Explain Briefing the half yearly schedule maintenance of OH mains?

1 Answer

Answer :

Ans. "(a) Check all the jumper connections (b) Check any connections of the strands of the
conductor (c ) Check and ensure proper earth connection (d) Check proper fixation of insulators,
stay wires, guard wires, etc. (e) Check proper tensioning and connection of service wires."

Related questions

Description : What are the schedule maintenance to be carried out OH mains & UG Cables?

Last Answer : Ans. Following are the schedule to be maintained of HO mains and UG cables. a. OH mains – Every Half yearly b. UG.Cables – Every Yearly. During those schedules, for OH, Guarding condition of insulators, sag in OH line are to be checked for UG cables, cables are to be beggared for their IR values.

Description : How to Make a Workout Schedule

Last Answer : How to Make a Workout Schedule One of the toughest thing about sticking to a workout is finding the time to actually do it. A lot of people end up claiming that they are too busy or ... Your body strength and endurance will have definitely improved, not to mention the health benefits you've earned.

Description : How to Fit Exercise into a Busy Schedule

Last Answer : How to Fit Exercise into a Busy Schedule One of the most common reasons why some people don't exercise at all is that they just couldn't find the time to exercise. Having no time is a very ... you can keep a fit and active body even if you don't have much time for a complete gym workout.

Description : How to Schedule a Business Meeting

Last Answer : How to Schedule a Business Meeting Many people in business today agree that meetings, when held too frequently and when allowed to drag on needlessly, can actually be counterproductive. Meetings should ... tasks on schedule, and at the same time keep your employees productive and well-informed.

Description : Explain on-line maintenance of Rotameter. 

Last Answer : On line maintenance of Rotameter: In a chemical plant, it is a normal practice to do on line maintenance work. This avoids total shutdown of the equipment or plant. This is possible, if proper ... . Thus it is possible to attend maintenance jobs in the line without stopping the production.

Description : Explain functions and responsibilities of maintenance department.  

Last Answer : Functions and duties of plant maintenance department 1)Inspection 2)Engineering 3) Maintenance 4) Repair 5) Overhaul 6)Construction 7) Salvage 8) Clerical work 1)Inspection: i) Inspection of ... , ii) of time progress on jobs pertaining to important features of building and production equipment.

Description : Explain breakdown maintenance. Give any two disadvantages of it.  

Last Answer : Breakdown maintenance: This method of maintenance implies that repairs are made after the equipment is out of order and it cannot perform its normal function any longer. In such situation, ... those plant items which are regulated by statutory provision eg. Cranes, lifts, and pressure vessels.

Description : Explain preventive maintenance. 

Last Answer : Preventive maintenance: It is a system of scheduled, planned maintenance tries to minimize the problem of breakdown maintenance. It is a stich- in- time procedure. It locates weak spots in all equipment ... 8. Lower unit cost of manufacture. 9. Increased equipment life. 10. Better product quality.

Description : Explain predictive maintenance in detail.

Last Answer : Predictive maintenance: Predictive maintenance makes use of human sense or other sensitive instruments such as audio gauges, vibration analyser, amplitude meter , pressure , temperature and resistance ... 4. Pressure, temperature and resistance strain gauges: eg. Excessive temperature of equipment.

Description : Explain the activities carried out during weekly maintenance of 3 ph. Induction motor. 

Last Answer : Activities Carried out During Weekly Maintenance of 3 ph. Induction Motor:  1) Check belt tension. In cases where this is excessive it should immediately be reduces and in the case of sleeve ... and cooled by oil mist systems its important to check the oil mist flow paths/pressure components.

Description : Explain the maintenance of lead acid battery.

Last Answer : Maintenance of lead acid battery: 1) Keep the container surface dry by using dry cloths. 2) Tighten the terminal connections. 3) Battery should not be discharged below a minimum voltage. 4) Never keep battery ... -container embed { position: absolute; top: 0; left: 0; width: 100%; height: 100%; }

Description : Batteries Maintenance –

Last Answer : a) Specific gravity. b) Voltage/Cell. ON Load/OFF Load(2.2V when fully charged and 1.8 when fully discharged.

