Explain in brief the allowances to be considered while estimating the standard time.

1 Answer

Answer :

Allowances to be considered while estimating the Standard Time: Allowances are added to the normal time in order to arrive at standard time. It is impossible to work throughout the day even though the most practicable, effective method has been developed. Some allowances must therefore be made for recovery from fatigue and for relaxation. Allowances must also be made to enable the worker to attend to his personal needs. There are following types of allowances;

[1] Relaxation Allowance: These are calculated so as to allow the worker to recover from fatigue. These are used to provide the worker with the opportunity to recover from physiological & psychological effects of carrying out specified work under specified conditions. The amount of allowance will depend on nature of job. 

[2] Personal (Need) Allowance: It is intended to compensate the operator for the time necessary to leave, the workplace to attend to personal needs like drinking water, smoking, washing hands. Women require longer personal allowance than men. A fair personal allowance is 5 % for men and 7% for women.

[3] Fatigue Allowance: It is an allowance given to compensate for energy expended during working. A common fatigue considered as allowance is 4 % of the basic time 

[4] Variable Allowance: It is allowed to an operator who is working under poor environmental conditions that cannot be improved, added stress and strain in performing the job. The variable fatigue allowance is added to the fixed allowance to an operator who is engaged on medium and heavy work and working under abnormal conditions. 

[5] Interference Allowance: It is an allowance of time included into the work content of the job to compensate the operator for the unavoidable loss of production due to simultaneous stoppage of machines. This allowance is applicable for machine or process controlled jobs. 

[6] Contingency Allowance: It is an allowance of time which may be included in standard time to meet legitimate and expected items of work or delays etc. This allowance provides for small unavoidable delays as well as for occasional minor, extra work. E.g. Tool breakage, Power failures etc. 

[7] Policy Allowance: Basic purpose of this allowance is to line up standard times with requirements of wage arrangement between employers and trade unions. It is an increment, other than bonus increment, applied to standard time to provide satisfactory level of earnings for a specified level of performance under exceptional circumstances. It is used with utmost care and only in clearly defined circumstances.

Related questions

Description : What allowances are considered while calculating standard time? 

Last Answer : following types of allowances are considered while calculating standard time. 1) Relaxation allowance a) Personal need allowance b) Fatigue allowance i) Basic fatigue allowance ii) Variable ... 2) Contingency allowance 3) Special allowance 4) Process allowance 5) Interference allowance

Description : Explain in brief steps involved in process planning.

Last Answer : Steps involved in process planning: 1. Analysis of Product and its specification: - During analysis, following parameter should be considered, a. Drawing and specification of product. b. Quality of ... and fixing the rates of payment. 11. Prepare the route sheet and operation sheet.

Description : What are grippers? Explain vacuum actuated gripper in brief.

Last Answer : Grippers:- A gripper is a device which enables the holding of an object to be manipulated. a gripper enables holding, tightening, handling and releasing of an object. Vacuum Grippers:- The ... or Suction Cup, some vacuum grippers use a closed-cell foam rubber layer for gripping application. 

Description : Explain in brief product and process type layout

Last Answer : Product Layout:- It is also known as line layout. It implies that various operations on raw materials are performed in a sequence and the machines are placed along the product flow line i.e. machines are ... lathes will be at one place, all milling machines will be at one place etc

Description : State the necessity of grippers. Explain vacuum actuated grippes in brief

Last Answer : Necessity [1] It enables holding of the object [2] It helps to release the object [3] It handles the object [4] Objects can be tightening Vacuum Actuated Grippes  The vacuum ... Vacuum cup or Suction Cup, some vacuum grippers use a closed-cell foam rubber layer for gripping application.

Description : Explain the principles considered for selection of material handling equipment.

Last Answer : 1. Planning :All activity should be planned. Plan a system which include all the handling activities & co-coordinating the operations. 2. Simplification principle: Reduced or eliminate ... 10. Maintenance principle: Plan for preventing maintenance and schedule repair of all handling equipment

Description : If worker takes 15 min as a standard time for as job in which total allowance is 20% of normal time. If the rating of the worker is 100 %. Find the actual time required by the worker

Last Answer : Standard Time (ST) = 15 Minutes Rating Factor (RF) = 100 % Allowance = 20 % of Normal Time (NT) Standard Time (ST) = Normal Time (NT) + Allowance 15 = NT + (20/100) NT 15 = ... (Actual) Time Actual (Observed) Time (AT) required by the worker to complete the job is 12.5 Minutes.

Description : What are the factors to be considered to determine stages of inspection during process planning?

Last Answer : Factors to be considered to determine stages of Inspection during Process Planning: 1. Type of Production System 2. Type of Facility Layout 3. Type (Nature) of Product/Components 4. ... /Equipments used 5. Application of the Product/Components etc. 6. Strength/characteristics of the product

Description :  Explain the concept of AGV? State it’s any two applications. 

Last Answer : AGV is the battery operated programmed vehicle, used to carry load from one location to another by following a prescribed path around the manufacturing floor. It is a driverless vehicle, ... System) 2) AGV material handling system is very suited to computer integrated manufacturing system  

Description : Explain various Robot configurations with neat sketch. 

Last Answer : Different Robot Configurations: Robots are being classified on the basis of their physical configuration and control systems adopted. These classifications are briefly described as below: [1] ... direction for vertical insertion tasks. It is basically used for the assembly purpose.

Description : What is ejector? Explain role and necessity of ejector in the design of jigs and fixtures.

Last Answer : Ejector: Ejector is used to remove the work piece from close fitted locators and is present behind the work piece. Ejector speed up the operation by reducing unloading time. This increases the ... [6] The combined mechanism used in Ejectors can be powered hydraulically or by compressed air. 

Description : Explain the concept of JIT and how does it help the manufacturing system to improve productivity?

Last Answer : Concept of JIT: [1] JIT is a Production methodology which aims to improve overall productivity through elimination of waste and which leads to improved quality. [2] JIT concept was ... ] It improves customer satisfaction [14] It improves working condition and relation between employees. 

Description : Explain the importance of ‘5S’ (“Five S”) Concept.

Last Answer : Introduction of 5 S Concept: [1] 5S is a process of workplace organization and housekeeping which is carried out gradually and systematically. [2] It is a structured program to implement workplace ... In fact, 5S is a basic step in a journey towards Total Quality Management (TQM).

Description : What are the different types of Fixtures? Explain any one with sketch.

Last Answer : Types of Fixtures: Following are the types of Fixtures according to the type of machine operations for which they are used. [1] Lathe (Turning) Fixture [2] Milling fixtures  [3] Grinding ... relative to the tool of the machine table and guide the broaching tool in relation to the job. 

Description : Explain the principle of working of hydraulic actuator and state its advantages.

Last Answer : Working Principle of Hydraulic Actuator  1. According to Pascal, when there is an increase in pressure at any point in a confined incompressible fluid, then there is an equal increase at every point in ... better performance than others. 3. Power to weight ratio of these actuators is high.

Description : List down various types of clamping devices used in design of Jigs. Explain any one with sketch.

Last Answer : List of Types of clamping devices used in design of jigs. i. Screw clamp ii. Pivoted clamp. iii. Equalizing clamp. iv. Latch clamp. v. Wedge clamp. vi. Hinged jaw clamp. ... to be gripped on its edges as shown in figure. This arrangement ensures easy machining of the work piece 

Description : Explain the following terms in context with work study.

Last Answer : i. Therbligs. ii. MTM (Method Time Measurement)  Therbligs :  1. Therbligs are used to describe the basic element of movement or fundamental hand motions of the work cycle. 2. Every ... sum of these motion times is the time an operator of average skill would take to perform the task.

Description : Explain the need and importance of material handling devices in an industry. 

Last Answer : Need of material handling devices: Material handling is an important activity in the industries. A large part of indirect labour employed in an industry is engaged in handling of materials. It has ... material handling and provides proper working conditions. 6. Reduced in process inventory.

Description : Explain the various steps for planning a process for product from raw material to finished product in an industry.

Last Answer : 1. Analysis of Product and its specification: - During analysis, following parameter should be considereda. Drawing and specification of product. b. Quality of product. c. Number of parts/components per ... and fixing the rates of payment. 11. Prepare the route sheet and operation sheet.

Description : Explain the design principles of plant layout.

Last Answer : Design Principles of Plant Layout: S.N. Design Principles Description 1 Principle of Integration All the plant facilities should be fully integrated into a single operating unit ... should be utilized in an optimum manner so as to result in minimum initial capital investment.

Description : Enlist any four factors which affect selection of material handling system. Explain which type of material handling system is suitable for: (i) Unloading two wheelers from truck ii) Stacking of pallets in store racks.

Last Answer : Four Factors affecting Selection of Material Handling System: [1] Adaptability and Flexibility [2] Type of Material to be handled [3] Type of Layout [4] Type of Production [5] ... [11] Cost of installation and handling Suitable Material Handling Devices for Following Activities:

Description : Explain how Gantt chart is used in project planning with proper example. 

Last Answer : Use of Gantt Chart in Project Planning: Gantt Chart is a project planning tool that can be used to represent the timing of tasks required to complete a project. Because Gantt chats are simple to ... a chart, which are used to record the actual operating times and delays of workers and machines.

Description : Explain the concept of production system with proper input output model.

Last Answer : Concept of Production System: The Production System of any organization is that part which produces the organizations products. [1] Production is the basic activity of any organization and all ... feedback system about the activities, which is essential to control and improve system performance.

Description : Explain tactile sensors in robots

Last Answer : Tactile Sensors:- Tactile sensors provide the robot with the capability to respond to contact forces between itself and other objects within its work volume. Tactile sensors can be divided ... magnitude of the contact force. Strain gauge devices are typically employed in force measuring sensors.

Description : Explain pull and push types of manufacturing system

Last Answer : Pull Type Manufacturing System: [1] Just in Time (JIT) is a pull system which is also known as Make to Order Production. [2] Pull System means that parts are produced to order and the ... represented by "Make to Stock" (MTS) in which the production is not based on actual demand.

Description : Explain any two clamping devices with neat sketch

Last Answer : [1] Screw clamp:- It is particularly useful when a component is to be gripped on its edges. This arrangement insures easy machining of top surface of work piece. [2] Equalizing clamp: - It ... is operated by simply actuating the handle up or down which locks or unlocks the strap with the work.

Description : State and explain the basic principle to be followed to develop a good plant layout.

Last Answer : Following are the basic principle to be followed to develop a good plant layout. 1. Overall integration: A good layout is one that integrates men, materials, machine and supporting ... to the production process. For this purpose there must be sufficient space between different machines.

Description : Name different types of material handling equipments used in industry. Explain any one with neat sketch.

Last Answer : Types of material handling devices 1.Trucks : i) Power lift : a. Fork lift b. elevating platform ii) Hand Lift. iii) Porters trolley. 2.Tractors and trailers 3. Hoist and cranes: ... bands can also be used. 5. Speed of belt normally ranges from 1 m/s to 70 m/s.

Description : How productivity is measured? Explain any one method of productivity measurement.

Last Answer : Measurement of productivity: - For measurement of productivity, one must find out input and output of the system. To measure the input resources and goods or services supplied is a critical job ... , cutting tools, coolant etc. Material productivity measures in terms of goods produced.

Description : What is meant by 5'S'? Explain each 'S' in details

Last Answer : 5 S' Concept:- 5'S is the name of a workplace organization methodology that uses a list of five Japanese words which are seiri, seiton, seiso, seiketsu and shitsuke constitute the system. ... Eliminate unwanted items. ➢ Maintain the discipline at work place ➢ Improved safety

Description : Explain various configurations with sketches

Last Answer : Robot Configurations 1) Rectangular Configuration:- This uses three perpendicular slides to construct the x, y, z axes. By moving three slides relative to one another, the robot is capable of ... , which provides a substantial rigidity in the vertical direction for many essential tasks.  

Description : State types of mechanical joints used in robots. Explain any one with sketch.

Last Answer : [1] Rotational joint [2] Linear joint [3] Twisting joint [4] Orthogonal & [5] Revolving joint Rotational Joint: Rotational joint can also be represented as R - Joint. This type will allow the ... to the rotational axes. As like twisting joint, the output link spins about the input link. 

Description : Explain any one non tactile sensor used in robot

Last Answer : Non Tactile Sensor  [1] Vision Sensor: Robot vision is made possible by means of video camera, a sufficient light source and a computer programmed to process image data. The camera is mounted ... the input and the stored vocabulary word the robot performs some actions which correspond to the word.

Description : Explain the concept of lean manufacturing

Last Answer : Lean manufacturing or lean production, often simply "lean", is a systemic method for the elimination of waste (" Muda") within a manufacturing process. Lean manufacturing is a production practice that ... T obtained higher customer satisfaction 4) To reduce per unit cost 5) To control inventory 

Description : Explain cylindrical locator with neat sketch 

Last Answer : Cylindrical locators: - Cylindrical locators are very useful when finely finished holes are available for the positioning of components. It is used for locating components having drilled holes. The cylindrical ... jig s body around the locator is undercut to provide space for swarf clearance

Description : Explain general principles of jigs/fixture design

Last Answer : 1. Before planning the design of a tool, compare the cost of production of the work with present tools with the expected cost of production, using the tool to be made. Confirm that the cost of ... nearly as possible opposite to some bearing point of the work to avoid springing. 11. Round all corners

Description : Define process planning. State the factors affecting process planning and explain it.

Last Answer : Definition of Process planning: Process planning can be defined as the systematic determination of the process by which a product is to be manufactured economically and competitively. Factors ... process engineer sufficient time to go details of each aspect to select most economical process.

Description : Define routing. Explain in short various steps in routing procedure.

Last Answer : Definition of routing: - Routing is defined as the decision to follow the path and sequence of operations to be performed on the work piece from one machine to another. Following steps are ... prepared. - Route sheet shows the sequence of operations, their department, machines and tool used.

Description : Explain spherical configuration with sketch.

Last Answer : Spherical configuration  Spherical Configuration: - It uses telescopic arm that can be raised or lowered about a horizontal pivot point. The pivot point is mounted on a rotating base and gives the ... joints provide the robot with the ability to move its arm within a spherical envelope.

Description : Explain degree of freedom in robots.

Last Answer : Degree of freedom in robots. 1. It is term used to describe a robots freedom of motion in three dimensional spacespecifically, ability to move forward and backward, up and down and left and right. ... The three degrees of freedom in the wrist have aeronautical names Pitch, Yaw and Roll or Swivel.

Description : Explain the cycle of Kaizen activity.

Last Answer : Cycle of Kaizen activity. Kai means Change and Zen means for the better. Kaizen is a Japanese term that basically translated to continuous improvement or change to become good is a management concept ... the same. Act according to the action plan. This cycle is also called as PDCA cycle.

Description : Explain the factor affecting process planning.

Last Answer : Factors affecting process planning. a. Size and shape of part: The size and shape of many components decides the basic operations for the manufacturing of pert. For example : For manufacturing ... process engineer sufficient time to go details of each aspect to select most economical process. 

Description : Explain any four factor that affects selection of site.

Last Answer : Factors that affecting on selection of site. 1. Availability of raw material: As far as possible the site selected should be near the source of raw materials so that cost of transportation can be ... attitude: Mindset of the local people is also important, many times they oppose the work. 

Description : Define process planning and explain the steps in process planning.

Last Answer : Process Planning is the selection of a systematic method or process by which the product is to be manufactured economically and competitively. Steps: 1) Study of part drawings and its specifications. ... product. 10) Preparation of route and operation sheet which is also called process sheet.  

Description : Explain the different types of Automated guided vehicle system and also state its functions and applications.

Last Answer : Types of AGV  1. Wire guided AGVs: These AGVs follow as inductive wire as guided path. 2. AGVs having optical/chemical/magnetic guide path: These AGVs use a strip of ... Manufacturing system and Computer integrated manufacturing system. 3. Non industrial applications like hospitals, offices etc.

Description : Explain with neat sketch any two material handling devices used in mass production.

Last Answer : 1.Roller conveyors may be gravity aided or powered and are employed for transporting products having flat bottoms. Bigger jobs can be handled as they are, whereas small items are put in boxes, tins ... and unloading of the products.   4.Screw Conveyor, Pneumatic Conveyor, Elevated Conveyor . 

Description : Explain technique for improving productivity.

Last Answer : Techniques for improving productivity  1) Work Study:- It aims ,one to find out the best method of doing job and another one is to find the time taken to do it. This ... TQM results in grater customer satisfaction, fewer defects, less waste, improved profitability and increased productivity.

Description : What are actuators? Explain Mechanical and Hydraulic actuators type with advantages and disadvantages.

Last Answer : Actuators:- An actuator is a component of a machine that is responsible for moving or controlling a mechanism or system. Mechanical Actuator:- A mechanical actuator functions to ... the control of the system due to the transmission lines and oil viscosity changes from temperature

Description : Explain the different recording techniques used in method study. Also outline process chart for checking diameter of 50mm of shaft.

Last Answer : Different recording techniques used in method study: Process charts are used to record the data systematically so that none of the information needed for study and analysis is missed. A. Chart indicating ... area. However, there is no indication of the direction or speed of motion.

Description : Explain the robot anatomy and structure with sketch. 

Last Answer : Robot Anatomy: Robot anatomy concerns with the physical construction and characteristics of the body, arm, wrist which are components of the robot manipulator. Most robots are mounted on a base. The body is ... 6. Drive: The drive is the motor that moves the links into their designated position.