You are the test manager and you are about the start the system testing. The
developer team says that due to change in requirements they will be able to deliver
the system to you for testing 5 working days after the due date. You can not change
the resources(work hours, test tools, etc.) What steps you will take to be able to finish
the testing in time.
A. Tell to the development team to deliver the system in time so that testing activity will be finish
in time.
B. Extend the testing plan, so that you can accommodate the slip going to occur
C. Rank the functionality as per risk and concentrate more on critical functionality testing
D. Add more resources so that the slippage should be avoided

1 Answer

Answer :

B. Extend the testing plan, so that you can accommodate the slip going to occur

Related questions

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : System test can begin when? I. The test team competes a three day smoke test and reports on the results to the system test phase entry meeting II. The development team provides software to the test team 3 business days prior ... . I and II only B. II and III only C. I and III only D. I, II and III

Last Answer : D. I, II and III

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : A test manager wants to use the resources available for the automated testing of a web application. The best choice is A. Test automater, web specialist, DBA, test lead B. Tester, test automater, web ... C. Tester, test lead, test automater, DBA D. Tester, web specialist, test lead, test automater

Last Answer : B. Tester, test automater, web specialist, DBA

Description : Regression testing should be performed: i. every week ii. after the software has changed iii. as often as possible iv. when the environment has changed v. when the project manager says a) i & ii are true, iii, iv & v are ... iv are true, i, iii & v are false d) ii is true, i, iii, iv & v are false

Last Answer : c) ii & iv are true, i, iii & v are false

Description : Exit Criteria may consist of :- i. Thoroughness measures , such as coverage of code, functionality or risk ii. Estimates of Defect density or reliability measures. iii. Residual risk such as defects not fixed or ... correct and i,ii,iii are incorrect d) iii and iv are correct and i,ii are incorrect

Last Answer : b) i,ii,iii is correct and iv is incorrect

Description : Acceptance tests are normally conducted by the A. Developer B. End usersC. Test team D. Systems engineers

Last Answer : B. End users

Description : Software testing activities should start A. As soon as the code is written B. During the design stage C. When the requirements have been formally documented D. As soon as possible in the development lifecycle

Last Answer : C. When the requirements have been formally documented

Description : Acceptance requirements that a system should meet is A. Usability B. Understandability C. Functionality D. Enhancements

Last Answer : C. Functionality

Description : _________must be developed to describe when and how testing will occur. A. Test Strategy B. Test Plan C. Test Design D. High Level document

Last Answer : B. Test Plan

Description : Functional system testing is: a) testing that the system functions with other systems b) testing that the components that comprise the system function together c) testing the end to end functionality of the system as a whole d) testing the system performs functions within specified response times

Last Answer : c) testing the end to end functionality of the system as a whole

Description : : Load Testing Tools _______ A. Reduces the time spent by the testers B. Reduces the resources spent like hardware C. Are mostly used in web testing D. All of the above

Last Answer : D. All of the above

Description : Coverage based analysis is best described as: A. A metric used to show the logic covered during a test session providing insight to the extent of testing. B. A tool for documenting the unique ... their status through to resolution. D. The most traditional means for analyzing a system or a program

Last Answer : A. A metric used to show the logic covered during a test session providing insight to the extent of testing.

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : Impact Analysis helps to decide :- a) How much regression testing should be done. b) Exit Criteria c) How many more test cases need to written. d) Different Tools to perform Regression Testing

Last Answer : a) How much regression testing should be done.

Description : Which of the following helps in monitoring the Test Progress:- i. Percentage of Test Case Execution ii. Percentage of work done in test environment preparation. iii. Defect Information e.g. defect density, ... ii,iii are correct and iv is incorrect c) i,ii are correct and iii,iv are incorrect

Last Answer : b) i,ii,iii are correct and iv is incorrect

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester or developer IV. Dependencies of the change request.

Last Answer : A. Improve super vision, More reviews of artifacts or program means stage containment of the defects.

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester ... and IV B. I, II and III C. II, III and IV D. I, II and IV

Last Answer : D. I, II and IV

Description : . One of the more daunting challenges of managing a test project is that so many dependencies converge at test execution. One missing configuration file or hard ware device can render all your test results ... incident? A. Test managers faults only B. Test lead faults only C. Test manager and proj

Last Answer : A. Test managers faults only

Description : Change X requires a higher level of authority than Change Y in which of the following pairs? Change X Change Y A. Code in development Code in production B. Specifications during requirements ... Documents requested by customers D. A product distributed to several sites A product with a single user

Last Answer : D. A product distributed to several sites A product with a single user

Description : In case of Large Systems :- a) Only few tests should be run b) Testing should be on the basis of Risk c) Only Good Test Cases should be executed. d) Test Cases written by good test engineers should be executed.

Last Answer : b) Testing should be on the basis of Risk

Description : Which is not the responsibility of customer/ user of the software A. Plan how and by whom each acceptance activity will be performed B. Prepare the acceptance plan C. Prepare resource plan D. Plan resources for providing information on which to base acceptance decisions

Last Answer : C. Prepare resource plan

Description : The following defines the statement of what the tester is expected to accomplish or validate during testing activity A. Test scope B. Test objective C. Test environment D. None of the above

Last Answer : B. Test objective

Description : A test plan defines A. What is selected for testing B. Objectives and results C. Expected results D. Targets and misses

Last Answer : B. Objectives and results

Description : Test Plan A. Road map for testing B. Tells about the actual results and expected results C. Both A and B D. None of the above

Last Answer : A. Road map for testing

Description : Testing Process comprised of A. Test Plan and Test Cases B. Test log and Test Status C. Defect Tracking D. All of the above

Last Answer : D. All of the above

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing ... after system testing. A. Water Fall Model B.V-Model C. Spiral Model D. RAD Model

Last Answer : B.V-Model

Description : Acceptance testing means A. Testing performed on a single stand - alone module or unit of code B. Testing after changes have been made to ensure that no unwanted changes were introduced C. ... the needs of the organization and end user. D. Users test the application in the developers environment

Last Answer : C. Testing to ensure that the system meets the needs of the organization and end user.

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing after component testing, and

Last Answer : B.V-Model

Description : Evaluating testability of the requirements and system are a part of which phase:- a) Test Analysis and Design b) Test Planning and control c) Test Implementation and execution d) Evaluating ... text box which accepts alphabets in lower or upper case. Identify the invalid Equivalence class value.

Last Answer : a) Test Analysis and Design

Description : A project manager has been transferred to a major software development project that is in the implementation phase. The highest priority for this projectmanager should be to A. Establish a relationship with ... the manager' s management style D. Ensure that the project proceeds at its current pace

Last Answer : B. Learn the project objectives and the existing project plan

Description : A test harness is a A. A high level document describing the principles, approach and major objectives of the organization regarding testing B. A distance set of test activities collected into a manageable phase ... conduct a test D. A set of several test cases for a component or system under test

Last Answer : C. A test environment comprised of stubs and drives needed to conduct a test

Description : The selection of test cases for regression testing A. Requires knowledge on the bug fixes and how it affect the system B. Includes the area of frequent defects C. Includes the area which has undergone many/recent code changes D. All of the above

Last Answer : D. All of the above

Description : Defects are least costly to correct at what stage of the development cycle? A. Requirements B. Analysis & Design C. Construction D. Implementation

Last Answer : A. Requirements

Description : Which testing methods are used by end-users who actually test software before they use it? A. Alpha & Beta Testing B. White Box Testing C. Black Box Testing D. Trial & Error Testing

Last Answer : A. Alpha & Beta Testing

Description : “The tracing of requirements for a test level through the layers of a test documentation” done by A. Horizontal tracebility B. Depth tracebility C. Vertical tracebility D. Horizontal & Vertical tracebilities

Last Answer : A. Horizontal tracebility

Description : What is NOT a test log? A. Maps the test results to requirements B. Records test activities C. Maintains control over the test D. Contains pass or fail results.

Last Answer : A. Maps the test results to requirements

Description : Benefits of Independent Testing a) Independent testers are much more qualified than Developers b) Independent testers see other and different defects and are unbiased. c) Independent Testers cannot identify defects. d) Independent Testers can test better than developers

Last Answer : b) Independent testers see other and different defects and are unbiased.

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : Test charters are used in ________ testingA. Exploratory testing B. Usability testing C. Component testing D. Maintainability testing

Last Answer : A. Exploratory testing

Description : The testing attempts to violate those procedures, which should test the adequacy of the security procedures. A. Disaster testing B. Functional testing C. Regression testing D. Compliance testing

Last Answer : D. Compliance testing

Description : Decision to stop testing should be based upon A. Successful use of specific test case design methodologies B. A percentage of coverage for each coverage category C. Rate of error detection falls below a specified threshold D. All of the above

Last Answer : D. All of the above

Description : Alpha testing is differentiated from Beta testing by A. The location where the tests are conducted. B. The types of test conducted C. The people doing the testing D. The degree to which white box techniques are used

Last Answer : A. The location where the tests are conducted.

Description : Which of the following is not a type of test under phases in testing life cycle? A. Integration test B. Load test C. User Acceptance test D. Beta test

Last Answer : D. Beta test

Description : Test summary report A. Functional testing is mostly B. Validation techniques C. Verification techniques D. Both of the above E. None of the above

Last Answer : B. Validation techniques

Description : Features to be tested, approach, item pass/fail criteria and test deliverables should be specified in which document? a) Test case specification b) Test procedure specification c) Test plan d) Test design specification

Last Answer : c) Test plan

Description : Deliverables of test design phase include all the following except A. Test data B. Test data plan C. Test summary report D. Test procedure plan

Last Answer : C. Test summary report