In practice, which Life Cycle model may have more, fewer or different levels of
development and testing, depending on the project and the software product. For
example, there may be component integration testing after component testing, andsystem integration testing after system testing.
A. Water Fall Model
B.V-Model
C. Spiral Model
D. RAD Model

1 Answer

Answer :

B.V-Model

Related questions

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing after component testing, and

Last Answer : B.V-Model

Description : This life cycle model is basically driven by schedule and budget risks This statement is best suited for A. Water fall model B. Spiral model C. Incremental model D. V-Model Q33. The bug tracking ... these phases for each bug. I. Phase injected II. Phase detected III. Phase fixed IV. Phase removed

Last Answer : B. I, II and IV

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Check the technical accuracy of the document

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing

Description : Integration testing where no incremental testing takes place prior to all the system’s components being combined to form the system. A. System testing B. Component Testing C. Incremental Testing D. Big bang testing

Last Answer : D. Big bang testing

Description : Which of the following is not a type of test under phases in testing life cycle? A. Integration test B. Load test C. User Acceptance test D. Beta test

Last Answer : D. Beta test

Description : Regression testing should be performed: i. every week ii. after the software has changed iii. as often as possible iv. when the environment has changed v. when the project manager says a) i & ii are true, iii, iv & v are ... iv are true, i, iii & v are false d) ii is true, i, iii, iv & v are false

Last Answer : c) ii & iv are true, i, iii & v are false

Description : A test harness is a A. A high level document describing the principles, approach and major objectives of the organization regarding testing B. A distance set of test activities collected into a manageable phase ... conduct a test D. A set of several test cases for a component or system under test

Last Answer : C. A test environment comprised of stubs and drives needed to conduct a test

Description : Repeated Testing of an already tested program, after modification, to discover any defects introduced or uncovered as a result of the changes in the software being tested or in another related or ... software component: a) Re Testing b) Confirmation Testing c) Regression Testing d) Negative Testing

Last Answer : c) Regression Testing

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : Big bang approach is related to A. Regression testing B. Inter system testingC. Re-testing D. Integration testing

Last Answer : D. Integration testing

Description : Which technique can be used to achieve input and output coverage? It can be applied to human input, input via interfaces to a system, or interface parameters in integration testing. A. Error Guessing B. Boundary Value Analysis C. Decision Table testing D. Equivalence partitioning

Last Answer : D. Equivalence partitioning

Description : Which technique can be used to achieve input and output coverage? It can be applied to human input, input via interfaces to a system, or interface parameters in integration testing. a) Error Guessing b) Boundary Value Analysis c) Decision Table testing d) Equivalence partitioning

Last Answer : d) Equivalence partitioning

Description : System test can begin when? I. The test team competes a three day smoke test and reports on the results to the system test phase entry meeting II. The development team provides software to the test team 3 business days prior ... . I and II only B. II and III only C. I and III only D. I, II and III

Last Answer : D. I, II and III

Description : V- model uses -------- test models a) Component testing, integration testing, system testing and acceptance testing b) alpha testing, beta testing , acceptance testing and user testing c) black box testing, white box testing and gray box testing

Last Answer : a

Description : Software testing activities should start A. As soon as the code is written B. During the design stage C. When the requirements have been formally documented D. As soon as possible in the development lifecycle

Last Answer : C. When the requirements have been formally documented

Description : Which of the following uses Impact Analysis most? a) Component testing b) Non-functional system testing c) User acceptance testing d) Maintenance testing

Last Answer : d) Maintenance testing

Description : Which of the following statements is true about a software verification and validation program? I. It strives to ensure that quality is built into software. II. It provides management with insights into the state ... software development activities. A. I, II&III B.II, III&IV C.I, II&IV D.I, III&IV

Last Answer : C.I, II&IV

Description : A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this projectmanager should be to A. Establish a relationship with ... the manager' s management style D. Ensure that the project proceeds at its current pace

Last Answer : B. Learn the project objectives and the existing project plan

Description : The spiral model of software development (A) Ends with the delivery of the software product (B) Is more chaotic than the incremental model (C) Includes project risks evaluation during each iteration (D) All of the above

Last Answer : (C) Includes project risks evaluation during each iteration

Description : Testing error messages fall under _________category of testing. A. Incremental Testing B. Thread Testing C. Documentation Testing D. Stress Testing

Last Answer : C. Documentation Testing

Description : In data flow testing, objective is to find A. All dc-paths that are not du-paths B. V All du-paths C. All du-paths that are not dc-paths D. All dc-paths

Last Answer : C. All du-paths that are not dc-paths

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : For final software acceptance testing, the system should include A. Delivered software B. All user documents C. Final version of oth

Last Answer : D. All of the above

Description : Which of the following will be the best definition for Testing :- a) The goal / purpose of testing is to demonstrate that the program works. b) The purpose of testing is to demonstrate that the ... does what it is supposed to do. d) Testing is executing Software for the purpose of finding defects.

