Regression testing should be performed:
i. every week
ii. after the software has changed
iii. as often as possible
iv. when the environment has changed
v. when the project manager says
a) i & ii are true, iii, iv & v are false
b) ii, iii & iv are true, i & v are false
c) ii & iv are true, i, iii & v are false
d) ii is true, i, iii, iv & v are false

1 Answer

Answer :

c) ii & iv are true, i, iii & v are false

Related questions

Description : Which of the following statements is true about a software verification and validation program? I. It strives to ensure that quality is built into software. II. It provides management with insights into the state ... software development activities. A. I, II&III B.II, III&IV C.I, II&IV D.I, III&IV

Last Answer : C.I, II&IV

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : Which of the following is a requirement of an effective software environment? I. Ease of use II. Capacity for incremental implementation III. Capability of evolving with the needs of a project IV. Inclusion of advanced tools A.I, II &III B.I, II &IV C.II, III&IV D.I, III&IV

Last Answer : A.I, II &III

Description : Consider the following statements: i. 100% statement coverage guarantees 100% branch coverage. ii. 100% branch coverage guarantees 100% statement coverage. iii. 100% branch coverage guarantees 100% decision coverage. iv. 100% decision ... & v are False d) ii, iii & iv are True; i & v are False

Last Answer : d) ii, iii & iv are True; i & v are False

Description : Which of the following helps in monitoring the Test Progress:- i. Percentage of Test Case Execution ii. Percentage of work done in test environment preparation. iii. Defect Information e.g. defect density, ... ii,iii are correct and iv is incorrect c) i,ii are correct and iii,iv are incorrect

Last Answer : b) i,ii,iii are correct and iv is incorrect

Description : Repeated Testing of an already tested program, after modification, to discover any defects introduced or uncovered as a result of the changes in the software being tested or in another related or ... software component: a) Re Testing b) Confirmation Testing c) Regression Testing d) Negative Testing

Last Answer : c) Regression Testing

Description : Acceptance testing means A. Testing performed on a single stand - alone module or unit of code B. Testing after changes have been made to ensure that no unwanted changes were introduced C. ... the needs of the organization and end user. D. Users test the application in the developers environment

Last Answer : C. Testing to ensure that the system meets the needs of the organization and end user.

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing ... after system testing. A. Water Fall Model B.V-Model C. Spiral Model D. RAD Model

Last Answer : B.V-Model

Description : Which of the following is a part of Test Closure Activities? i. Checking which planned deliverables have been delivered ii. Defect report analysis. iii. Finalizing and archiving testware. iv. Analyzing lessons. a) i , ii , ... false c) i , iii , iv are true and ii is false d) All of above are true

Last Answer : c) i , iii , iv are true and ii is false

Description : Validation involves which of the following: i. Helps to check the Quality of the Built Product ii. Helps to check that we have built the right product. iii. Helps in developing the product iv. Monitoring tool wastage and ... , ii, iii are true and iv is false d) iii is true and i, ii, iv are false

Last Answer : b) ii is true and i, iii, iv are false

Description : Which of the following functions is typically supported by a software quality information system? I. Record keeping II. System design III. Evaluation scheduling IV. Error reporting A.I, II&III B.II, III &IV C.I, III &IV D.I, II & IV

Last Answer : C.I, III &IV

Description : Exit Criteria may consist of :- i. Thoroughness measures , such as coverage of code, functionality or risk ii. Estimates of Defect density or reliability measures. iii. Residual risk such as defects not fixed or ... correct and i,ii,iii are incorrect d) iii and iv are correct and i,ii are incorrect

Last Answer : b) i,ii,iii is correct and iv is incorrect

Description : Impact Analysis helps to decide :- a) How much regression testing should be done. b) Exit Criteria c) How many more test cases need to written. d) Different Tools to perform Regression Testing

Last Answer : a) How much regression testing should be done.

Description : Big bang approach is related to A. Regression testing B. Inter system testingC. Re-testing D. Integration testing

Last Answer : D. Integration testing

Description : COTS is known as A. Commercial off the shelf sA. Sanity testing B. System testing C. Smoke testing D. Regression testing

Last Answer : C. Smoke testing

Description : The testing attempts to violate those procedures, which should test the adequacy of the security procedures. A. Disaster testing B. Functional testing C. Regression testing D. Compliance testing

Last Answer : D. Compliance testing

Description : The selection of test cases for regression testing A. Requires knowledge on the bug fixes and how it affect the system B. Includes the area of frequent defects C. Includes the area which has undergone many/recent code changes D. All of the above

Last Answer : D. All of the above

Description : This life cycle model is basically driven by schedule and budget risks This statement is best suited for A. Water fall model B. Spiral model C. Incremental model D. V-Model Q33. The bug tracking ... these phases for each bug. I. Phase injected II. Phase detected III. Phase fixed IV. Phase removed

