Draw a sketch and explain how to find height of chajja or slab using dumpy level.

1 Answer

Answer :

image

Explanation :

1. First the back sight reading is taken on floor level whose RL is known to us; from which RL of instrument axis can be find out by adding RL of BM and BS reading.

2. Now the inverted staff is kept touching to bottom of slab and from same instrument station the reading is taken on it.

3. Then RL of chajja is calculated by adding RL of instrument axis to inverted staff reading.

4. Finally height of chajja is calculated as RL of slab bottom –  RL of floor top.

Related questions

Description : State and explain temporary adjustments of dumpy level.

Last Answer : 1. Setting up the level. a. The level fixed on tripod. b. The legs of tripod stand are well spread so that the level will remain stable on tripod. c. Bring all the three foot screws ... screw till the image is distinct and clear. The cross hair on the diaphragm should also be seen clearly. 

Description : State the fundamental axes and mention their relationship for a dumpy level.

Last Answer : Fundamental axis of dumpy level are as follows; i) The vertical axis ii) The axis of bubble tube iii) The line of collimation iv) The axis of the telescope Relationship between ... iii) Axis of telescope and line of collimation should coincide when dumpy level is correctly leveled.

Description : State fundamental lines and their relationships with each other of dumpy level.

Last Answer : Fundamental axes of dumpy level : i) The vertical axis ii) The axis of bubble tube iii) The line of collimation iv) The axis of the telescope Relations of Fundamental axes : i) The ... to the axis of the bubble tube. iii) Axis of telescope and line of collimation should coincide.

Description : State fundamental axis of dumpy level and give their relationship 

Last Answer : Fundamental axes of dumpy level : i) The vertical axis ii) The axis of bubble tube iii) The line of collimation iv) The axis of the telescope Relations of Fundamental axes : i) The ... parallel to the axis of the bubble tube. iii) Axis of telescope and line of collimation should coincide. 

Description : State advantages of Auto-Level over dumpy level. 

Last Answer : 1) Auto level gives quick and easy leveling with less effort than dumpy level. 2) It is most accurate and precise which gives least error about 0.5 to 0.8 in 5 km. 3) It is simply ... readings to read; which reflects inverted in some dumpy level. 5) It gives more operational comfort to surveyor. 

Description : State any two desired relationship between fundamental axes of dumpy level.

Last Answer : Following are the desired relationship between fundamental axes of dumpy level. 1. The axis of level tube should be perpendicular to the vertical axis. 2. The line of collimation should be parallel to ... of bubble (level) tube. 3. Axis of telescope and line of collimation should be coinciding.

Description : Draw sketch and explain method of traversing of plane table surveying. 

Last Answer : Procedure: 1.Set plane table over station A use plumbing fork for transferring station point from ground on sheet. Draw the direction of magnetic meridian with the help of compass. 2. With the ... scale Similarly, the table can be set at other successive station and traverse is completed.

Description : Draw a neat lebelled sketch of optical square. Explain its working.

Last Answer : Working of optical square1. Optical square works on principle of optical square to set perpendicular offset 2. Keep ranging rods at point B and C as shown in fig. 3. Observe the ... matched each other point D can be marked on ground and distance CD is measured as perpendicular offset.

Description : Draw a neat sketch of optical square. Explain its working.

Last Answer : Optical Square: Working: The optical square consists of circular box 50 mm in diameter, 12.5 mm in depth. The box has three slits as A,B, and C. bb' is horizon glass, half silvered i.e ... the point on the chain line where the offset can be dropped to meet point J as shown in fig.  

Description : Draw sketch and write the procedure for setting offset to the left or right side of suvey line with open cross-staff.

Last Answer : Procedure for setting offset with open cross staff : 1. Keep the ranging rods at point P(fixed on survey line) and at point A1 approximately. 2. The cross staff with stadia rod is fixed ... can be fixed and perpendicular offset AB is said to be set to given survey line PQ in left side.

