Consider the following operations:
 1. Drilling
 2. Blasting
 3. Mucking
 4. Placing steel
 5. Placing concrete
 The correct sequence of these operations in tunnel construction is
(A) 1, 2, 4, 3, 5
(B) 1, 3, 2, 4, 5
(C) 1, 2, 3, 4, 5
(D) 1, 3, 4, 2,

1 Answer

Answer :

(C) 1, 2, 3, 4, 5

Related questions

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is (A) Dry rolling, wet rolling, application of screening and application of ... of filler (D) Dry rolling, application of screening, application of filler and wet rolling

Last Answer : Answer: Option C

Description : The stones obtained by blasting are used as (A) Ballast in railways (B) Aggregates for concrete (C) Road metal (D) All the above

Last Answer : Answer: Option D

Description : It is the process of placing seeds in holes made in the seedbed and closing the seed with soil. In this method, seeds are placed in holes made at definite depth at fixed spacing. b. Drilling c. Broadcasting d. None of the above.

Last Answer : Ans - a. Dibbing

Description : is the process of placing seeds in holes made in seedbed and covering them. a) Broadcasting. b) Dibbling c) Drilling. d) Transplanting

Last Answer : Dibbling

Description : Consider the following salient points in a stress-strain curve of a mild steel bar: 1. Yield point 2. Braking point 3. Yield plateau 4 . Proportionality limit 5. Ultimate point The correct sequence in which they occur while testing the mild ... , 5 and 2 (c) 4, 1, 3, 5 and 2 (d) 1, 4, 2, 3 and 5

Last Answer : (c) 4, 1, 3, 5 and 2

Description : Consider the following statements: Percentage of steel for balanced designed of a singly reinforced rectangular section by limit state method depends on (1) Characteristic strength of concrete (2) Yield strength of concrete (3) Modulus of elasticity ... (b) 1, 3 and 4 (c) 1, 2 and 4 (d) 1, 2 and 3

Last Answer : 1,2,4

Description : For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is (A) 1 (B) 2 (C) 3 (D) 4

Last Answer : (A) 1

Description : The process of hardening the concrete by keeping its surface moist is known (A) Placing (B) Wetting (C) Curing (D) Compacting

Last Answer : Answer: Option C

Description : To prevent segregation, the maximum height for placing concrete, is (A) 100 cm (B) 125 cm (C) 150 cm (D) 200 cm

Last Answer : Answer: Option A

Description : The process of mixing, transporting, placing and compacting concrete using Ordinary Port land Cement should not take more than (A) 30 minutes (B) 40 minutes (C) 60 minutes (D) 90 minutes

Last Answer : Answer: Option A

Description : The property of the ingredients to separate from each other while placing the concrete is called (A) Segregation (B) Compaction (C) Shrinkage (D) Bulking

Last Answer : Answer: Option A

Description : The property of fresh concrete, in which the water in the mix tends to rise to the surface while placing and compacting, is called (A) Segregation (B) Bleeding (C) Bulking (D) Creep

Last Answer : Answer: Option B

Description : The process of keeping concrete moist for a certain period after its finishing, is known as (A) Finishing of concrete (B) Curing of concrete (C) Placing of concrete (D) Compaction of concrete

Last Answer : Answer: Option B

Description : The process of consolidating concrete mix after placing it in position is termed as. (a) Curing (b) Wetting (c) Compaction (d) All of these

Last Answer : (c) Compaction

Description : The process of mixing, transporting, placing and compacting the cement, concrete should not take more than. (a) 30 minutes (b) 60minutes (c) 90 minutes (d) 120mm

Last Answer : (a) 30 minutes

Description : The removal of excess air after placing concrete helps in increasing the strength of concrete by (a) 15 to 20% (b) 20 to 30% (c) 30 to 50% (d) 50 to 70%

Last Answer : (a) 15 to 20%

Description : While placing of concrete the thickness of each layer for R.C.C. is [ A ] 150 to 300 mm [ B ] 450 mm [ C ] 500 to 750 mm [ D ] 500 mm

Last Answer : [ A ] 150 to 300 mm

Description : What will all you Fluther muckers be mucking around with this summer?