Last Answer : B. I, II and IV

Description : System test can begin when? I. The test team competes a three day smoke test and reports on the results to the system test phase entry meeting II. The development team provides software to the test team 3 business days prior ... . I and II only B. II and III only C. I and III only D. I, II and III

Last Answer : D. I, II and III

Description : A test harness is a A. A high level document describing the principles, approach and major objectives of the organization regarding testing B. A distance set of test activities collected into a manageable phase ... conduct a test D. A set of several test cases for a component or system under test

Last Answer : C. A test environment comprised of stubs and drives needed to conduct a test

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing after component testing, and

Last Answer : B.V-Model

Description : A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this projectmanager should be to A. Establish a relationship with ... the manager' s management style D. Ensure that the project proceeds at its current pace

Last Answer : B. Learn the project objectives and the existing project plan

Description : Drivers are also known as: i. Spade ii. Test harness iii. Scaffolding a) i , ii are true and iii is false b) i , iii are true and ii is false

Last Answer : c) ii , iii are true and i is false

Description : Verification performed without any executable code is referred to as A. Review B. Static testing C. Validation D. Sanity testing

Last Answer : B. Static testing

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : A test manager wants to use the resources available for the automated testing of a web application. The best choice is A. Test automater, web specialist, DBA, test lead B. Tester, test automater, web ... C. Tester, test lead, test automater, DBA D. Tester, web specialist, test lead, test automater

Last Answer : B. Tester, test automater, web specialist, DBA

Description : Software testing activities should start A. As soon as the code is written B. During the design stage C. When the requirements have been formally documented D. As soon as possible in the development lifecycle

Last Answer : C. When the requirements have been formally documented

Description : Defects discovered by static analysis tools include: i. Variables that are never used. ii. Security vulnerabilities. iii. Programming Standard Violations iv. Uncalled functions and procedures a) i , ii,iii,iv is correct b ... ,iv are incorrect. c) i ,ii, iii and iv are incorrect d) iv, ii is correct

Last Answer : a) i , ii,iii,iv is correct

Description : Success Factors for a review include: i. Each Review does not have a predefined objective ii. Defects found are welcomed and expressed objectively iii. Management supports a good review process. iv. There is an emphasis on ... and ii is incorrect c) i , iii , iv , ii is in correct d) ii is correct

Last Answer : a) ii,iii,iv are correct and i is incorrect

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester or developer IV. Dependencies of the change request.

Last Answer : A. Improve super vision, More reviews of artifacts or program means stage containment of the defects.

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester ... and IV B. I, II and III C. II, III and IV D. I, II and IV

Last Answer : D. I, II and IV

Description : Recovery Testing aims at verifying the system's ability to recover from varying degrees of failure. A. True B. False

Last Answer : A. True

Description : Which testing methods are used by end-users who actually test software before they use it? A. Alpha & Beta Testing B. White Box Testing C. Black Box Testing D. Trial & Error Testing

Last Answer : A. Alpha & Beta Testing

Description : Sources of regression test cases are A. Boundary tests and other pre planned tests. B. Tests that reveal bugs in the program C. Customer reported bugs D. All of the above

Last Answer : D. All of the above

Description : . One of the more daunting challenges of managing a test project is that so many dependencies converge at test execution. One missing configuration file or hard ware device can render all your test results ... incident? A. Test managers faults only B. Test lead faults only C. Test manager and proj

Last Answer : A. Test managers faults only

Description : The following defines the statement of what the tester is expected to accomplish or validate during testing activity A. Test scope B. Test objective C. Test environment D. None of the above

Last Answer : B. Test objective

Description : Which is not the responsibility of customer/ user of the software A. Plan how and by whom each acceptance activity will be performed B. Prepare the acceptance plan C. Prepare resource plan D. Plan resources for providing information on which to base acceptance decisions

Last Answer : C. Prepare resource plan

Description : In data flow testing, objective is to find A. All dc-paths that are not du-paths B. V All du-paths C. All du-paths that are not dc-paths D. All dc-paths

Last Answer : C. All du-paths that are not dc-paths

Description : State which of the one is false A. In performance testing, usage of tool is a must B. In database testing, database knowledge is a must. C. In Functional Testing, knowledge of business logic is a must D. None of the above.

Last Answer : D. None of the above.

Description : Which of the following will be the best definition for Testing :- a) The goal / purpose of testing is to demonstrate that the program works. b) The purpose of testing is to demonstrate that the ... does what it is supposed to do. d) Testing is executing Software for the purpose of finding defects.

Last Answer : d) Testing is executing Software for the purpose of finding defects.

Description : Testing of software used to convert data from existing systems for use in replacement systems A. Data driven testing B. Migration testing C. Configuration testing D. Back to back testing

Last Answer : B. Migration testing

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Check the technical accuracy of the document

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing