson distribution

Description : The ration between mean arrival rate and mean service rate is called ................... a. Idle period b. Average length of queue c. Traffic intensity d. None of these

Last Answer : c. Traffic intensity

Description : Number of customers in the queue per unit of time is called ...................... a. Queuing system b. Length of queue c. Average length of queue d. None of these

Last Answer : c. Average length of queue

Description : In waiting line theory, number of customers waiting in the queue is referred to as ................ a. Traffic intensity b. Queuing system c. Service pattern d. Queue length

Last Answer : d. Queue length