What is the time of removal the tensor from the newly executed A T Weld?
(i) 15 minutes after pouring.
(ii) 20 minutes after pouring*
(iii) 25 minutes after pouring.
(iv) 30 minutes after pouring.

1 Answer

Answer :

(ii) 20 minutes after pouring*

Related questions

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : Marking on weld should be done which side? (i) Non gauge face side of A.T. weld * (ii) Gauge face side of A.T. weld (iii) On web of non gauge face side of A.T. weld (iv) On web of gauge face side of A.T. weld

Last Answer : (i) Non gauge face side of A.T. weld

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : After declare good in USFD testing what is the joggling criteria ? (i) Joggle will be open from the AT weld* (ii) Joggling with two far end bolting (iii) joggling with four tight bold (iv) None of the above

Last Answer : (i) Joggle will be open from the AT weld*

Description : What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above

Last Answer : iii) With in the one month of welding*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Thickness of Lining/Charge is kept? (i) 20 mm. (ii) 25 mm* (iii) 30 mm (iv) As decided by the site supervisor

Last Answer : (ii) 25 mm*

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Tandem rig test with 450 probe for AT weld detects. (i) Horizontal longitudinal defect in weld. (ii) Vertical oriented defect in AT weld.* (iii) Transverse defect in AT weld. (iv) Defect in flange of AT welds.

Last Answer : (ii) Vertical oriented defect in AT weld.*

Description : By 00 probe in AT weld testing with normal gain setting. (i) Area below N.axis can be tested. (ii) Area below N.axis can not be tested.* (iii) Only web below N.axis can be tested. (iv) All above are correct.

Last Answer : (ii) Area below N.axis can not be tested.*

Description : 450 probe is used for detecting defect in; (i) FB weld (ii) AT weld (iii) FB weld, AT weld & SEJ (iv) All above*

Last Answer : (iv) All above*

Description : Trimming of AT weld should be done by ? (i) Chisel (ii) Trimmer* (iii) Both (iv) None of the above

Last Answer : ii) Trimmer*

Description : USFD testing of new AT weld will be done by ? (i) JE/SSE sectional (ii) Incharge SSE (iii) USFD machine operator* (iv) None of the above

Last Answer : (iv) None of the above

Description : Till USFD testing of new AT weld what is criteria for joggling ? (i) Joggling with two far end bold (ii) Joggling with two tight clamps* (iii) Leave without joggling till its testing (iv) None of the above

Last Answer : (ii) Joggling with two tight clamps*

Description : New AT weld should be entered in TMS by ? (i) Sectional JE/SSE* (ii) Incharge SSE (iii) Welder (iv) None of the above

Last Answer : (i) Sectional JE/SSE*

Description : Weather date of welding is marked on weld? (i) Yes (ii) As decided by the site supervisor (iii) No* (iv) None of the above

Last Answer : (iii) No*

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : Main advantage of 3-piece P F Mould is? (i) To overcome fin defect.* (ii) To prevent the flaw of molten metal (iii) To make proper weld size (iv) None to the above

Last Answer : (i) To overcome fin defect.*

Description : Defect of High joint is due to ? (i) Early trimming of weld (ii) Excess provision of height during alignment.* (iii) Early grinding of weld (iv) None of above

Last Answer : (ii) Excess provision of height during alignment.

Description : Defect of low joint is due to? (i) Excess height (ii) Early trimming of weld (iii) Early grinding of weld (iv) Nil/Less provision of height during alignment.

Last Answer : (iv) Nil/Less provision of height during alignment.

Description : Defect of cracks in weld is mainly due to? (i) Early opening of mould.* (ii) Early trimming of weld (iii) Early grinding of weld (iv) None of above

Last Answer : (i) Early opening of mould.*

Description : Full form of SPW? (i) Special pre heated weld (ii) Short preheated weld.* (iii) Short post heated weld (iv) None of above

Last Answer : (ii) Short preheated weld.*

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : Finishing tolerances are measured by? (i) On 30 cm scale (ii) 1 MT straightedge or 10 CM straightedge.* (iii) On 15 cm straight edge (iv) On 30 cm straight edge

Last Answer : (ii) 1 MT straightedge or 10 CM straightedge.*

Description : Normal Reaction time in SPW technique? (i) 17 ± 3 seconds. (ii) 15 ± 3 seconds (iii) 23 ± 3 seconds (iv) 20 ± 3 seconds*

Last Answer : (iv) 20 ± 3 seconds*

Description : Distance between the two detonators should be (i) 15 Mt. (ii) 10 Mt.* (iii) 20 Mt (iv) None of the above

Last Answer : (ii) 10 Mt.*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : What is mould waiting time? (i) 3 to 5 minutes. (ii) 4 to 6 minutes* (iii) 3.5 to 5.5 minutes (iv) 4.5 to 6.5 minuteses

Last Answer : (ii) 4 to 6 minutes*

Description : Heating time with compressed air and petrol in SPW is ? (i) 4.0 to 4.5 minutes.* (ii) 4.0 to 5 minutes (iii) 5.0 to 5.5 minutes (iv) 5.5 to 6 minutes

Last Answer : (i) 4.0 to 4.5 minutes.*

Description : What is the heating time in OXY & LPG in SPW? (i) 2.0 - 3.5 minutes. (ii) 2.0 - 3.0 minutes. (iii) 2.0 - 2.5 minutes.* (iv) 3.0 - 4.5 minutes.

Last Answer : iii) 2.0 - 2.5 minutes

Description : What is the function of Zircon wash? (i) To maintain good quality of weld (ii)To achieve good finish of the weld surface.* (ii) Both above are correct (iv) Both are incorrect

Last Answer : (ii)To achieve good finish of the weld surface.*

Description : When was the collar painting done ? (i) After the welding * (ii) after one week of welding (iii) After 15 days of welding (iv) None of the above

Last Answer : (i) After the welding *

Description : Name the paint used in A.T. Welding painting? (i) Black Paint (ii) Bituminous black IS:9862-1981.* (iii) Any type of black paint (iv) None of the above

Last Answer : (ii) Bituminous black IS:9862-1981.*

Description : Name the material which is separated from molten steel during chemical reaction of A.T welding? (i) Aluminium oxide (slag). * (ii) Ferrous Oxide (iii) Aluminium (iv) Ferrous

Last Answer : (i) Aluminium oxide (slag). *

Description : Ist detonator is planted at a distance of (i) 1200 Mt. from welding site .* (ii) 600 mtrs from welding site (iii) 30 mtrs from welding site (iv) None of the above

Last Answer : (i) 1200 Mt. from welding site .*

Description : Banner flag is planted at a distance of (i) At the site of work (ii) At 1200 mtrs from welding site (iii) At 30 mtrs from welding site (iv) 600 Mt. from welding site .*

Last Answer : iv) 600 Mt. from welding site .

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : Height of crucible is kept from top surface of mould? (i) 30 mm (ii) 40 mm (iii) 50 mm* (iv) 60 mm

Last Answer : (iii) 50 mm*