For the construction of buildings, the subheads of the estimate are
(A) Earthwork, Concrete work, Brick work
(B) Brickwork, Stone work, Roofing
(C) Brickwork Flooring, Wood work, Steel work
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : Draw graphical symbols as per IS 962 – 1989. (i) Brickwork (ii) Partition Block (iii) Wood (iv) Single shutter door

Last Answer : Graphical Symbols as per IS 962 – 1989, for-

Description : Herringbone bond is used for (A) Walls having thickness more than 4 bricks (B) Architectural finish to the face work (C) Ornamental panels in brick flooring (D) All the above

Last Answer : Answer: Option D

Description : Compare stone masonry construction with brick masonry construction.

Last Answer : STONE MASONRY  BRICK MASONRY 1. Stone masonry is stronger and more durable than brick masonry 1. Brick masonry is less stronger and less durable than stone masonry. 2. ... other hand is considered unsuitable in the construction of piers, docks, dams and other marine structure.

Description : Compare brick masonry and stone masonry used in building construction.

Last Answer : Sr. No. Brick Masonry Stone Masonry 1 It is less stronger than stone masonry. It is stronger than brick masonry. 2 It is cheaper in places where clay is available ... is used Double scaffolding is used 12 Plastering is required  Plastering is not required

Description : The type of arch used for high class buildings where appearance is of prime importance, is known as (A) Ashlar arch (B) Rubble arch (C) Gauged brick arch (D) Axed brick arch

Last Answer : Answer: Option A

Description : (i) Suggest the relevant method of water-proofing used for following construction. 1) Basement of buildings. 2) Swimming pool. 3) Water tank. (ii) Suggest the relevant method of transportation of ... 1) Concreting in hilly areas. 2) Concreting of high-rise building. 3) Concreting under water.

Last Answer : Method of water-proofing for: 1) Basement of buildings: Waterproofing by using waterproof sealants. 2) Swimming pool: Waterproofing by spraying or grouting in cracks. 3) Water tank: Waterproofing by ... , concrete pump, slip form technique. 3) Concreting under water: Tremie pipe, grout pipe.

Description : Pick up the correct statement from the following: (A) In order to check up the average depth of excavation, 'Dead man s' are left at the midwidths of borrow pits (B) The earthwork ... embankment includes the formation of correct profile and depositing the soil in layers (D) All the above

Last Answer : (D) All the above

Description : If the length of a wall on either side of a lintel opening is at least half of its effective span L, the load W carried by the lintel is equivalent to the weight of brickwork contained in an equilateral triangle, producing a maximum bending moment (A) WL/2 (B) WL/4 (C) WL/6 (D) WL/8

Last Answer : Answer: Option C

Description : The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient ... calculated by Prismoidal formula, is (A) 3250 m3 (B) 3225 m3 (C) 3275 m3 (D) 3300 m3

Last Answer : (B) 3225 m3

Description : The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is (A) Rs. 400 (B) Rs. 425 (C) Rs. 450 (D) Rs. 500

Last Answer : (C) Rs. 450

Description : If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by (A) Mid-section formula (B) Trapezoidal formula (C) Prismoidal formula (D) All the above

Last Answer : (D) All the above

Description : The term frog means (A) An apparatus to lift the stone (B) A depression on a face of brick (C) Vertical joint in a brick work (D) Soaking brick in water

Last Answer : Answer: Option B

Description : Which one of the following rocks is used for monumental buildings? (A) Granite (B) Marble (C) Sand stone (D) Slate

Last Answer : Answer: Option B

Description : Sulphur melting pit in the sulphuric acid plant is made of (A) Lead lined stainless steel (B) Cast iron (C) Steel or cement-brick lined (D) Hard wood

Last Answer : (C) Steel or cement-brick lined

Description : Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is (A) 1, 2, 4, 3, 5 (B) 1, 3, 2, 4, 5 (C) 1, 2, 3, 4, 5 (D) 1, 3, 4, 2,

Last Answer : (C) 1, 2, 3, 4, 5

Description : In water bound macadam roads, binding material, is (A) Sand (B) Stone dust (C) Cement (D) Brick dust

Last Answer : Answer: Option B

Description : Stucco paints are suitable for (A) Stone masonry (B) Brick walls (C) Both (A) and (B) (D) Neither (A) nor (B)

Last Answer : Answer: Option C

Description : Which of the following pairs gives a correct combination of the useful and harmful constituents respectively of a good brick earth? (A) Lime stone and alumina (B) Silica and alkalies (C) Alumina and iron (D) Alkalies and magnesium

Last Answer : Answer: Option B

Description : Residential buildings are treated as (A) Light construction (B) Heavy construction (C) Industrial construction (D) Private construction

Last Answer : (A) Light construction

Description : The construction joints in buildings are provided after (A) 10 m (B) 15 m (C) 20 m (D) 40 m

Last Answer : Answer: Option D

Description : Lime concrete is generally used for (A) Wall foundations (B) Flooring at ground level (C) Both (A) and (B) (D) Neither (A) nor (b)

Last Answer : Answer: Option B

Description : For constructing a terrazzo floor, Pick up the incorrect statement from the following: (A) A base course is prepared as in cement concrete flooring (B) A 32 mm thick layer of cement concrete ... final grinding is over, oxalic acid mixed with water is spread over and rubbed hard with soft material

Last Answer : Answer: Option B

Description : Radiocarbon dating is used to estimate the ages of (a) babies (b) fossils (c) rocks (d) ancient buildings

