How many nos. of sleepers should be loosened either side of the proposed weld?  (i) 3 sleepers
 (ii) 5 sleepers.*
 (iii) 2 sleepers
 (iv) 4 sleepers

1 Answer

Answer :

(ii) 5 sleepers.

Related questions

Description : In M+7 sleeper density, how many sleepers are there in a km Track. a. 1660 nos b. 1540 nos.* c. 1310 nos. d. 1440 nos.

Last Answer : b. 1540 nos

Description : Marking on weld should be done which side? (i) Non gauge face side of A.T. weld * (ii) Gauge face side of A.T. weld (iii) On web of non gauge face side of A.T. weld (iv) On web of gauge face side of A.T. weld

Last Answer : (i) Non gauge face side of A.T. weld

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Tandem rig test with 450 probe for AT weld detects. (i) Horizontal longitudinal defect in weld. (ii) Vertical oriented defect in AT weld.* (iii) Transverse defect in AT weld. (iv) Defect in flange of AT welds.

Last Answer : (ii) Vertical oriented defect in AT weld.*

Description : By 00 probe in AT weld testing with normal gain setting. (i) Area below N.axis can be tested. (ii) Area below N.axis can not be tested.* (iii) Only web below N.axis can be tested. (iv) All above are correct.

Last Answer : (ii) Area below N.axis can not be tested.*

Description : 450 probe is used for detecting defect in; (i) FB weld (ii) AT weld (iii) FB weld, AT weld & SEJ (iv) All above*

Last Answer : (iv) All above*

Description : Trimming of AT weld should be done by ? (i) Chisel (ii) Trimmer* (iii) Both (iv) None of the above

Last Answer : ii) Trimmer*

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : USFD testing of new AT weld will be done by ? (i) JE/SSE sectional (ii) Incharge SSE (iii) USFD machine operator* (iv) None of the above

Last Answer : (iv) None of the above

Description : After declare good in USFD testing what is the joggling criteria ? (i) Joggle will be open from the AT weld* (ii) Joggling with two far end bolting (iii) joggling with four tight bold (iv) None of the above

Last Answer : (i) Joggle will be open from the AT weld*

Description : What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above

Last Answer : iii) With in the one month of welding*

Description : Till USFD testing of new AT weld what is criteria for joggling ? (i) Joggling with two far end bold (ii) Joggling with two tight clamps* (iii) Leave without joggling till its testing (iv) None of the above

Last Answer : (ii) Joggling with two tight clamps*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : New AT weld should be entered in TMS by ? (i) Sectional JE/SSE* (ii) Incharge SSE (iii) Welder (iv) None of the above

Last Answer : (i) Sectional JE/SSE*

Description : Weather date of welding is marked on weld? (i) Yes (ii) As decided by the site supervisor (iii) No* (iv) None of the above

Last Answer : (iii) No*

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Main advantage of 3-piece P F Mould is? (i) To overcome fin defect.* (ii) To prevent the flaw of molten metal (iii) To make proper weld size (iv) None to the above

Last Answer : (i) To overcome fin defect.*

Description : Defect of High joint is due to ? (i) Early trimming of weld (ii) Excess provision of height during alignment.* (iii) Early grinding of weld (iv) None of above

Last Answer : (ii) Excess provision of height during alignment.

Description : Defect of low joint is due to? (i) Excess height (ii) Early trimming of weld (iii) Early grinding of weld (iv) Nil/Less provision of height during alignment.

Last Answer : (iv) Nil/Less provision of height during alignment.

Description : Defect of cracks in weld is mainly due to? (i) Early opening of mould.* (ii) Early trimming of weld (iii) Early grinding of weld (iv) None of above

Last Answer : (i) Early opening of mould.*

Description : Full form of SPW? (i) Special pre heated weld (ii) Short preheated weld.* (iii) Short post heated weld (iv) None of above

Last Answer : (ii) Short preheated weld.*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : What is the function of Zircon wash? (i) To maintain good quality of weld (ii)To achieve good finish of the weld surface.* (ii) Both above are correct (iv) Both are incorrect

Last Answer : (ii)To achieve good finish of the weld surface.*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : How much rail ends are cleaned with Kerosene Oil and steel wire brush? (i) Minimum 100 mm both side (ii) Minimum 50 mm both side.* (iii) No need (iv) As decided by site supervisor

Last Answer : (ii) Minimum 50 mm both side.*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : Number of Elastic clips used for one K to BG single line section having 13 length & concrete sleepers of M+7 sleeper density are (a) 5280 (b) 6160* (c) 6250 (d) 6500

Last Answer : (b) 6160*

Description : Number of sleepers required having sleeper density of M+7 for one Km of BG single line is (a) 1360 (b) 1540* (c) 1660 (d) None of the above

Last Answer : (b) 1540*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Sleeper density for group ‘A’ route with traffic density more than 20 GMT is:- (a) 1560 sleepers/ Km. (b) 1660 sleepers/ Km.* (c) 1540 sleepers/ Km. (d) 1340 sleepers/ Km.

Last Answer : (b) 1660 sleepers/ Km.*