Consider the following activities in a building construction:
 1. Concreting of roof slabs
 2. Brick-jelly lime concrete terracing
 3. Erection of form work for slab
 4. Construction of parapet wall in terrace
 The correct sequence of these activities is
(A) 1, 3, 2, 4
(B) 3, 1, 4, 2
(C) 3, 1, 2, 4
(D) 1, 3, 4, 2

1 Answer

Answer :

(C) 3, 1, 2, 4

Related questions

Description : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Last Answer : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Description : Pick up the correct statement from the following: (A) The roof slabs of multi-storeyed buildings are constructed monolithically to carry the various floor loads (B) The beams of multi-storeyed ... slab is spanned across the secondary beams provided between the main beams (D) All of these

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) Cavity of a cavity wall should start near ground level (B) Cavity of a cavity wall should terminate near eaves level of sloping roof (C) Cavity of a cavity wall should terminate near coping of flat roof with parapet wall (D) All the above

Last Answer : Answer: Option D

Description : The concrete work for the following part of the building of specified thickness is measured in square metres (A) Root slabs (B) Floors (C) Wall panels (D) All the above

Last Answer : (D) All the above

Description : (i) Suggest the relevant method of water-proofing used for following construction. 1) Basement of buildings. 2) Swimming pool. 3) Water tank. (ii) Suggest the relevant method of transportation of ... 1) Concreting in hilly areas. 2) Concreting of high-rise building. 3) Concreting under water.

Last Answer : Method of water-proofing for: 1) Basement of buildings: Waterproofing by using waterproof sealants. 2) Swimming pool: Waterproofing by spraying or grouting in cracks. 3) Water tank: Waterproofing by ... , concrete pump, slip form technique. 3) Concreting under water: Tremie pipe, grout pipe.

Description : Which one of the following activities is not correct as applicable to brick corbels? (A) The maximum projection of the corbel should not be more than the thickness of the wall (B) The ... to carry heavy concentrated loads (D) Stretcher bond is generally used for the construction of brick corbel

Last Answer : Answer: Option D

Description : The toe projection of foundation slabs is taken (A) As one third of the base (B) As one sixth of overall height of the wall (C) Equal to heel slab (D) Below ground surface

Last Answer : Answer: Option A

Description : Find the correct statement from the followings. (a) For a cantilever slab, the ratio of span to overall depth should not 12. (b) One way slab which carry uniformly distributed load should be designed to ... be designed to resist a hogging moment at the face of the support. (d) All of the above.

Last Answer : (d) All of the above.

Description : Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is (A) 1, 2, 4, 3, 5 (B) 1, 3, 2, 4, 5 (C) 1, 2, 3, 4, 5 (D) 1, 3, 4, 2,

Last Answer : (C) 1, 2, 3, 4, 5

Description : Suggest the type of cement used for the following : (i) For modular construction where form work needs to be removed early for re-use. . (ii) Mass concreting such as construction of dam. (iii) Decorative works in external surfaces of building. (iv) Cementing the oil well.

Last Answer : i) For modular construction where form work needs to be removed early for reuse. – Rapid Hardening Cement ii) Mass concreting such as construction of dam. – Low heat cement. iii) Decorative works in external surfaces of building – Coloured cement. iv) Cementing the oil well. – Oil Well Cement. 

Description : For the construction of R.C.C. slabs, columns, beams, walls, etc. the grade of concrete mix used, is (A) 1 : 3 : 6 (B) 1 : 1½ : 3 (C) 1 : 2 : 4 (D) 1 : 1 : 2

Last Answer : (C) 1 : 2 : 4

Description : The proportions of lime and sand in the mortar normally used in brick construction are (A) 1 : 2 (B) 1 : 4 (C) 1 : 6 (D) 1 : 8

Last Answer : Answer: Option A

Description : For brick construction, the lime-sand mortar, is (A) 1 : 1 (B) 1 : 2 (C) 1 : 3 (D) 1 : 4

Last Answer : Answer: Option B

Description : For the construction of buildings, the subheads of the estimate are (A) Earthwork, Concrete work, Brick work (B) Brickwork, Stone work, Roofing (C) Brickwork Flooring, Wood work, Steel work (D) All the above

