Procedure of vaccum dewatering concreting for construction of floors: The concreting using vaccum dewatering for floor construction is done as follows. 1. Concrete is places uniformly on the spread of concrete floor and level it approximately. 2. Vibration by using suitable vibrators is applied to remove voids from concrete mass. The surface vibration is done using double beam surface vibrator. 3. Levelling of vibrated is done by using suitable straight edge. 4. The magnitude of applied vacuum is usually about 0.08 MPa and the water content is reduced by upto 20-25%. The reduction is effective upto a depth of about 100 to 150 mm only. 5. Vacuum pump is a small but strong pump of 5 to 10 HP. Water is extracted by vacuum and stored in the water separator. The mats are placed over fine filter pads, which prevent the removal of cement with water. 6. Proper control on the magnitude of the water removed is equal to the contraction in total volume of concrete. About 3% reduction in concrete layer depth takes place. 7. Finally the floating and towelling is done to achieve better finishing of surface.