Description : What are the maintenance schedules of a pumping station and type of starters?

Last Answer : Ans. Following are maintenance schedule of the pumping installation: Switch gear in every quarter and the motor & pump section every half yearly. Starters are DOL starter, star delta starter, Auto T/F starter.

Description : What are the schedules of maintenance done on transformers?

Last Answer : Ans. Following are the schedules of maintenance on transformers. a. Daily maintenance. b. Monthly maintenance. c. Quarterly maintenance. d. Half yearly maintenance. e. Yearly maintenance. f. 5 Yearly maintenance.

Description : Power Maintenance INDICATE TRUE OR FALSE TO THE FOLLOWING

Last Answer : 1) MCB is used in circuits for Overload protection. True or False Ans True 2) We can improve the earth resistance by packing common salt charcoal & water. (True or False) Ans True 3) Silica gel used ... False 15) Shorting of power diode test to be conducted at full load. (True or false) Ans True

Description : Power Maintenance FILL IN THE BLANKS

Last Answer : 1) The process of removing heat from low temperature level and rejecting at high temperature is called. REFRIGERATION. 2) Any substances for change of its state at constant temperature absorbs/give up heat is ... ) The capacity of alternator, batteries & fans in TL coach are 4.5KW, 120Ah & 35W.

Description : Power Maintenance ABBREVIATIONS

Last Answer : 1 W - Watts 2 KW - Kilowatts 3 KWH - Kilowatt Hour 4 KVA - Kilo Volt Amps 5 KVAR - Kilo Volt Ampers Reactive 6 H.P. - Horse Power 7 A.H. - Ampere Hours 8 P.F. - Power Factor 9 R.P.M. - ... L.T.U.G - Low Tension Under Ground 36 P.V.C. - Poly Vinly Chloride 37 H.R.C. - High Rapturing Capacity

Description : Power Maintenance MCQ

Last Answer : 1) Turbine pumps are used up to a suction head of ( b ) a. 1000 ft. c. 20 ft b. 100 ft d. 50 ft 2) The yard stick for provision of Electrical points in staff quarters can be changed by the Zonal railways ... is used for electrical fire ( b ) a. Water c. Foam b. Co2 & dry powder d. None of the above

Description : Septic System Maintenance

Last Answer : Nobody is interested in thinking about what happens when someone forgets to clean his or her septic system in the backyard. We don't need to tell you either. Not draining and cleaning your septic ... its regular cleaning schedule you don't have to worry about the system breaking down anytime soon.

Description : Maintenance and Care: How to clean your Vacuum Cleaner

Last Answer : Maintenance and Care: How to clean your Vacuum Cleaner There are numerous ways to clean your vacuum cleaner, depending on the brand (manufacturer) and design. However, it is best to ... will bother your work area. Remember, safety considerations are important to prevent any unwanted accidents.

Description : Name types of maintenance. 

Last Answer : Types of maintenance: 1. Corrective or breakdown maintenance 2. Scheduled maintenance 3. Preventive maintenance 4. Predictive maintenance

Description : Describe scheduled maintenance. What are its advantages ? 

Last Answer : Scheduled maintenance: Scheduled maintenance is a stich-in-time procedure which is aimed at avoiding breakdowns. Breakdowns can be dangerous to life and hence should be minimized. Scheduled ... , such as lubricating and retightening screws Lower long term costs compared with breakdown maintenance 

Description : Describe online maintenance with respect to rotameter. 

Last Answer : On line maintenance of Rotameter: In a chemical plant, it is a normal practice to do on line maintenance work. This avoids total shutdown of the equipment or plant. This is possible, if proper ... . Thus it is possible to attend maintenance jobs in the line without stopping the production.

Description : Give the importance of plant maintenance. 