Last Answer : d) Testing is executing Software for the purpose of finding defects.

Description : Testing of software used to convert data from existing systems for use in replacement systems A. Data driven testing B. Migration testing C. Configuration testing D. Back to back testing

Last Answer : B. Migration testing

Description : Which testing methods are used by end-users who actually test software before they use it? A. Alpha & Beta Testing B. White Box Testing C. Black Box Testing D. Trial & Error Testing

Last Answer : A. Alpha & Beta Testing

Description : The purpose of software testing is to A. Demonstrate that the application works properly B. Detect the defects C. Validate the logical design

Last Answer : A. Demonstrate that the application works properly

Description : What is COTS? A. Commercial On-the-shelf software B. Commercial off-the-shelf software C. Common Offshore testing Software

Last Answer : B. Commercial off-the-shelf software

Description : We use the output of the requirement analysis, the requirement specification as the input for writing :- a) User Acceptance Test Cases b) Integration Level Test Cases c) Unit Level Test Cases d) Program specifications

Last Answer : a) User Acceptance Test Cases

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : Benefits of Independent Testing a) Independent testers are much more qualified than Developers b) Independent testers see other and different defects and are unbiased. c) Independent Testers cannot identify defects. d) Independent Testers can test better than developers

Last Answer : b) Independent testers see other and different defects and are unbiased.

Description : Impact Analysis helps to decide :- a) How much regression testing should be done. b) Exit Criteria c) How many more test cases need to written. d) Different Tools to perform Regression Testing

Last Answer : a) How much regression testing should be done.

Description : Use of an executable model to represent the behavior of an object is called A. Simulation B. Software item C. Software feature D. None of the above

Last Answer : A. Simulation

Description : Which of the following is a requirement of an effective software environment? I. Ease of use II. Capacity for incremental implementation III. Capability of evolving with the needs of a project IV. Inclusion of advanced tools A.I, II &III B.I, II &IV C.II, III&IV D.I, III&IV

Last Answer : A.I, II &III

Description : Acceptance testing means A. Testing performed on a single stand - alone module or unit of code B. Testing after changes have been made to ensure that no unwanted changes were introduced C. ... the needs of the organization and end user. D. Users test the application in the developers environment

Last Answer : C. Testing to ensure that the system meets the needs of the organization and end user.

Description : Defects are least costly to correct at what stage of the development cycle? A. Requirements B. Analysis & Design C. Construction D. Implementation

Last Answer : A. Requirements

Description : UAT is different from other testing types normally because of A. Data B. Cycles C. Defects D. None of the above

Last Answer : A. Data

Description : Defect Density' calculated in terms of A. The number of defects identified in a component or system divided by the size of the component or the system B. The number of defects found by a test phase ... The number of defects found by a test phase divided by the number found by the size of the system

Last Answer : A. The number of defects identified in a component or system divided by the size of the component or the system

Description : In preparation for developing the acceptance criteria, the user should A. Know the defects in the application B. Acquire the basic knowledge of the application for which the system is ... D. Know new enhancement and basic understanding of how the application is implemented in users organization

Last Answer : Understand the risks and benefits of the development methodology that is to be used in correcting the software system

Description : Functional system testing is: a) testing that the system functions with other systems b) testing that the components that comprise the system function together c) testing the end to end functionality of the system as a whole d) testing the system performs functions within specified response times

Last Answer : c) testing the end to end functionality of the system as a whole

Description : The primary goal of comparing a user manual with the actual behavior of the running program during system testing is to A. Find bugs in the program B. Check the technical accuracy of the document

Last Answer : B. Check the technical accuracy of the document

Description : When testing a grade calculation system, a tester determines that all scores from 90 to 100 will yield a grade of A, but scores below 90 will not. This analysis is known as: A. Equivalence partitioning B. Boundary value analysis C. Decision table D. Hybrid analysis

Last Answer : A. Equivalence partitioning

Description : When testing a grade calculation system, a tester determines that all scores from 90 to 100 will yield a grade of A, but scores below 90 will not. This analysis is known as: A. Equivalence partitioning B. Boundary value analysis C. Decision table D. Hybrid analysis

Last Answer : B. Boundary value analysis

Description : COTS is known as A. Commercial off the shelf sA. Sanity testing B. System testing C. Smoke testing D. Regression testing

Last Answer : C. Smoke testing

Description : The selection of test cases for regression testing A. Requires knowledge on the bug fixes and how it affect the system B. Includes the area of frequent defects C. Includes the area which has undergone many/recent code changes D. All of the above

Last Answer : D. All of the above