You need to convey some very complex, detailed information to the project 

stakeholders. What is the best method for communicating this kind of information? 

A. Verbal 

B. Vertical 

C. Horizontal 

D. Written

1 Answer

Answer :

D. Written

Related questions

Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.

Last Answer : a. informing stakeholders about the project.

Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : Project reporting can best be defined as:  a. informing stakeholders about the project.  b. storing and archiving of project information. c. gathering stakeholder feedback.  d. collecting project information.

Last Answer : a. informing stakeholders about the project

Description : A communication management plan identifies the relevant information that should be  communicated to:  a. the project team.  b. the project stakeholders.  c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : Using the shortcut method to determine the complexity of a systems project, a very  complex system having 300 unadjusted function points would have 405 adjust function  points.

Last Answer : Ans: True

Description : Truly effective communication: 1. Depends on using multiple channels  2. Depends on selecting the right method for each message and avoiding duplication, since  everyone is overloaded with information  3. ... misunderstood  4. Can only be achieved by communication professional  5. a, b and c

Last Answer : 5. a, b and c

Description : The process of communication contains four major parts. Which part is the vehicle or method  used to convey the message? 1. Communicator  2. Message 3. Medium  4. Recipient

Last Answer : 3. Medium

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Which one is a true statement relating to project communications? a. A project sponsor is responsible for all communication methods and media. b. Different stakeholders typically have different communication needs ... project. d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

Last Answer : d. 36

Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.

Last Answer : a. The cost associated at the beginning of the project is highest.

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : Which one is a true statement relating to project communications?  A. A project sponsor is responsible for all communication methods and media.  B.Different stakeholders typically have different communication ... project.  D. Email is the only way to communicate with large numbers of people

Last Answer : B.Different stakeholders typically have different communication needs

Description : Why is it important to understand your Stakeholders?  A. They may work in a different department or company B. They may have different technical backgrounds C. They may not care about the project D. They can be a positive or negative influence on the project (Ans.)

Last Answer : D. They can be a positive or negative influence on the project (Ans.)

Description : The project you are managing has nine stakeholders. How many channel of communications  are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

Last Answer : 36

Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.

Last Answer : a. The cost associated at the beginning of the project is highest.

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.

Description : Which one is a true statement relating to project communications?  a. A project sponsor is responsible for all communication methods and media.  b. Different stakeholders typically have different communication ... project.  d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : The PM distributed a document to the stakeholders, which described the software to be  developed, the functionality, the users it would serve and the installation timeline. The document  was an example of: ... scope  4. It was not complete enough to be either a product or a project scope document

Last Answer : 4. It was not complete enough to be either a product or a project scope document

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : Who among the following are less able to influence a project? (A) Consultants (B) Contractors (C) Stakeholders (D) Project team

Last Answer : (B) Contractors

Description : )Methods of transmitting include: 1. Oral and written  2. Non-verbal/ visual  3. Tactile, involuntary and intuitive  4. All of the above

Last Answer : 4. All of the above

Description : Pre-operatively, the nurse identified the nursing dagnosis, Knowledge Deficit: Post-operative communication strategies . Which of the following is a relevant nursing intervention? A. ... uses an alternative form of verbal communication D. Illustrate means of communicating post- operatively

Last Answer : D. Illustrate means of communicating post- operatively

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : Once project planning is complete, project managers document their plan in A. SPMP document B. SRS document C. Detailed Design document D. Excel Sheet

Last Answer : A. SPMP document

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : The most formal definition of marketing is ________. A. Meeting needs profitably B. Identifying and meeting human and social needs C. The four Ps (product, price, place, promotion) D. ... ways that benefit the organization and its stakeholders. E. Improving the quality of life for consumers

Last Answer : D. An organizational function and a set of processes for creating, communicating, and delivering value to customers and for managing customer relationships in ways that benefit the organization and its stakeholders.

Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich  environment will suffer. e. Contracts promote the growth of a trusting project culture.

Last Answer : b. They do not lend themselves to create an environment of trust.

Description : Assume a systems development project effort calculation determines that the system  will require 240 function points. If the developers choose to implement this system in the  C programming language, approximately ... without more information  c. exactly the same  d. much greater  e. much less

Last Answer : e. much less

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : Constantine suggests four “organizational paradigms” for  engineering teams. The best project team organizational model to use when handling extremely complex problems is  a. Random paradigm b. Open paradigm c. Synchronous paradigm d. Closed paradigm

Last Answer : a. Random paradigm

Description : The activities that make up the project are not simple, repetitive  acts, such as mowing the lawn, painting the house, washing the car, or loading the delivery truck. a. They are complex b. They are simple c. Different d. Same

Last Answer : a. They are complex

Description : A project is a sequence of a. Unique b. Complex c. connected activities d. all the above

Last Answer : d. all the above

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : A Communications Management Plan does the following:  A. Coordinates an effort to communicate in meetings effectively B. Lays out a plan on how to communicate with your Project ... and  efficiently. D. Coordinates the communication between project leaders and uninterested project  members

Last Answer : C. Lays out the approach and method for delivering information effectively and  efficiently.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature