Pick up the correct statement from the following:
(A) Optimistic time estimate refers to activities
(B) Pessimistic time estimate refers to activities
(C) Most likely time estimate refers to activities
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (A) (a + m + b)/6 (B) (a + 2m + b)/6 (C) (a + 4m + b)/6 (D) (a + 5m + b)/6

Last Answer : (C) (a + 4m + b)/6

Description : The area under the Beta distribution curve is divided into two equal parts by (A) Most likely time (B) Optimistic time (C) Pessimistic time (D) Expected time

Last Answer : (D) Expected time

Description : If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively (A) 3.5 and 5/6 (B) 5 and 25/36 (C) 3.5 and 25/36 (D) 4 and 5/6

Last Answer : (C) 3.5 and 25/36

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is (A) 8 days (B) 9 days (C) 10 days (D) 15 days

Last Answer : (B) 9 days

Description : Are you pessimistic or optimistic for the economic future of your country?

Last Answer : answer:I agree with David Suzuki that economics is a mental illness. From inside that illness, I think that things may go up or down but that it will eventually get worse and worse, unless/until many things change that are outside the mental box of that illness.

Description : Are humans naturally optimistic or pessimistic?

Last Answer : neither, we are neutral at birth and the effects of life change us to think one way or the other.

Description : Are you optimistic or pessimistic about our future? (Immediate and Long-term)

Last Answer : Well, lloydbird honey, I don't know how much of a future we have since I'm a happily married woman . . . Oh, wait, us? Humanity? I think the future looks bright. While I don't ... the importance of saving our planet and its resources. Fluther gives me hope, especially the posts of the young people.

Description : What situation best describes a difference in interpretation A.One painter's life work shows an optimistic outlook while another painter's life work shows a deeply pessimistic outlook. B.One noveli?

Last Answer : What is the answer ?

Description : The maximise criteria is ........................... a. Optimistic b. Pessimistic c. Neutral d. None of these

Last Answer : b. Pessimistic

Description : Pick up the correct statement from the following: (A) The incidental expenses of a miscellaneous character which could not be predicted during preparation of the estimate, is called contingencies (B) ... and the proportions of materials to be used for a particular item (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) O.M.C. refers to the moisture corresponding to the maximum point on the moisture content dry density curve (B) The line which shows moisture content dry ... void line (C) The free fall of hammer for compaction is 30.5 cm (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Indian space effort started in 1962 with the establishment of a rocket (B) Development of space (DOS) was established by the Government of ... is responsible for the space technology and its application to various activities (D) All of these

Last Answer : Answer: Option D

Description : CPM is (A) Synthesising in concepts (B) Is built of activities oriented programme (C) Is based on time estimate (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) An artificial barrier which makes the enclosed area safe for anchorage of ships, is known as break water (B) The break water whose inside is used ... wall is governed by the length of the largest vessel likely to be berthed (D) All the above

Last Answer : (D) All the above

Description : The time corresponding to minimum total project cost is (A) Crash time (B) Normal time (C) Optimistic time (D) Between normal time and crash time

Last Answer : (D) Between normal time and crash time

Description : The time with which direct cost does not reduce with the increase in time is known as (A) Crash time (B) Normal time (C) Optimistic time (D) Standard time

Last Answer : (B) Normal time

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : Pick up the item of work not included in the plinth area estimate (A) Wall thickness (B) Room area (C) W.C. area (D) Courtyard are

Last Answer : (D) Courtyard area

Description : Point out the wrong statement. a) Taken as a unit, Request => Process => Response is not an atomic transaction b) A coherent transaction either succeeds and is enacted, or ... transaction commitment in a multiuser application, durability requires correcting the condition d) None of the mentioned

Last Answer : Taken as a unit, “Request => Process => Response” is not an atomic transaction

Description : How do you know if you're either: jaded, cynical, pessimistic, or have a more realistic outlook of life?

Last Answer : I grappled with this a bit, but decided I’m a ‘positive cynic.’ I know, it seems oxymoronic. All the better.

Description : What to do when...you happen to be surrounded by pessimistic people?

