project that is in the implementation phase. The highest priority for this projectmanager should be to
A. Establish a relationship with the customer
B. Learn the project objectives and the existing project plan
C. Modify the project’ s organizational structure to meet the manager’ s management style
D. Ensure that the project proceeds at its current pace