Last Answer : I love the heat. Everyone wears less. Although that isn’t always a good thing.

Description : For the construction of buildings, the subheads of the estimate are (A) Earthwork, Concrete work, Brick work (B) Brickwork, Stone work, Roofing (C) Brickwork Flooring, Wood work, Steel work (D) All the above

Last Answer : (D) All the above

Description : To improve the machinability of steel by its softening, it is subjected to (A) Cold working (B) Annealing (C) Shot blasting (D) Heating

Last Answer : (B) Annealing

Description : The process of removal of scale formed during hot rolling of steel is termed as (A) Descaling (B) Shot blasting (C) Pickling (D) Skimming

Last Answer : Option C

Description : For concreting tunnel linings, transportation of concrete is done by (A) Pans (B) Wheel borrows (C) Containers (D) Pumps

Last Answer : (D) Pumps

Description : After fixing the plane table to the tripod, the main operations which are needed at each plane table station are (i) Levelling (ii) Orientation (iii) Centering The correct sequence of these operations is (A) (i), (ii), (iii) (B) (i), (iii), (ii) (C) (iii), (i), (ii) (D) (ii), (iii), (i)

Last Answer : (B) (i), (iii), (ii)

Description : The preparation of surface of stone to obtain plain edges or to obtain stones of required size and shape is known as (A) Quarrying of stones (B) Blasting of stones (C) Seasoning of stones (D) Dressing of stones

Last Answer : Answer: Option D

Description : Describe the construction and working of bench drilling machine with block diagram.

Last Answer : Major Parts of Bench Drilling Machine : Functions of Parts: i. Base: It supports the column, which in turn, support the table and head etc. ii. Spindle: It is made up of alloy steel. It ... : It is vertical round or box section, which rests on the base and supports the head and the table.

Description : For providing a raft foundation, the following activities are involved 1. Ramming the foundation bed 2. Excavation of the soil upto required depth 3. Laying the reinforcement over the foundation bed 4. Curing the cement concrete placed over ... 2, 1 (C) 2, 1, 3, 5, 4 (D) 3, 2, 5, 1, 4

Last Answer : Answer: Option C

Description : Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. ... and 4 are correct (C) 2, 3 and 4 are correct (D) 1, 2 and 4 are correct

Last Answer : (B) 1 and 4 are correct

Description : most suitable material of construction for a sewer to carry sewage under high pressure is (A) Asbestos cement (B) Steel (C) Cement concrete (D) Stoneware

Last Answer : Option B

Description : The main use of HCl is in the (A) Drilling of petroleum wells and pickling of steel sheets (B) Manufacture of cationic detergent (C) Treatment of spent fuel of nuclear reactor (D) None of these

Last Answer : (A) Drilling of petroleum wells and pickling of steel sheets

Description : In a drilling process, the metal is removed by both shearing & extrusion. General purpose drills are made of (A) Stainless steel (B) Mild steel (C) High speed steel (D) High carbon steel

Last Answer : (C) High speed steel

Description : Powder metallurgy technique is used in the production of __________ tools. (A) Tungsten carbide (B) High carbon steel (C) High speed steel (D) Drilling

Last Answer : Option A

Description : A construction schedule is prepared after collecting (A) Number of operations (B) Output of labour (C) Output of machinery (D) All the above

Last Answer : (D) All the above

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Consider the following types of turbines: 1. Francis 2. Pelton with a single jet 3. Kaplan The correct sequence of these turbines in increasing order of their specific speeds is (a) 1, 3 & 2 (b) 2, 1 & 3 (c) 1, 2 & 3 (d) 2, 3 & 1

