For providing a raft foundation, the following activities are involved
1. Ramming the foundation bed
2. Excavation of the soil upto required depth
3. Laying the reinforcement over the foundation bed
4. Curing the cement concrete placed over reinforcement
5. Pouring the cement concrete over the reinforcement
The correct sequence is
(A) 1, 2, 3, 4, 5
(B) 5, 4, 3, 2, 1
(C) 2, 1, 3, 5, 4
(D) 3, 2, 5, 1, 4

1 Answer

Answer :

Answer: Option C

Related questions

Description : Which one of the following represents an activity? (A) Excavation for foundation (B) Curing of concrete (C) Setting of question paper (D) All the above

Last Answer : (D) All the above

Description : Raft foundations are used for: (A) Providing increased area of foundation over poor bearing capacity of soil (B) Spanning over small soft or loose pockets (C) Counter acting the hydrostatic effect (D) All the above

Last Answer : Answer: Option D

Description : The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than (A) The column spacing (B) One-third the column spacing (C) Half the column spacing (D) Three-fourth the column spacing

Last Answer : Answer: Option B

Description : The depth of concrete bed of the foundation depends upon (A) The projection of the concrete block beyond the footing over it (B) The upward soil pressure (C) The mix of the concrete (D) All the above

Last Answer : Answer: Option D

Description : Minimum shear reinforcement is necessary to [ A ] Prevent brittle shear failure [ B ] Prevent failure due to shrinkage and thermal stresses [ C ] Hold the reinforcements in place while pouring concrete [ D ] All the above.

Last Answer : [ D ] All the above.

Description : Reinforcement in cement concrete slab of road pavements, is placed (A) Longitudinally (B) Transversely (C) Longitudinally and transversely (D) In the form of welded wire mesh

Last Answer : Answer: Option D

Description : State the necessity of providing (i) Combined column footing and (ii) Raft foundation

Last Answer : (i) Combined column footing:- A combined footing provided as a column for two or more columns in a row. Combine footing is also provided when the columns are very near to each other and ... total individual footing area of all columns exceeds 50% of built up area of building at ground floor.

Description : Pick up the correct statement from the following: (A) Plain cement concrete is equally strong in compression as well as in tension (B) Slump test is performed to check concrete strength (C ... D) Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates

Last Answer : Option D

Description : Pick up the correct statement from the following: (A) In order to check up the average depth of excavation, 'Dead man s' are left at the midwidths of borrow pits (B) The earthwork ... embankment includes the formation of correct profile and depositing the soil in layers (D) All the above

Last Answer : (D) All the above

Description : To support a heavy structure in sandy soil, the type of foundation generally used, is (A) Combined footing (B) Raft footing (C) Pier footing (D) Strap footing

Last Answer : Answer: Option C

Description : Pick up the PERT event from the following: (A) Digging of foundation started (B) Digging of foundation completed (C) Laying of concrete started (D) All the above

Last Answer : (D) All the above

Description : The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as (A) Combined footing (B) Strap footing (C) Raft footing (D) None of these

Last Answer : Option C

Description : When shear stress exceeds the permissible limit in a slab, then it is reduced by (A) Increasing the depth (B) Providing shear reinforcement (C) Using high strength steel (D) Using thinner bars but more in number

Last Answer : Answer: Option A

Description : Depth of lean concrete bed placed at the bottom of a wall footing, is kept (A) 10 cm (B) 15 cm (C) Equal to its projection beyond wall base (D) Less than its projection beyond wall base

Last Answer : Answer: Option C

Description : Pick up the correct statement from the following: (A) Isolated footing is provided under column to transfer the load safely to soil bed (B) Column footings may have steps or projections in the ... ) Heavily loaded column base must be provided steel reinforcement in both directions (D) All the above

Last Answer : Option D

Description : Strength of concrete increases with (A) Increase in water-cement ratio (B) Increase in fineness of cement (C) Decrease in curing time (D) Decrease in size of aggregate

Last Answer : (B) Increase in fineness of cement

Description : Blast furnace slag cement concrete requires ___________time for shuttering and curing. (a) Less (b) More (c) Medium (d) All the above

Last Answer : (b) More

Description : For Ordinary Portland cement concrete exposed to dry and hot weather conditions, good moist curing period is [ A ] 7 days [ B ] 10 days [ C ] 14 days [ D ] None of the above

Last Answer : [ B ] 10 days

Description : Modulus of elasticity of concrete is primarily influenced by [ A ] Elastic properties of aggregate [ B ] Curing of concrete [ C ] Age of concrete [ D ] Mix proportion and type of cement

Last Answer : [ A ] Elastic properties of aggregate

Description : While investigating the site, a thick layer of fairly firm clay over a deep layer of soft clay is encountered. In such a situation, the following type of foundation is useful: (A) Pile formation (B) Raft foundation (C) Grillage foundation (D) None of these

Last Answer : Answer: Option B

Description : Pick up the incorrect statement from the following: (A) The function of foundation is to distribute the load of super structure over a large bearing area (B) No timbering is required for shallow ... can be constructed on made-up soil (D) Black cotton soil is very good for foundation bed

Last Answer : Answer: Option D

Description : Raft foundation are generally preferred to when the area required for individual footing, is more than (A) 25% to total area (B) 30% of total area (C) 40% to total area (D) 50% of total area

Last Answer : Option D

Description : Depth of reinforcement below the surface of a concrete pavement, is generally kept (A) 5 cm (B) 6 cm (C) 7 m (D) 9 m

Last Answer : Answer: Option A

Description : Grillage foundation (A) Is used to transfer heavy structural loads from steel columns to a soil having low bearing capacity (B) Is light and economical (C) Does not require deep cutting as the required base area with required pressure intensity is obtained at a shallow depth (D) All the above

Last Answer : Answer: Option D

Description : In a simply supported reinforced concrete beam, the reinforcement is placed. (a) Above the neutral axis (b) Below the neutral axis (c) At the neutral axis (d) None of these

Last Answer : (b) Below the neutral axis

Description : In the reinforced cement concrete structure, the steel reinforcement consists of . (a) Deformed bars (b) Cold twisted bars (c) Mildsteel and medium tensile steel bars (d) All of these

Last Answer : (d) All of these

Description : A raft foundation is provided if its area exceeds the plan area of the building by (A) 10 % (B) 20 % (C) 40 % (D) 50 %

Last Answer : Answer: Option D

Description : For a number of columns constructed in a rcjw, the type of foundation provided, is (A) Footing (B) Raft (C) Strap (D) Strip

Last Answer : Answer: Option D

Description : The rate of payment is made for 100 cu m (per % cu m) in case of (A) Earth work in excavation (B) Rock cutting (C) Excavation in trenches for foundation (D) All the above

Last Answer : (D) All the above

Description : The foundation in which a cantilever beam is provided to join two footings, is known as (A) Strip footing (B) Strap footing (C) Combined footing (D) Raft footing

Last Answer : Answer: Option B

Description : The maximum total settlement for raft foundation on clayey soils should be limited to (A) 25 mm (B) 25 to 40 mm (C) 40 to 65 mm (D) 65 to 100 mm

Last Answer : Answer: Option D

Description : For the construction of flyovers in sandy soils, the type of foundation provided, is (A) Strap footing (B) Raft footing (C) Combined footing (D) Pier footing

Last Answer : Answer: Option D

Description : The type of footing which is used to transmit heavy loads through steel columns is (A) Raft foundation (B) Grillage foundation (C) Well foundation (D) Isolated footing

Last Answer : Option B

Description : In soils possessing low bearing capacity, the type of foundation generally provided, is (A) Column footing (B) Grillage footing (C) Raft footing (D) All the above

Last Answer : Option D

Description : Pick up the incorrect statement from the following: (A) The width of the wall is constructed thicker at the base in a stepped fashion (B) A long vertical load transferring concrete structure is ... ) The pile which transfers the load to a hard rock bed at certain depth is called load bearing

Last Answer : Answer: Option D

Description : Bearing capacity of soils cannot be improved by (A) Draining sub-soil water (B) Ramming crushed stone in soil (C) Driving sand piles (D) Watering surface of soil

Last Answer : Answer: Option D

Description : In congested areas where excavation is expensive and inconvenient 'draw in system' of laying of underground cables is often adopted. (a) Yes (b) No

Last Answer : (a) Yes

Description : The measurement is made in square metre in case of (A) Cement concrete in foundation (B) R.C.C. structure (C) Hollow concrete block wall (D) None of these

Last Answer : (D) None of these

Description : For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is (A) 1 (B) 2 (C) 3 (D) 4

Last Answer : (A) 1

Description : The produce impermeable concrete (A) Thorough mixing of concrete is required (B) Proper compaction of concrete is required (C) Proper curing of concrete is required (D) All the above

Last Answer : Answer: Option D

Description : If P kg/m2 is the upward pressure on the slab of a plain concrete footing whose projection on either side of the wall is a cm, the depth of foundation D is given by (A) D = 0.00775 aP (B) D = 0.0775 aP (C) D = 0.07775 aP (D) D = 0.775 Pa

Last Answer : Answer: Option A

Description : raft increases with increase in forward speed for most of the implement, mainly due to a) More rapid acceleration of any soil particles that is moved appreciably b) More working width c) Increased working depth d) Draft decreases with increase in speed of implement

Last Answer : a) More rapid acceleration of any soil particles that is moved appreciably

Description : The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as (A) Excavation (B) Surface dressing (C) Cutting (D) Surface excavation

Last Answer : (D) Surface excavation

Description : If the depth of an excavation is 20 metres, number of single stage well points to be installed at various levels, is (A) 5 (B) 4 (C) 3 (D) 2

Last Answer : Answer: Option C

Description : The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed (A) 5 m (B) 10 m (C) 15 m (D) 20 m

Last Answer : Answer: Option A

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : The depth of excavation of foundations, is generally measured with a (A) Ranging rod (B) Steel tape (C) Levelling staff (D) Boning rod

Last Answer : Answer: Option D

Description : channel is said to be of most economical cross-section, if (A) It gives maximum discharge for a given cross-sectional area and bed slope (B) It has minimum wetted perimeter (C) It involves lesser excavation for the designed amount of discharge (D) All of the above

Last Answer : Answer: Option D

Description : A contractor wishes to determine a suitable combination of manual labour and machine work for the excavation of a multistory construction. For every cum of excavation, 3 man-hours are needed; or 0.2 machine-hour. Costs ... total cost will be (a) 1500 cum (b) 1800 cum (c) 2250 cum (d) 2500 cum

Last Answer : (d) 2500 cum

Description : If d is the economic designed depth of a slab, the thickness of the cement concrete pavement slab at interior, is kept (A) 1.275 d (B) 1.125 d (C) 0.85 d (D) 0.75 d

Last Answer : Answer: Option C