For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,
17 and 8 days respectively, The expected time is
(A) 8 days
(B) 9 days
(C) 10 days
(D) 15 days
17 and 8 days respectively, The expected time is
(A) 8 days
(B) 9 days
(C) 10 days
(D) 15 days