If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its
expected time and variance are respectively
(A) 3.5 and 5/6
(B) 5 and 25/36
(C) 3.5 and 25/36
(D) 4 and 5/6