Description : Draw a neat sketch of an arrow with dimensions.

Last Answer :  neat sketch of an arrow with dimensions

Description : Draw a neat labeled sketch of 30m chain.

Last Answer : neat labeled sketch of 30m chain

Description : Draw a neat sketch of prismatic compass and label its component parts

Last Answer : Sketch of prismatic compass and label its component parts

Description : Draw the sketch of chain triangulation and label different lines.

Last Answer : AB – Base line AC, CD, DE, AE, EB - main survey lines DD’ – Check line. ab – Tie line.

Description : Draw labeled sketch of prismatic compass.

Last Answer : Sketch of prismatic compass :

Description : Draw sketch of optical square and state its principle.

Last Answer : The optical square is an instrument used to set perpendicular offset on the chain line. The optical square works on the principle of optics. Principle of optical square: The angle between the incident ray and reflected ray is twice the angle between mirrors.

Description : Describe with neat sketch, the optical square and explain its principle.

Last Answer : Principal of optical square :- the angle between the first incident ray and the last reflected ray is twice the angle between the two mirrors OR If there are two plane mirrors whose reflecting surfaces ... is 450 while that between the first incident ray and last reflected ray is 900 .  

Description : What are offsets? How are they taken and recorded? Explain with sketch.

Last Answer : Offsets are lateral measurement to the base line. They are Located by judgment if short And by instruments (optical square or cross staff) if long and measured by metallic tape and shown with their chainages on base line

Description : Explain the radiation method of plane table survey with neat sketch. 

Last Answer : This method is used when all the points to be plotted are visible from single instrument station. Steps are: 1. Select a suitable point P on the ground such that all the details are visible from it. 2. Center and ... , pc, pd, pe respectively. Join a, b, c, d, and e to give the outline.

Description : Explain dip of magnetic needle with neat sketch. 

Last Answer : i) The inclination of the magnetic needle with the horizontal is called as magnetic dip of the needle. ii) Ordinary needle if perfectly balanced on pivot, remains in horizontal position. But when the needle ... sliding weight is attached on the side of the needle which is at higher position.  

Description : Explain reciprocal ranging with neat sketch. 

Last Answer : Reciprocal ranging is done when ends of survey line are not intervisible due to hill intervening or ends of survey line are at far distance apart. Step wise procedure reciprocal ranging: 1. Let A and B be ... chained. 8. This method can also be used in ranging a line across a valley.  

Description : Explain the procedure for profile leveling with neat sketch. 

Last Answer : 1) Let PQR be the given line of section.   2) Mark point at 10 m intervals on this line. 3) Level is set up on a firm ground at a suitable point I1. 4) Temporary adjustment of level is done and B. ... and set up on firm ground at I2 as before. 10) B.S is taken on CP1 and new HI is calculated  

Description : Explain ‘Intersection Method’ of plane table surveying with neat sketch. Also give situation when intersection method is used.

Last Answer : 1. Lay out a base line AB and measure it and Plot a distance ab' on sheet using any scale. 2.Set up instrument at A' with a' over A' 3.Orient the table by placing alidade ... the case of the survey of mountainous country. 5. The only linear measurement required is that of a base line.

Description : Explain Fly Levelling with neat sketch. State situation under which fly levelling is needed.

Last Answer : Ans: When DifferentialLevelling is done in order to connect a bench mark to the starting point of the alignment of any project, it is called as fly levelling. Fly levelling is also done to connect ...  ii)if distance is more between two points.  iii)if there obstacles between the two points.  

Description : Explain indirect ranging with neat sketch

Last Answer : Step wise procedure indirect ranging i.e. reciprocal ranging- Let A and B be the two station with rising ground or a hill intervening between them even i)Select any two intermediate station say M1 and N1 ... there position will be changed until finally they are both on the line A B exactly.  

Description : Explain with neat sketch the procedure of radiation method of plane tabling.

Last Answer : 1. The table is set at suitable station e.g. P from where all stations can be sighted and measured. 2. After centering and leveling, mark station P as P' on sheet. 3. Suppose stations A, B, C, and D are ... marked as pa. 5. Similarly station B, C and D are bisected and marked as b, c and d.

Description : Explain with neat sketch graphical adjustment of closing error.

Last Answer : Procedure: 1. Plot the traverse e.g. A'BCDEA to suitable scale and obtain magnitude and direction of closing error. 2. Draw a straight line A'BCDEA to some suitable scale representing the ... plotted points and locate new position of station points to give correct traverse A'B'C'D'E'A'.

Description : With neat sketch, explain the included angle method of plotting compass traverse. 

Last Answer : 1. Calculate all included angles of the traverse from observed bearings of the lines. e.g. <A, <B, <C, <D, <E  2. Check sum of included angles as equal to ( ... coincide with starting station (in case of closed traverse). If there is closing error, it needs to be corrected. 

Description : Explain with neat sketch the procedure of reciprocal ranging.

Last Answer : Reciprocal ranging / Indirect ranging Procedure: Let A and B be two survey stations. They are not mutually visible due to high ground between them. Let two assistant stands at M1 and N1 as ... and N1 which are nearer to line AB. Repeat same process until points M and N are established. 

Description : Explain with neat sketch method of stepping of chaining on sloping ground.

Last Answer : Procedure : To measure the horizontal distance between points A & B on sloping ground following steps should be followed ( Refer above figure.) 1. Starting from point A, the chain is unfolded and ... . Finally calculate total chained distance as d(AB) = d(AP1) + d(P2P3) + d(P4P5)

Description : Explain principle of optical square with neat sketch.

Last Answer : Principle of optical square :- The angle between the first incident ray and the last reflected ray is twice the angle between the two mirrors In the case of optical square the angle between the mirrors is 45° while that between the first incident ray and last reflected ray is 90°.  

Description : Explain the process of chaining on sloping ground by stepping method with neat sketch.

Last Answer : The procedure to measure horizontal distance between the points A and B on sloping ground is as follows. 1. Two persons-leader and follower are required for chaining. 2. The follower holds the end of chain at A. The leader goes ... between A and b L = AM, + MN' + NO' + OP' + PQ' + QB'

Description : Explain reciprocal levelling with neat sketch. 

Last Answer : Reciprocal levelling is adopted i) To find the difference in level accurately Between the two points considerably apart. ii) When it is not possible to set up the level in between the two points ... true difference is equal to the mean of the two apparent differences of level between A and B 

Description : Define base line and check line with neat sketch. 

Last Answer : 1)Base Line : The longest line running roughly through the middle of the area to be surveyed is known as base line 2) Check line: The line joining the apex of a triangle to some fixed point on the ... A line joining some fixed point on any two sides of a triangle is known as check line. 

Description : Define ‘ Fore bearing ’ & ‘ back bearing ’ of line with a neat sketch

Last Answer : Fore bearing : The bearing of line observed in the direction of progress of survey is called fore bearing of the line. Bearing of line AB is observed at A' towards B' is called as fore bearing of the line ... The bearing observed at B' towards A' is called as back bearing of the line AB'  

Description : With neat sketch, write the procedure of measurement of fore bearing with compass.

Last Answer : For measuring fore bearing of line AB, i) Place the compass over station A, center and level it.  ii) Looking through eye slit towards object vane, bisect the ranging rod at station ... which coincides with horse hair at observer end. The observed reading is the fore bearing of line AB

Description : Differentiate between simple levelling and differential levelling with neat sketch. 

Last Answer : S.N Simple Levelling Differential levelling 1 Instrument is not shifted till the end of survey work.  Instrument is shifted as per requirements. 2 In this difference in elevation between ... elevation between two points is more or any obstacle between them. 4

Description : Describe in brief with neat sketch: i) Base line ii) Check line

Last Answer : i) Base line:  Base line is generally the longest line running roughly through the middle of the area. It is laid on a level ground as far as possible. The whole frame work is built upon this line. ... on the opposite side or a line joining some fixed point on any two sides of the triangle. 

Description : Draw Conventional symbol for i) Embankment ii) Pond or Lake iii) Tunnel iv) Compound Wall

Last Answer : Conventional symbol for i) Embankment ii) Pond or Lake iii) Tunnel iv) Compound Wall

Description : Draw conventional symbol for: i. Cutting ii. Road with bridge iii. Orchard iv. river

Last Answer : conventional symbol for: i. Cutting ii. Road with bridge iii. Orchard iv. river

Description : Draw a "well labelled diagram of 30 m metric chain & state the function of swivel joint & oval rings.

Last Answer : Swivel joint: To turn the handle without twisting the chain. Oval ring: To provide flexibility and fold the chain.

Description : Define the following: (i) Height of instrument (i) Back sight (iii) Fore sight (iv) Axis of bubble tube

Last Answer : i. Height of instrument: It is the reduced level of line of collimation when the leveling instrument is properly leveled. It is obtained by adding the BS reading to RL of bench mark or change point on which the ... when the bubble is at the center of its run i.e. at middle point of the tube.

Description : Define : 1) Change point 2) Height of instrument.

Last Answer : 1) Change point It is point on which fore and back sights are taken. 2) Height of instrument. It is the reduced level of line of collimation when the leveling instrument is properly leveled. It is ... adding the BS reading to RL of bench mark or change point on which the staff reading was taken.

Description : A dumpy level is set up with its eye-piece vertically over a peg . The height from the top of peg to the centre of the eye-piece is 1.540 m and the reading on peg is 0.705 m. The level is then setup over . The height ... in level between and is (A) 2.900 m (B) 3.030 m (C) 0.770 m (D) 0.785 m

Last Answer : (C) 0.770 m

Description : Explain in brief linear measurement using : i) Pacing ii) Digital Tape 

Last Answer : i) Pacing : This method is used only for knowing approximate distance between the objects. In preliminary survey this method can be used for linear measurement. This method consists of counting the ... and compact and measures accurate reading. The maximum measuring length of digital tape is 4.8m 

Description : Explain in brief linear measurements using: {i) Chaining (ii) Digital Tape

Last Answer : i. Chaining:  a. Linear measurement with chain carried out by two chainmen-Leader and follower.  b. The follower keeps the chain handle at starting station point, holds firmly it and directs the ... is at right spot, press the button and tape measures, calculates and displays distance on screen.

Description : State the important points kept in mind while recording the staff readings in level pages with respect first reading, intermediate reading, last reading, change point, carry forward from one page to next page-Remark

Last Answer : 1) First reading is on bench mark point and should be noted in back sight(BS) column 2) Intermediate reading (IS) should be taken on the points between first and last station. 3) Last reading ... column of next page 6) Remark column should have denote First and Last RL along with change points.

Description : Define: i) Level Line, ii) Horizontal Line, iii) Vertical Line iv) Bench Mark. 

Last Answer : j) Level Line: It is line lying in a level surface; it is therefore, normal to the plumb line at all points. ii) Horizontal Line: It is a straight line tangential to the level line at a ... RL determined with reference to the datum line. They serve as reference points for finding RL of new points. 

Description : Define: i) Mean sea level, ii) Station point. 

Last Answer : i) M.S.L: Mean sea level is the average height of the sea for all stages of tides. It is determined by averaging the hourly tide heights over a long period of 19 years at a place.  ii) Station ... is a point which is to be established at a given elevation or it is a point where the Staff is held 

Description : What is Level surface & Datum surface

Last Answer : Level surface : It is surface parallel to the mean spheroidal surface of the earth.  It is normal to the direction of plumb line at all points. Datum surface : It is an arbitrary level ... may be referred. Vertical distances (elevations) of the points are measured with respect to this datum.