Last Answer : Importance of Plant Maintenance : In modern industry, equipment and machinery are a very important part of the total productive effort. With the development of special purpose and sophisticated machines ... and services required by other section of the factory for the performance of their function.

Description : Which of the following circuit breakers has high reliability & minimum maintenance?  (A) Bulk oil type CB (B) Air blast CB (C) Vacuum CB (D) Sulphur hexafluoride CB 

Last Answer : Which of the following circuit breakers has high reliability & minimum maintenance?  (A) Bulk oil type CB (B) Air blast CB (C) Vacuum CB (D) Sulphur hexafluoride CB 

Description : Give procedure for doing safety audit. Explain records to be examined during safety audit. 

Last Answer : Procedure of safety Auditing : Safety audit is carried out by a team whose members are not involved in the plant or activity being audited. The expertise of the team should be compatible with ... . Maintenance procedure records. 14. House keeping inspection records. 15. Record of previous audits.

Description : Explain factories Act 1948 with respect to (i) General duties of occupier (ii) Approval, licencing and registration of factories (iii) Duties of the inspector. 

Last Answer : Factories Act 1948: (i) General duties of occupier:  (1) Every occupier shall ensure, so far as is reasonably practicable, the health, safety and welfare of all workers while they ... be compelled under this section to answer any question or give any evidence tending to incriminate himself.

Description : Explain safe work place layout in industry. 

Last Answer : Safe work place layout in industry: 1. The layout should be such that every workman has enough space to move and operate. 2. The minimum distance between each equipment should be 75 ... each major hazard. 8. Equipment within process unit should be located with due consideration to potential hazard.

Description : Explain objectives of safety audit.  

Last Answer : Objectives of safety audit: Objectives are: 1. To provide the safe working place to every working staff and management. 2. To identify different level of hazards in each working place ... and correct safety impediments which may result in personal injuries, property damage or business interruption.

Description : Explain information derived from Hazard Analysis (HAZAN).

Last Answer : Information derived from HAZAN: It is the operation in which initial study is done to determine Hazard, effect and its causes. e.g. Manufacturing of product using electricity Hazard could be assumed as ... system cause the accident for storage reactor, pipe line, vessel 3) Find out the initial event

Description : Explain the steps to build a safety strategic plan. 

Last Answer : Steps to build a safety strategic plan: 1. Decide the mission and long range objectives of an organization 2. Collect and analyses the related information of mission, objectives and challenges 3 ... and environmental crisis that can be faced in future. 5. Implement and control the alternative

Description : Explain causes of accident. 

Last Answer : Causes of accident:  Causes of accident in an industry:  1. Technical causes. These are due to un safe condition which is originated from a) Mechanical factors b) Environmental ... vi) Lack of skill and knowledge. vii)Improper attitude towards work viii)Carelessness ix) Inattentiveness.

Description : Explain safety failures which caused Bhopal tragedy. 

Last Answer : Safety failures which caused Bhopal tragedy: 1.During the leakage of methyl Isocynate from the storage tanks of union carbide the water sprayers of the industry was not in working conditions. 2. ... Gas scrubbers were not in working condition. 5. Absence of occupiers in industry at that situation.

Description : Explain events leading to flixborough industrial disaster. 

Last Answer : Events leading to flixborough industrial disaster: The plant at Flixborough produced the raw materials for nylon. The disaster happened during the processing of cyclohexane - a highly inflammable component liquid - when a ... simplest form it's a bit like throwing water on to a burning chip pan." 

Description : Explain Failure Modes and Effect Analysis (FEMA). 

Last Answer : Failure Modes and Effective Analysis (FMEA): FMEA is a design tool used to systematically analyze component failure and identify the resultant effects on system operations. It is a systematic way of identifying ... 4. Human errors are not considered It considers only one failure mode at a time.

Description : Explain the procedure for shut down of a plant. 