Last Answer : (b) 2, 1 & 3

Description : Consider the following devices : 1. Orifice 2. Borda’s mouthpiece running free 3. Bell mouthed orifice 4. External mouthpiece What is the correct sequence of these devices by decreasing magnitude of coefficient of discharge? a) 2, 3, 1 and 4 b) 4, 3, 1 and 2 c) 4, 1, 3 and 2 d) 2, 1, 3 and 4

Last Answer : b) 4, 3, 1 and 2

Description : Pick up the correct statement from the following: (A) Cement should be mixed for at least one minute (B) 10% of water is placed in the rotating drum before adding dry material (C) 10% of water is added after placing the other ingredients in the drum (D) All the above

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The plastic bottles are made by the process of blowing (B) The application of thermo-setting resins on sheets of paper, is called laminating ... placing raw material in the desired moulds, is known as moulding process (D) All the above

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The sand in the sand pile is well compacted (B) The sand is kept moist at the time of placing and tamping (C) Sand piles are generally used under column loads (D) All of the above

Last Answer : Answer: Option D

Description : What is the main difference in construction between normal PN junction diodes and tunnel diodes?

Last Answer : The amount of doping.

Description : Sketch the construction of tunnel diode and write its operation.

Last Answer : Construction: Applications: • In digital networks. • As a high speed switch. • As a high frequency oscillator. • As a logic memory storage device. • In relaxation oscillator circuits.

Description : Describe in brief with neat sketch construction of tunnel with needle beam method

Last Answer : In this method stout timber beam known as needle beam is used which forms the main temporary support during the excavation. Construction steps: (a) First of all a small drift of about 1 1 m is ... . (d) After excavation, the lining is provided to the tunnel section and mucking is done. 

Description : Examine the following statements: (i) Factor of safety for steel should be based on its yield stress, (ii) Factor of safety for steel should be based on its ultimate stress, (iii) Factor of safety for concrete should be based on ... (iii) (B) (i) and (iv) (C) (ii) and (iii) (D) (ii) and (iv

Last Answer : Answer: Option B

Description : In general in the design of a section by limit method, it is assumed that [ A ] the stress in steel to reach its yield limit before concrete failure [ B ] the stress in concrete to ... in both concrete and steel reach their permissible values simultaneously [ D ] none of the above are correct

Last Answer : [ A ] the stress in steel to reach its yield limit before concrete failure

Description : In general in the design of a section by limit method, it is assumed that [ A ] the stress in steel to reach its yield limit before concrete failure [ B ] the stress in concrete to ... in both concrete and steel reach their permissible values simultaneously [ D ] none of the above are correct

Last Answer : [ A ] the stress in steel to reach its yield limit before concrete failure

Description : To indicate proper control of consistency of a freshly mixed concrete for pavement construction, the slump should be between (A) 3 to 5 cm (B) 4 to 6 cm (C) 5 to 7 cm (D) 7 to 10 cm

Last Answer : Answer: Option D

Description : In case of cement concrete pavements, pick up the incorrect statement (A) Tractive resistance is low (B) Initial cost of construction is high (C) Initial cost of construction is low (D) Visibility during nights is high

Last Answer : Answer: Option C

Description : Which of the following is considered to be the highest quality construction in the group of black top pavements? (A) Mastic asphalt (B) Sheet asphalt (C) Bituminous carpet (D) Bituminous concrete

Last Answer : Answer: Option D

Description : For the construction of R.C.C. slabs, columns, beams, walls, etc. the grade of concrete mix used, is (A) 1 : 3 : 6 (B) 1 : 1½ : 3 (C) 1 : 2 : 4 (D) 1 : 1 : 2

Last Answer : (C) 1 : 2 : 4

Description : For the construction of the retaining structures, the type of concrete mix to be used, is (A) 1 : 3 : 6 (B) 1 : 2 : 4 (C) 1 : 1½ : 3 (D) 1 : 4 : 8

Last Answer : Answer: Option C