Last Answer : (D) All the above

Description : An R.C.C. lintel is spanning an opening of 2 m span in a brick wall. The height of the roof is 2.9 m above the floor level and that of the opening is 2.1 m above the floor level. The lintel is to be ... (B) UDL of wall (C) UDL of wall + load from the roof (D) Triangular load + load from the roof

Last Answer : Answer: Option C

Description : Negative yield line form i. Near the supports in the case of slabs fixed or continuous at the edge. ii. At mid span in the case of slabs fixed. iii.At mid span for simply supported circular slab [ A ] i [ B ] i and ii [ C ] i and iii [ D ] i, ii and iii

Last Answer : [ A ] i

Description : Pick up the correct statement from the following: (A) The cost of square rooms is less (B) The expenditure on the foundation and roof for the double storeyed building is nearly half of that ... cost of construction of a house may be minimised by restricting the height floors (D) All the above

Last Answer : Answer: Option D

Description : According to I.S. : 456, slabs which span in two directions with corners held down, are assumed to be divided in each direction into middle strips and edge strips such that the width of the middle strip, is ... (C) Three-fourth of the width of the slab (D) Four-fifth of the width of the slab

Last Answer : Answer: Option C

Description : Critical section for shear in case of flat slabs is at a distance of (A) Effective depth of slab from periphery of column/drop panel (B) d/2 from periphery of column/capital/ drop panel (C) At the drop panel of slab (D) At the periphery of column

Last Answer : Answer: Option B

Description : The Maximum diameter steel in slabs should not exceed --------- the total thickness of the slab [ A ] One-half [ B ] One-fourth [ C ] One-eighth [ D ] One-sixteenth

Last Answer : [ C ] One-eighth

Description : Describe the procedure of water proofing used in slabs stating its importance in building construction.

Last Answer : Following is the stepwise procedure effectively applied in treatment of brick bat coba.  1 All existing treatment or coating on roof slab top is initially removed and surface is cleaned by hard wire brush ... surface is marked with 300 mm false squares The curing is done on next day. 

Description : Parapet walls along hill roads, are provided (A) To retain the back filling (B) To prevent the hill from sliding (C) To prevent the wheels of the vehicle from coming on the retaining wall (D) None of these

Last Answer : Answer: Option C

Description : The wall constructed for the stability of an excavated portion of a road on the hill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option B

Description : The wall constructed for the stability of a back filling portion of a road on the downhill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option A

Description : Formation width of a hill road is the distance between (A) Outer end of side drain to outer end of parapet wall (B) Outer end of side drain to inner end of parapet wall (C) Inner end of side drain to outer end of parapet wall (D) Inner end of side drain to inner end of parapet wall

Last Answer : Answer: Option A

Description : The walls which are necessary on the hill side of roadway where earth has to be retained from slipping is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) None of the above

Last Answer : Answer: Option B

Description : The stepped structure provided for lateral support of a structure, is (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Answer: Option C

Description : If P kg/m2 is the upward pressure on the slab of a plain concrete footing whose projection on either side of the wall is a cm, the depth of foundation D is given by (A) D = 0.00775 aP (B) D = 0.0775 aP (C) D = 0.07775 aP (D) D = 0.775 Pa

Last Answer : Answer: Option A

Description : Pick up the correct statement from the following: (A) Construction joints in columns are provided a few cm below the junction of beam (B) Construction joints in columns are provided at the bottom ... (C) Construction joints in beams and slabs are provided within middle third (D) All the above

Last Answer : Answer: Option D

Description : For concreting tunnel linings, transportation of concrete is done by (A) Pans (B) Wheel borrows (C) Containers (D) Pumps

Last Answer : (D) Pumps

Description : For concreting of heavily reinforced sections without vibration, the workability of concrete expressed as compacting factor should be (A) 0.75 - 0.80 (B) 0.80 - 0.85 (C) 0.85 - 0.92 (D) Above 0.92

Last Answer : Answer: Option D

Description : For providing a raft foundation, the following activities are involved 1. Ramming the foundation bed 2. Excavation of the soil upto required depth 3. Laying the reinforcement over the foundation bed 4. Curing the cement concrete placed over ... 2, 1 (C) 2, 1, 3, 5, 4 (D) 3, 2, 5, 1, 4

Last Answer : Answer: Option C

Description : Which of the following pairs gives a correct combination of the useful and harmful constituents respectively of a good brick earth? (A) Lime stone and alumina (B) Silica and alkalies (C) Alumina and iron (D) Alkalies and magnesium

Last Answer : Answer: Option B

Description : What is terrace gardening or roof gardening?

Last Answer : On the floor of our house, plants, twines, flower, fruits are cultivated. It might be roof, terrace or balcony. Instead of garden around the house the plants transferred to the floor. No requirements to bought new land, use of existing roof or floor for gardening is appreciable.

Description : Lime concrete is generally used for (A) Wall foundations (B) Flooring at ground level (C) Both (A) and (B) (D) Neither (A) nor (b)

Last Answer : Answer: Option B

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Vertical construction joints are provided where the shearing forces are minimum in the case of (A) Slabs (B) Beams (C) Girders (D) All of these

Last Answer : Answer: Option D

Description : The concrete slump recommended for beams and slabs; is (A) 25 to 50 mm (B) 25 to 75 mm (C) 30 to 125 mm (D) 50 to 100 mm

Last Answer : Answer: Option C

Description : If high yield strength deformed bars are used, the are of distribution reinforcement in slabs, should not less than. (a) 0.12% of the gross area of concrete (b) 0.15% of the gross area of concrete (c) 0.18% of the gross area of concrete (d) 0.20% of the gross area of concrete

Last Answer : (a) 0.12% of the gross area of concrete

Description : If plain bars are used, the area of distribution reinforcement in slabs should not less than (a) 0.12% of the gross area f concrete (b) 0.15% of the gross area of concrete (c) 0.18% of the gross area of concrete (d) 0.20% of the gross area of concrete

Last Answer : (b) 0.15% of the gross area of concrete

Description : Compare brick masonry and stone masonry used in building construction.

Last Answer : Sr. No. Brick Masonry Stone Masonry 1 It is less stronger than stone masonry. It is stronger than brick masonry. 2 It is cheaper in places where clay is available ... is used Double scaffolding is used 12 Plastering is required  Plastering is not required

Description : The reduced level of a floor is 99.995 m, the staff reading on the floor is 1.505 m. If the inverted staff reading against the roof is 1.795 m, the floor level below the slab, is (A) 3.290 m (B) 3.300 m (C) 3.275 m (D) 2.790 m

Last Answer : (B) 3.300 m

Description : An R.C.C. roof slab is designed as a two way slab if (A) It supports live loads in both directions (B) The ratio of spans in two directions is less than 2 (C) The slab is continuous over two supports (D) The slab is discontinuous at edges

Last Answer : Answer: Option B

Description : Pick up the correct statement from the following: (A) English bond is used for brick masonry to support heavy loads (B) Double-Flemish bond is suitable for brick masonry to give uniform face ... The stretcher bond is used for the construction of half brick masonry brick (D) All the above

Last Answer : Answer: Option D

Description : A wall constructed to resist the pressure of an earth filling, is called (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Option A

Description : A wall constructed with stones to protect slopes of cuttings in natural ground from the action of weathering agents, is called (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Option B

Description : Write the procedure of vaccum dewatering concreting for construction of floors.

Last Answer : Procedure of vaccum dewatering concreting for construction of floors: The concreting using vaccum dewatering for floor construction is done as follows. 1. Concrete is places uniformly on the spread of ... Finally the floating and towelling is done to achieve better finishing of surface. 

Description : In sequence, write concreting operations.

Last Answer : i. Batching of materials ii. Mixing of materials iii. Transportation of concrete iv. Placing of concrete v. Compaction of concrete vi. Curing of concrete vii. Finishing of concrete

Description : Draw concreting operation chain in sequence. 

Last Answer : Sequential chain of Concreting Operations: