A project manager has been transferred to a major software development
project that is in the implementation phase. The highest priority for this projectmanager should be to
A. Establish a relationship with the customer
B. Learn the project objectives and the existing project plan
C. Modify the project’ s organizational structure to meet the manager’ s management style
D. Ensure that the project proceeds at its current pace

1 Answer

Answer :

B. Learn the project objectives and the existing project plan

Related questions

Description : Which of the following is a requirement of an effective software environment? I. Ease of use II. Capacity for incremental implementation III. Capability of evolving with the needs of a project IV. Inclusion of advanced tools A.I, II &III B.I, II &IV C.II, III&IV D.I, III&IV

Last Answer : A.I, II &III

Description : Regression testing should be performed: i. every week ii. after the software has changed iii. as often as possible iv. when the environment has changed v. when the project manager says a) i & ii are true, iii, iv & v are ... iv are true, i, iii & v are false d) ii is true, i, iii, iv & v are false

Last Answer : c) ii & iv are true, i, iii & v are false

Description : Which of the following is not phase of the Fundamental Test Process? a) Test Planning and Control b) Test implementation and Execution c) Requirement Analysis d) Evaluating Exit criteria and reporting

Last Answer : c) Requirement Analysis

Description : Evaluating testability of the requirements and system are a part of which phase:- a) Test Analysis and Design b) Test Planning and control c) Test Implementation and execution d) Evaluating ... text box which accepts alphabets in lower or upper case. Identify the invalid Equivalence class value.

Last Answer : a) Test Analysis and Design

Description : Defects are least costly to correct at what stage of the development cycle? A. Requirements B. Analysis & Design C. Construction D. Implementation

Last Answer : A. Requirements

Description : A test harness is a A. A high level document describing the principles, approach and major objectives of the organization regarding testing B. A distance set of test activities collected into a manageable phase ... conduct a test D. A set of several test cases for a component or system under test

Last Answer : C. A test environment comprised of stubs and drives needed to conduct a test

Description : . One of the more daunting challenges of managing a test project is that so many dependencies converge at test execution. One missing configuration file or hard ware device can render all your test results ... incident? A. Test managers faults only B. Test lead faults only C. Test manager and proj

Last Answer : A. Test managers faults only

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing ... after system testing. A. Water Fall Model B.V-Model C. Spiral Model D. RAD Model

Last Answer : B.V-Model

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing after component testing, and

Last Answer : B.V-Model

Description : Which of the following statements is true about a software verification and validation program? I. It strives to ensure that quality is built into software. II. It provides management with insights into the state ... software development activities. A. I, II&III B.II, III&IV C.I, II&IV D.I, III&IV

Last Answer : C.I, II&IV

Description : System test can begin when? I. The test team competes a three day smoke test and reports on the results to the system test phase entry meeting II. The development team provides software to the test team 3 business days prior ... . I and II only B. II and III only C. I and III only D. I, II and III

Last Answer : D. I, II and III

Description : What are the four attributes to be present in any test problem?A. Statement, criteria, effect and cause B. Priority, fix, schedule and report C. Statement, fix effect and report D. None of the above.

Last Answer : A. Statement, criteria, effect and cause

Description : Software testing activities should start A. As soon as the code is written B. During the design stage C. When the requirements have been formally documented D. As soon as possible in the development lifecycle

Last Answer : C. When the requirements have been formally documented

Description : Which of the following is not decided in the test-planning phase? A. Schedules and deliverables B. Hardware and software C. Entry and exit criteria D. Types of test cases

Last Answer : D. Types of test cases

Description : Which of the following has highest level of independence in which test cases are : a) Designed by persons who write the software under test b) Designed by a person from a different sectionc) Designed by a person from a different organization d) Designed by another person

Last Answer : c) Designed by a person from a different organization

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : A test manager wants to use the resources available for the automated testing of a web application. The best choice is A. Test automater, web specialist, DBA, test lead B. Tester, test automater, web ... C. Tester, test lead, test automater, DBA D. Tester, web specialist, test lead, test automater

Last Answer : B. Tester, test automater, web specialist, DBA

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : In preparation for developing the acceptance criteria, the user should A. Know the defects in the application B. Acquire the basic knowledge of the application for which the system is ... D. Know new enhancement and basic understanding of how the application is implemented in users organization

Last Answer : Understand the risks and benefits of the development methodology that is to be used in correcting the software system

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : The Kick Off phase of a formal review includes the following :- a) Explaining the objective b) Fixing defects found typically done by author c) Follow up d) Individual Meeting preparations

Last Answer : a) Explaining the objective

Description : This life cycle model is basically driven by schedule and budget risks This statement is best suited for A. Water fall model B. Spiral model C. Incremental model D. V-Model Q33. The bug tracking ... these phases for each bug. I. Phase injected II. Phase detected III. Phase fixed IV. Phase removed

Last Answer : B. I, II and IV

Description : Defect Density' calculated in terms of A. The number of defects identified in a component or system divided by the size of the component or the system B. The number of defects found by a test phase ... The number of defects found by a test phase divided by the number found by the size of the system

Last Answer : A. The number of defects identified in a component or system divided by the size of the component or the system

Description : Deliverables of test design phase include all the following except A. Test data B. Test data plan C. Test summary report D. Test procedure plan

Last Answer : C. Test summary report

Description : Which of the following will be the best definition for Testing :- a) The goal / purpose of testing is to demonstrate that the program works. b) The purpose of testing is to demonstrate that the ... does what it is supposed to do. d) Testing is executing Software for the purpose of finding defects.

Last Answer : d) Testing is executing Software for the purpose of finding defects.

Description : The structure of an incident report is covered in the Standard for Software Test Documentation IEEE 829 and is called as : - a) Anomaly Report b) Defect Report c) Test Defect Report d) Test Incident Report

Last Answer : a) Anomaly Report

Description : Repeated Testing of an already tested program, after modification, to discover any defects introduced or uncovered as a result of the changes in the software being tested or in another related or ... software component: a) Re Testing b) Confirmation Testing c) Regression Testing d) Negative Testing

Last Answer : c) Regression Testing

Description : Testing of software used to convert data from existing systems for use in replacement systems A. Data driven testing B. Migration testing C. Configuration testing D. Back to back testing

Last Answer : B. Migration testing

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Check the technical accuracy of the document

Description : A type of integration testing in which software elements, hardware elements, or both are combined all at once into a component or an overall system, rather than in stages. A. System Testing B. Big-Bang Testing C. Integration Testing D. Unit Testing

Last Answer : B. Big-Bang Testing

Description : Which of the following functions is typically supported by a software quality information system? I. Record keeping II. System design III. Evaluation scheduling IV. Error reporting A.I, II&III B.II, III &IV C.I, III &IV D.I, II & IV

Last Answer : C.I, III &IV

Description : Which of the following characteristics is primarily associated with software reusability? A. The extent to which the software can be used in other applications B. The extent to which the software can ... moved to a different platform D. The capability of one system to be coupled with another system

Last Answer : B. The extent to which the software can be used by many different users

Description : Which of the following software change management activities is most vital to assessing the impact of proposed software modifications? A. Baseline identification B. Configuration auditing C. Change control D. Version control

Last Answer : C. Change control

Description : COTS is known as A. Commercial off the shelf software B. Compliance of the software C. Change control of the software D. Capable off the shelf software

Last Answer : A. Commercial off the shelf software

Description : For final software acceptance testing, the system should include A. Delivered software B. All user documents C. Final version of oth

Last Answer : D. All of the above

Description : Which is not the responsibility of customer/ user of the software A. Plan how and by whom each acceptance activity will be performed B. Prepare the acceptance plan C. Prepare resource plan D. Plan resources for providing information on which to base acceptance decisions

Last Answer : C. Prepare resource plan

Description : Which testing methods are used by end-users who actually test software before they use it? A. Alpha & Beta Testing B. White Box Testing C. Black Box Testing D. Trial & Error Testing

Last Answer : A. Alpha & Beta Testing

Description : The purpose of software testing is to A. Demonstrate that the application works properly B. Detect the defects C. Validate the logical design

Last Answer : A. Demonstrate that the application works properly

Description : What is COTS? A. Commercial On-the-shelf software B. Commercial off-the-shelf software C. Common Offshore testing Software

Last Answer : B. Commercial off-the-shelf software

Description : Use of an executable model to represent the behavior of an object is called A. Simulation B. Software item C. Software feature D. None of the above

Last Answer : A. Simulation

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester or developer IV. Dependencies of the change request.

Last Answer : A. Improve super vision, More reviews of artifacts or program means stage containment of the defects.

Description : Change request should be submitted through development or program management. A change request must be written and should include the following criteria. I. Definition of the change II. Documentation to be updated III. Name of the tester ... and IV B. I, II and III C. II, III and IV D. I, II and IV

Last Answer : D. I, II and IV

Description : Change X requires a higher level of authority than Change Y in which of the following pairs? Change X Change Y A. Code in development Code in production B. Specifications during requirements ... Documents requested by customers D. A product distributed to several sites A product with a single user

Last Answer : D. A product distributed to several sites A product with a single user