Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
(A) 1, 2, 4, 3, 5
(B) 1, 3, 2, 4, 5
(C) 1, 2, 3, 4, 5
(D) 1, 3, 4, 2,