Last Answer : Ans:(b)

Description : The proportions of lime and sand in the mortar normally used in brick construction are (A) 1 : 2 (B) 1 : 4 (C) 1 : 6 (D) 1 : 8

Last Answer : Answer: Option A

Description : Pick up the correct statement from the following: (A) English bond is used for brick masonry to support heavy loads (B) Double-Flemish bond is suitable for brick masonry to give uniform face ... The stretcher bond is used for the construction of half brick masonry brick (D) All the above

Last Answer : Answer: Option D

Description : For brick construction, the lime-sand mortar, is (A) 1 : 1 (B) 1 : 2 (C) 1 : 3 (D) 1 : 4

Last Answer : Answer: Option B

Description : Which one of the following activities is not correct as applicable to brick corbels? (A) The maximum projection of the corbel should not be more than the thickness of the wall (B) The ... to carry heavy concentrated loads (D) Stretcher bond is generally used for the construction of brick corbel

Last Answer : Answer: Option D

Description : What trustworthy websites would you recommend for outsourcing (besides getfriday, elance, brickwork)?

Last Answer : I worked with a really great Rails developer that was found on ODesk.

Description : The first stage of a construction, is (A) Preparation of estimate (B) Survey of the site (C) Initiation of proposal (D) Preparation of tender

Last Answer : (C) Initiation of proposal

Description : I have lakes with no water, mountains with no stone and cities with no buildings. What am I? -Riddles

Last Answer : I am the Map.

Description : I have lakes with no water, mountains with no stone and cities with no buildings. What am I?

Last Answer : the ground

Description : I have lakes with no water, mountains with no stone and cities with no buildings. What am I?

Last Answer : the ground

Description : Specify the material of construction suitable for handling concentrated HNO3 at 100°C. (A) High silicon iron, Kel-F and Teflon (B) Tin and wood (C) Silicone rubber (D) Stainless steel

Last Answer : (A) High silicon iron, Kel-F and Teflon

Description : The fermenter used for the production of ethyl alcohol from molasses is made of (A) Wood (B) Concrete (C) Copper bearing steel (D) Porcelain

Last Answer : (C) Copper bearing steel

Description : In the Kraft process of sulphate paper pulp manufacture, the black liquor and the white liquor storage tank is made of (A) Concrete (B) Wood (C) Steel (D) Porcelain

Last Answer : (C) Steel

Description : Copper is dissolved from its ore by H2SO4 in a percolation tank made of (A) Wood (B) Stainless steel (C) Reinforced concrete lined with lead (D) High silicon iron (14% Si)

Last Answer : (C) Reinforced concrete lined with lead

Description : most suitable material of construction for a sewer to carry sewage under high pressure is (A) Asbestos cement (B) Steel (C) Cement concrete (D) Stoneware

Last Answer : Option B

Description : Time and progress chart of a construction, is also known as (A) Bar chart (B) Gantt chart (C) Modified Mile stone chart (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Acid test is done to find out the weathering quality of stones (B) Attrition test is done to find out the rate of wear of stones which are used ... (C) Crushing test is done to find out the compressive strength of the stone (D) All the above

Last Answer : Answer: Option D

Description : Which of the following stone is best suited for construction of piers and abutments of a railway bridge? (A) Granite (B) Sand stone (C) Lime stone (D) Quartze

Last Answer : Answer: Option A

Description : The pressure acting on the stones in stone masonry construction should be (A) Along the direction of bedding planes (B) At 45° to the direction of bedding planes (C) At 60° to the direction of bedding planes (D) Perpendicular to the direction of bedding planes

Last Answer : Answer: Option D

Description : Can brick, stone, or marble tile / pavers be used on a floor with a basement underneath it, in a new house to be constructed?

Last Answer : It’s quite possible. You just need to make sure your plans account for the weight. I know of several floors that have stone and marble tile over crawlspaces.

Description : Differentiate between brick masonry and stone masonry

Last Answer : Sr. no. Brick masonry Stone masonry 1 It is cheaper than stone masonry It is stronger than Brick masonry 2 It is cheaper in places where clay is available It is ... easy to apply any finishing to Brick surface. It is difficult to apply any finishing to stone surface

Description : How can I keep my wood laminate flooring in good condition?

Last Answer : From what I understand it is important to keep sand and grit off it, so a daily dustmopping would be a good idea.

Description : When installing wood floors it is often recommended that you leave a half-inch of space between the flooring and the wall why do you think this space would be recommended?

Last Answer : The space is to allow for expansion of the flooring. Otherwise the flooring may buckle and lift in places.

Description : Can I use wood glue to bond oak flooring or should I use a professional product?

Last Answer : Wood glue can be used to bond flooring but the end result will be very poor. For only a few dollars more a proper bonding product can be used.

Description : What is better real wood flooring or wood looking flooring?

Last Answer : Real wood flooring is better because it looks more natural and it is authentic wood.

Description : Hard wood floor is too expensive, but I've been wondering about laminate flooring. Is this a good option?

Last Answer : Laminate flooring doesn't look quite as good as hardwood flooring, but it is less expensive and more durable. It resists stains and fading. It doesn't get nicked or scratched as easily as ... side comparison of laminate flooring and hard wood floors check out Floor Facts Hard wood vs. Laminate.

Description : Is linoleum flooring better than wood?

Last Answer : Linoleum is an excellent flooring for the kitchen. It is easy to clean, resistant to water damage, warmer underfoot than ceramic tiles and very reasonable in price.