Systematic risk is higher when:

A. α > 0.

B. α < 0.

C. α > 1.

D. β > 1

1 Answer

Answer :

D. β > 1

Related questions

Description : Inferior investment alternatives are identified when: A. α < 0. B. β = 0. C. β > 1. D. β < 1.

Last Answer : A. α < 0.

Description : Total risk for common stocks is: A. the sum of systematic risk and diversifiable risk. B. measured by beta. C. the sum of market risk and systematic risk. D. the sum of diversifiable risk and unsystematic risk

Last Answer : A. the sum of systematic risk and diversifiable risk.

Description : Identify the incorrect statement in connection with working capital management. A. Long-term funds are more expensive than short-term funds but also riskier B. The objectives of ... fluctuating current assets E. Aggressive financing policies increase profitability at the cost of higher risk

Last Answer : A. Long-term funds are more expensive than short-term funds but also riskier

Description : Pick out the correct statement. (A) Positron is the antiparticle of electron (B) In α-decay, the ratio of neutron to proton decreases (C) Ionising power of β-rays is higher than that of α-rays (D) Speed of α-rays is more than that of γ-ray

Last Answer : (A) Positron is the antiparticle of electron

Description : To the nearest rupee, what is the net present value of a replacement project whose cash flows are -Rs.104,000; Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 0 through 4, respectively? The firm has decided to ... -free rate is 6%. A. Rs.15,115 B. Rs.26,798 C. Rs.33,346 D. Rs.48,121

Last Answer : C. Rs.33,346

Description : If α, β are the zeroes of the polynomial x2 – 16, then αβ(α + β) is (a) 0 (b) 4 (c) -4 (d) 16

Last Answer : (a) 0

Description : In Cobb-Douglas production function Q = ALα Kβ there will be increasing returns to scale, if (a) α + β = 1 (b) α + β > 0 (c) α + β > 1 (d) α + β < 1

Last Answer : (c) α + β > 1

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.

Last Answer : c. Project sponsor.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.

Last Answer : b. It facilitates the risk appetite.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : . A 66.6% risk is considered as a) very low b) low c) moderate d) high

Last Answer : d) high

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management

Last Answer : C. project monitoring

Description : . A 66.6% risk is considered as a) very low b) low c) moderate d) high

Last Answer : d) high

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the  project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk

Last Answer : b. An opportunity that must be explored

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Fill in the blank. There is _______ correlation between project complexity  and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general

Last Answer : b. a positive

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : An example of the risk involved in development is a) Key personnel may resign before the product is complete b) The manufacturer of critical components (e.g. the hardware  associated with a ... a fully functional lower-cost  equivalent package e) All of these are risks involved in development.

Last Answer : e) All of these are risks involved in development.

Description : Following is (are) the component(s) of risk management (A)Risk Assessment (B)Risk Control (C)Risk Ranking (D)All of the above

Last Answer : (D)All of the above

Description : Which of the following is not a Configuration Management  Activity? a) Configuration item identification b) Risk management c) Release management d) Branch management

Last Answer : b) Risk management

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above

Last Answer : c. Track progress

Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover

Last Answer : c. Testing

Description : Which of the following is not the part of Risk Control  A. Execution of the risk response strategy  B. Monitoring of triggering events  C. Initiating contingency plans  D. Not watching for new risks

Last Answer : D. Not watching for new risks

Description : Which risk is connected to the circumstance outside the project that may influence the  scope of work and the performance of the organization?  A.Operational Risk  B.Financial Risk  C.Strategic Risk  D.Contextual Risk

Last Answer : D.Contextual Risk

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle

Description : Risk in project management is defined as  A.An uncertain event that, if it occurs, has a positive effect on project objectives  B.An uncertain event that, if it occurs, has a negative ... effect on project  objectives  D.An uncertain event that do not have any effect on project objectives

Last Answer : C.An uncertain event that, if it occurs, has a positive or negative effect on project  objectives

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : Each of the following statements is true regarding the risk management plan except  for which one?  A. The risk management plan is an output of the Risk Management Planning process. B. The risk ... and budgets. D. The risk management plan is an input to all the remaining risk-planning processes.

Last Answer : B. The risk management plan includes a description of the responses to risks and  triggers.

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis