Which of the following technique overcomes drawback related to LOC?

A. Project Planning Sheet

B. Function Point Metric

C. COCOMO

D. COCOMO2

1 Answer

Answer :

B. Function Point Metric

Related questions

Description : Which of the following can estimate size of project directly from problem specification? A. LOC B. Function Point Metric C. Both D. None

Last Answer : B. Function Point Metric

Description : The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to ... ) 25 person months (B) 75 person months (C) 62.5 person months (D) 72.5 person months

Last Answer : (C) 62.5 person months 

Description : A software company needs to develop a project that is estimated as 1000 function points and is planning to use JAVA as the programming language whose approximate lines of code per function point is accepted as 50. Considering a=1. ... ? (1) 11.2 months (2) 12.2 months (3) 13.2 months (4) 10.2 months

Last Answer : Generally, any projects are measured in weeks. However, the complex project might take more time depending on the level of object re-use available.

Description : Which is not a size metric? (A) LOC (B) Function count (C) Program length (D) Cyclomatic complexity

Last Answer : (D) Cyclomatic complexity

Description : Once project planning is complete, project managers document their plan in A. SPMP document B. SRS document C. Detailed Design document D. Excel Sheet

Last Answer : A. SPMP document

Description : A is developed using historical cost information that relates  some metric to the project cost. a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : a) Algorithmic cost modelling

Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above

Last Answer : B. only i & ii

Description : In Intermediate COCOMO the mode that represents complex  products is referred to as a) Embedded b) Semidetached c) Organic d) Multiplicative e) onolithic.

Last Answer : a) Embedded

Description : The COCOMO model takes into account different approaches to development, reuse, etc. a) True b) False

Last Answer : b) False

Description :  The COCOMO model to convert lines of code estimates into person-month estimates  was designed by Allen Albrecht of IBM.

Last Answer : Ans: False

Description : Which of the following are advantages of using LOC (lines of code) as a sizeoriented metric? (A) LOC is easily computed. (B) LOC is a language dependent measure. (C) LOC is a language independent measure. (D) LOC can be computed before a design is completed.

Last Answer : (A) LOC is easily computed.

Description : Problems with using Lines of Code to measure the size of a product include(s) a) The creation of source code is only part of the development effort b) The Lines of Code (LOC) will differ between ... The final size (kLOC) can only be determined once the product is delivered e) All of the above.

Last Answer : e) All of the above.

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : The primary components of the quality management function are : 1. quality planning  2. quality control and assurance  3. quantitative measurement  4. quantitative assessment of the project

Last Answer : 5. a and b

Description : SWOT analysis is a strategic planning technique used to identify strengths, weaknesses,  opportunities, and (A) timing (B) tenure (C) totality (D) threats

Last Answer : (D) threats

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which of the following serves as project estimation technique? A. Empirical estimation B. Heuristic technique C. Analytical estimation D. All of the above

Last Answer : D. All of the above

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description :  The project team has just determined that the deadline for completion will not be met.  In order to deliver a high quality system on schedule, the team has requested that the  features be ... that a fixed deadline be imposed for the project. This technique  is referred to as SDLC methodology.

Last Answer : Ans: False

Description : Timeboxing is a popular technique which sets a fixed deadline for a project and  delivers the system by that deadline no matter what, even if functionality needs to be  reduced.

Last Answer : Ans: True

Description : Which conflict resolution technique do project managers use most often?  A. Smoothing B. Norming C. Confronting D. Forcing

Last Answer : C. Confronting

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : The project life cycle consists of (A) Understanding the scope of the project (B) Objectives of the project (C) Formulation and planning various activities (D) All of the above

Last Answer : (D) All of the above

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : . A key aspect of managing a project involves: a. defining which operational systems to put in place. b. identifying routine tasks. c. ensuring ongoing operations are maintained. d. planning to achieve defined objectives

Last Answer : d. planning to achieve defined objectives.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : . The process that evaluates overall project performance to provide confidence is called: a. quality assurance. b. quality planning. c. quality control. d. quality audit.

Last Answer : a. quality assurance.

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : Different activity of a project management is A. project planning B. project monitoring C. project control D. All of the above

Last Answer : B. project monitoring

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing