Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be?  (i) ± 0.4 mm   (ii) ± 0.1 mm   (iii) ± 0.2 mm   (iv) ± 0.3 mm*

1 Answer

Answer :

iv) ± 0.3 mm*

Related questions

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : Finishing tolerances are measured by? (i) On 30 cm scale (ii) 1 MT straightedge or 10 CM straightedge.* (iii) On 15 cm straight edge (iv) On 30 cm straight edge

Last Answer : (ii) 1 MT straightedge or 10 CM straightedge.*

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : Marking on weld should be done which side? (i) Non gauge face side of A.T. weld * (ii) Gauge face side of A.T. weld (iii) On web of non gauge face side of A.T. weld (iv) On web of gauge face side of A.T. weld

Last Answer : (i) Non gauge face side of A.T. weld

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : In new Rail as well as second hand rails how much end bends of the rails in lateral direction are permitted when checked with one metre straight edge before welding? (i) ± 0.2 mm in lateral direction (ii) ± 0.3 mm in lateral direction (iii) ± 0.5 mm in latera

Last Answer : (iii) ± 0.5 mm in latera

Description : How much rail ends are cleaned with Kerosene Oil and steel wire brush? (i) Minimum 100 mm both side (ii) Minimum 50 mm both side.* (iii) No need (iv) As decided by site supervisor

Last Answer : (ii) Minimum 50 mm both side.*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : Which gauge is used to measure the height of rail at the time of aligning of rails for AT welding? (i) Height gauge.* (ii) Vertical gauge (iii) Horizontal gauge (iv) As decided by site supervisor

Last Answer : (iv) As decided by site supervisor

Description : Which gauge is used to measure finishing tolerances . (i) Tilted gauge (ii) Filter gauge (iii) Meter gauge (iv) Filler gauge.*

Last Answer : (iv) Filler gauge.*

Description : Centre to Centre spacing of formation for double railway line for Broad Gauge is a) 1676 mm b) 4725 mm c) 4265mm d) 5300 mm*

Last Answer : d) 5300 mm*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : The gap between probing face and probing shoe should be. (i) 0.4 mm (ii) 0.2mm * (iii) 3mm (iv) 1mm.

Last Answer : (ii) 0.2mm *

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : What is the speed restriction to be observed for train passing? (i) Necessary speed restriction shall be observed until the grinding operation is over.* (ii) 30KMPH (iii) 45 KMPH (iv) Not required

Last Answer : (i) Necessary speed restriction shall be observed until the grinding operation is over.*

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : What is the dia of thimble ? (i) 14-16 mm (ii) 16-18 mm* (iii) 18-20 mm (iv) None of the above

Last Answer : (ii) 16-18 mm*

Description : Thickness of Lining/Charge is kept? (i) 20 mm. (ii) 25 mm* (iii) 30 mm (iv) As decided by the site supervisor

Last Answer : (ii) 25 mm*

Description : Height of crucible is kept from top surface of mould? (i) 30 mm (ii) 40 mm (iii) 50 mm* (iv) 60 mm

Last Answer : (iii) 50 mm*

Description : To take care of differential cooling rail ends of 72 UTS rails are lifted by? (i) 1 to 1.5 mm (ii) 1 to 2 mm (iii) 2 to 2.5 mm (iv) 3 to 4 mm *

Last Answer : iv) 3 to 4 mm *

Description : To take care of differential cooling rail ends of 90 UTS rails are lifted by? (i) 1 mm (ii) 2 mm (iii) 2 to 2.2 mm.* (iv) 1 to 2 mm

Last Answer : (iii) 2 to 2.2 mm.*

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*

Description : Stop boards on either side of approaches of all unmanned level crossings shall be provided at -------------from the centre line of nearest track. a) 3meters b) 5 meters* c) 6 meters d) 10 meters

Last Answer : b) 5 meters*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : nternal diameter of thimble in conventional type of crucible is? (i) 14-16 mm (i) 16-18 mm (iii) 18-20 mm* (iv) 20-22 mm

Last Answer : (iii) 18-20 mm*

Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters

Last Answer : a) 5 meters*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : What is the standard distance between lines in Broad Gauge a. 1670 mm b. 1676 mm* c. 1665 mm d. 1680 mm

Last Answer : b. 1676 mm*

Description : The minimum edge distance for rivets of diameter ‘d’ in steel plates shall be a) 2 x d b) 3 x d c) 1.5 x d* d) 2.5 x d

Last Answer : c) 1.5 x d*

Description : The horizontal clearance of edge of foot over bridge structure from face of platform is a) 6525 mm b) 3660 mm* c) 5330 mm d) 5300 mm

Last Answer : b) 3660 mm*

Description : Addition gain of 10 db is used for testing. (i) ‘D’ marked rails on single lines. (ii) ‘D’ marked rails on double lines. (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.* (iv) None of above.

Last Answer : (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.*

Description : What is the app. Weight of 52 kg portion? (i) 10 kg (ii) 11 kg* (iii) 12 kg (iv) None of the above

Last Answer : (ii) 11 kg*

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : Distance between the two detonators should be (i) 15 Mt. (ii) 10 Mt.* (iii) 20 Mt (iv) None of the above

Last Answer : (ii) 10 Mt.*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : Heating time with compressed air and petrol in SPW is ? (i) 4.0 to 4.5 minutes.* (ii) 4.0 to 5 minutes (iii) 5.0 to 5.5 minutes (iv) 5.5 to 6 minutes

Last Answer : (i) 4.0 to 4.5 minutes.*

Description : Pressure of compressed air is kept during preheating by CAPS? (i) 1 to 2 kg/cm2 (ii) .1 to .2 kg/cm2 (iii) 2 to 3 kg/cm2 (iv) 0.2 to 0.3 kg/cm2*

Last Answer : (iv) 0.2 to 0.3 kg/cm2*

Description : What is the heating time in OXY & LPG in SPW? (i) 2.0 - 3.5 minutes. (ii) 2.0 - 3.0 minutes. (iii) 2.0 - 2.5 minutes.* (iv) 3.0 - 4.5 minutes.

Last Answer : iii) 2.0 - 2.5 minutes

Description : Torch is kept at height from top surface of rail head? (i) 30 to 55 mm (ii) 35 to 40 mm (iii) 40 to 45 mm

Last Answer : (iii) 40 to 45 mm

Description : For high level flush the nominal dia of flush pipe shall be (a) 32 mm* (b) 40 mm (c) 25 mm (d) None of these

Last Answer : a) 32 mm*