Last Answer : Procedure for shut down of a plant: A plant shutdown, or turnaround, is a temporary closure of a building to perform maintenance. The main activities should be preventative in nature with the focus ... fault, the cause of the fault should be found, studied and removed before restarting the plant. 

Description : Explain the term “HAZOP” in brief. 

Last Answer : Hazop (Hazard & operability) study is carried out by application of guidewords to identify all possible deviations from design intent having undesirable effects on safety or operability, ... hazardous situations and to arrive at agreeable options to rectify design deviations and anomalies 

Description : Explain event tree analysis. 

Last Answer : Event Tree Analysis (ETA) : Event tree analysis is a method to illustrate the intermediate and final outcomes which may arise after the occurrence of a selected initial event. This ... operator response or safety system response to the initiating event in determining the potential sequence.

Description : Explain the procedure and plans for safe plant operation. 

Last Answer : Procedure and plans for safe plant operation: 1. Starting sequence should be well defined, written and known to the workers involved in this work. 2. Starting in sequence of utilities like water ... cold oil should be introduced), using heat-exchanger for indirect and gradual heating or cooling etc.

Description : Explain the procedure for Accident and Incident Analysis. 

Last Answer : Accident and Incident analysis is carried out in order to determine the cause or causes of an accident (that can result in single or multiple outcomes) so as to prevent further accidents of ... their maximum time for safety work by providing them information about the hazards in their departments.

Description : List and explain the types of instrumentation is provided for safe plant operation.

Last Answer : Instrumentation provided for safe plant operation: After understanding various types of chemical hazards in foregoing parts, we should process to know instruments, equipment and other control measure. To ... poisonous /explosive gases, various type of glass detector hand models are also available.

Description : Explain basic steps necessary for controlling plant hazards.

Last Answer : Basic steps necessary for controlling plant hazards: 1. Elimination: Physically remove the hazard is the most effective hazard control. For example, if employees must work high above the ... Protective Equipment: This includes gloves, apron, respirators, helmets, safety shoes, goggles atc. 

Description : Explain the procedure of safety audit.

Last Answer : Procedure of safety Auditing : Safety audit is carried out by a team whose members are not involved in the plant or activity being audited. The expertise of the team should be compatible with ... the management on completion of audit followed by a clear and concise written report within two weeks.

Description : During a general briefing at the pre-flight stage, the captain should emphasize: a. The complete delegation of all duties b. The importance of crew coordination c. The priority of departing on schedule d. The avoidance of inadequate handling of controls

Last Answer : b. The importance of crew coordination

Description : During a general briefing at the pre-flight stage, the captain should emphasize: a. The complete delegation of all duties b. The importance of crew coordination c. The priority of departing on schedule d. The avoidance of inadequate handling of controls

Last Answer : b. The importance of crew coordination

Description : Can I reset the regulator on my gas grill?

Last Answer : Sounds like the burner is not getting enough air, try cleaning the port where the air and gas mix. Look for little creepy crawlers in the port.

Description : How are public access e-scooters and e-bikes that are scattered all over the city maintained?

Last Answer : They’ve been very controversial. There are lots of articles on rental scooters that you’ll find if you google them. But yes, people do collect them at night and recharge them as contractors to the rental companies, if the scooters haven’t been stripped, dismantled, or thrown into a body of water.

Description : What can I do to protect my XBox 360?

Last Answer : the red rings come from overheating. When it gets hot to the touch or you hear the inner fan working overtime, take a break. Also, you can buy an intercooler fan that plugs on the back for about $15 at gamestop.

Description : Is there a good way of removing scratches from glass?

Last Answer : answer:http://www.rkdm.com/liquidlense/ There you go!

Description : Describe the sampling technique for petrochemical industry. 

Last Answer : Sampling technique for petrochemical industry: In the petrochemical industry, representative samples of liquid petroleum gas and other high vapor pressure gases and liquids are needed for process monitoring, ... quality, protect plant assets, and keep operators, the public and the environment safe.