What is the heating time in OXY & LPG in SPW?  
 (i) 2.0 - 3.5 minutes.
 (ii) 2.0 - 3.0 minutes.
 (iii) 2.0 - 2.5 minutes.*
 (iv) 3.0 - 4.5 minutes.

1 Answer

Answer :

iii) 2.0 - 2.5 minutes

Related questions

Description : Heating time with compressed air and petrol in SPW is ? (i) 4.0 to 4.5 minutes.* (ii) 4.0 to 5 minutes (iii) 5.0 to 5.5 minutes (iv) 5.5 to 6 minutes

Last Answer : (i) 4.0 to 4.5 minutes.*

Description : What are the recognized systems for pre heating of rails ends for AT Welding? (i) Oxygen –LPG & Compressed air petrol both* (ii) Only Oxygen –LPG (iii) Only Compressed air petrol both (iv) both are correct

Last Answer : ) Oxygen –LPG & Compressed air petrol both*

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : Normal Reaction time in SPW technique? (i) 17 ± 3 seconds. (ii) 15 ± 3 seconds (iii) 23 ± 3 seconds (iv) 20 ± 3 seconds*

Last Answer : (iv) 20 ± 3 seconds*

Description : Full form of SPW? (i) Special pre heated weld (ii) Short preheated weld.* (iii) Short post heated weld (iv) None of above

Last Answer : (ii) Short preheated weld.*

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : What is mould waiting time? (i) 3 to 5 minutes. (ii) 4 to 6 minutes* (iii) 3.5 to 5.5 minutes (iv) 4.5 to 6.5 minuteses

Last Answer : (ii) 4 to 6 minutes*

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Defect of lack of fusion is mainly due to? (i) Improper heating.* (ii) Improper Gap (iii) Improper grinding (iv) None of above

Last Answer : (i) Improper heating.*

Description : Defect of Blow holes is due to? (i) Slag (ii) Moisture* (iii) Lack of heating (iv) Extra heating

Last Answer : (ii) Moisture*

Description : What is Pre Heating Temperature of rail ends in AT Welding? (i) 300 ± 20oC (ii) 400 ± 20oC (iii) 500 ± 20oC (iv) 600 ± 20oC *

Last Answer : (iv) 600 ± 20oC *

Description : During AT welding reaction is ? (i) Exothermic .* (ii) Endothermic (iii) No Reaction (iv) Heating

Last Answer : (i) Exothermic .*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : 450 probe is used for detecting defect in; (i) FB weld (ii) AT weld (iii) FB weld, AT weld & SEJ (iv) All above*

Last Answer : (iv) All above*

Description : In AT welding process what is the role of asbestos powder & slag ? (i) To separate closing pin from portion* (ii) To hold the portion (iii) Both above are correct (iv) None of the above

Last Answer : (i) To separate closing pin from portion*

Description : In AT welding process what is the role of closing pin ? (i) To hold the portion before melt (ii) To hold the asbestos powder & slag (iii) Both above are correct* (iv) None of the above

Last Answer : (iii) Both above are correct*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : Crucible is repaired by? (i) Magnasite Powder (ii) Magnasite Powder & Sodium Silicate.* (iii) Sodium Silicate (iv) Aluminium powder

Last Answer : (ii) Magnasite Powder & Sodium Silicate.*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : The gap between probing face and probing shoe should be. (i) 0.4 mm (ii) 0.2mm * (iii) 3mm (iv) 1mm.

Last Answer : (ii) 0.2mm *

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Pressure of compressed air is kept during preheating by CAPS? (i) 1 to 2 kg/cm2 (ii) .1 to .2 kg/cm2 (iii) 2 to 3 kg/cm2 (iv) 0.2 to 0.3 kg/cm2*

Last Answer : (iv) 0.2 to 0.3 kg/cm2*

Description : How rejected portion are to be disposed-off? (i) By Igniting 5 Portions at a time in pit away from store?* (ii) By throwing them away (iii) By dispose off in a pit (iv) By using it in Branch/Yard lines for welding

Last Answer : (i) By Igniting 5 Portions at a time in pit away from store?*

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : How many grams asbestos powder is used to cover head of closing pin ? (i) 2 grams (ii) 3 grams (iii) 4 grams (iv) 5 grams*

Last Answer : (iv) 5 grams*

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : To take care of differential cooling rail ends of 72 UTS rails are lifted by? (i) 1 to 1.5 mm (ii) 1 to 2 mm (iii) 2 to 2.5 mm (iv) 3 to 4 mm *

Last Answer : iv) 3 to 4 mm *

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : Risers are broken at? (i) cold. * (ii) Hot (iii) After 5 mints (iv) After 3 mints

Last Answer : (i) cold. *

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : Which gauge is used to measure the height of rail at the time of aligning of rails for AT welding? (i) Height gauge.* (ii) Vertical gauge (iii) Horizontal gauge (iv) As decided by site supervisor

Last Answer : (iv) As decided by site supervisor

Description : hat action to be taken if slag is not separated within 20 ± 3 seconds? (i) Tap inside. (ii) Tap outside * (iii) Good reaction (iv) Tap well in time

Last Answer : ii) Tap outside *

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*