Last Answer : Go with the flow. When you hear some of these outlandishly wacky “theories” ... just go them one better. Obama is not only an alien, but he’s a space alien. The ears are a giveaway, you know. And Michelle is his controller. You don’t think she’s from this planet, do you? ‘Course not.

Description : How do you accommodate a person who is fervently pessimistic when you are an eternal optimist?

Last Answer : What are you getting out of the friendship? Is there any reason to remain in this person’s presence?

Description : Why is the synchronous impedance method of estimating voltage regulation considered as pessimistic method?

Last Answer : Compared to other methods, the value of voltage regulation obtained by the synchronous impedance method is always higher than the actual valuei.e actual value is lower than the results obtained and therefore this method is called the pessimistic method.

Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Some scientists‘ estimate that in nature, _____ of all microbial activities occur in biofilms. a. 0.25 b. 0.33 c. 0.45 d. 0.6 e. 0.99

Last Answer : e. 0.99

Description : …… is a tool to estimate the cost or necessary efforts for projects, work packages or activities in project management. 1. Cost budgeting 2. cost control 3. Cost analysis 4. Resource Planning

Last Answer : Cost budgeting

Description : While preparing a detailed estimate (A) Dimension should be measured correct to 0.01 m (B) Area should be measured correct to 0.01 sqm (C) Volume should be measured correct to 0.01 cum (D) All the above

Last Answer : (D) All the above

Description : How hard do you find it to be realistic and optimistic at the same time?

Last Answer : Being a realist is the practical way to put optimism into action.

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time D. between normal time and crash time

Last Answer : D. between normal time and crash time

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time

Last Answer : D. between normal time and crash time

Description : The time with which direct cost does not reduce with the increase in time is known as  A.crash time B.normal time C.optimistic time D.standard time

Last Answer : B.normal time

Description : The likely estimate on equivalent power wastage for a leakage from 7 bar compressed air system through 1.6 mm orifice size is ____ a) 0.2 kW b) 3.0 kW c) 0.8 kW d) 12 kW

Last Answer : c) 0.8 kW

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : How optimistic should we be about the recent HIV vaccine trial?

Last Answer : If it proves safe and effective, that’s wonderful. My heart goes out to those didn’t survive to see this day.

Description : Are you cautiously optimistic that the early voting turnout has been so huge?

Last Answer : I don’t get my hopes up. Too many disappointments in the past 30+ years of voting.

Description : What makes you optimistic for the future?

Last Answer : Only in a general way. I strongly believe that life, in general, is a product of cycles, and that all cycles change over time. I have found this to be true in my life, my happiness, my health, ... stems from my belief that bad things, over time, tend to get better. Or as George Harrison wrote, link

Description : Is there a downside of being a flexible, optimistic person?

Last Answer : The downsides, as I see them, are - People take your optimism and flexibility as naivety and a lack of backbone. Also see Why is enthusiasm often perceived as naivety? - The perception that there's ... to you. Just work on a healthy balance and realize what others see in your outlook and actions.

Description : Assuming the most optimistic scenario, how serious a problem is global warming going to be?

Last Answer : There is not but many will wrongly claim that there is. As far as how serious it will be is a complete unknown. Um . Bad, probably. I'm not even touching the cause here because it's pointless to ... . At least change will happen slowly enough to give us time to adapt. What else is there to say?

Description : Were you ever Negative Nancy but eventually changed your mindset and are now optimistic?

Last Answer : Actually I used to be what one would consider to be a true optimist, but my life experiences have led to me to support the logic behind this quote A pessimist is an optimist with experience - ... pessimist in the true sense, but I'm just more careful now being a bit older and more experienced.

Description : Do you believe if you have a positive and optimistic outlook, good things will happen to you?

Last Answer : Yes….positive attitude is everything to being happy! At an early age my mom taught me to answer “great!” no matter what when people asked you how you are doing. More often than not thinking you are doing great will help override even the funkiest of funks.

Description : What weather conditions would make a climber optimistic?

Last Answer : A sunny but little cold weather could make the mountain climberoptimistic.

Description : Why is the MMF method of estimating the voltage regulation considered as the optimistic method?

Last Answer : In this method the actual value is more than the result obtained.

Description : When planning a systems project, overly optimistic timetables are the cause of project  completion delays.

Last Answer : Ans: True