You are the project manager working on a research project for a new drug treatment.
Your preliminary project schedule runs past the due date for a federal grant application.
The manager of the R&D department has agreed to release two resources to work on your
project in order to meet the federal grant application date. This is an example of
_______________.
A. Crashing
B. fast tracking
C. resource leveling
D. adjusting the resource calendar