PERT (Project Evaluation and Review Technique) analysis is based on
A. Optimistic time, Pessimistic time and Most likely time
B.Pessimistic time, Optional time, Maximum time
C.Optimistic time, Efficient time, Most likely time
D.Minimax time, Optimistic time and harmonic time
A. Optimistic time, Pessimistic time and Most likely time
B.Pessimistic time, Optional time, Maximum time
C.Optimistic time, Efficient time, Most likely time
D.Minimax time, Optimistic time and harmonic time