What is the speed restriction to be observed for train passing?
 (i) Necessary speed restriction shall be observed until the grinding operation is  over.*
 (ii) 30KMPH
 (iii) 45 KMPH
 (iv) Not required

1 Answer

Answer :

(i) Necessary speed restriction shall be observed until the grinding operation is  over.*

Related questions

Description : Speed restriction required for using CC cribs as temporary arrangement is a) 20 kmph* b) 40 kmph c) 35 kmph d) 30 kmph

Last Answer : a) 20 kmph*

Description : Minimum speed restriction to be imposed for Track renewal is:- (a) Stop dead & 10 Kmph (b) 10 Kmph (c) 15 Kmph (d) 20 Kmph*

Last Answer : (d) 20 Kmph*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : Defect of lack of fusion is mainly due to? (i) Improper heating.* (ii) Improper Gap (iii) Improper grinding (iv) None of above

Last Answer : (i) Improper heating.*

Description : Defect of High joint is due to ? (i) Early trimming of weld (ii) Excess provision of height during alignment.* (iii) Early grinding of weld (iv) None of above

Last Answer : (ii) Excess provision of height during alignment.

Description : Defect of low joint is due to? (i) Excess height (ii) Early trimming of weld (iii) Early grinding of weld (iv) Nil/Less provision of height during alignment.

Last Answer : (iv) Nil/Less provision of height during alignment.

Description : Defect of cracks in weld is mainly due to? (i) Early opening of mould.* (ii) Early trimming of weld (iii) Early grinding of weld (iv) None of above

Last Answer : (i) Early opening of mould.*

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : What is the Highest speed of train in Indian Railway a. 140 KMPH b. 120 kmph c. 160 kmph* d. 130 kmph

Last Answer : c. 160 kmph*

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : Speed restrictions is suggested for distressed bridges on Group II a) upto maximum of 15 kmph b) 25 kmph to 50 kmph* c) 75 kmph d) 60 kmph

Last Answer : b) 25 kmph to 50 kmph*

Description : Weather traffic block is required for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.

Description : Weather protection of track is required during block for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : A certain thing is thrown twice from a place with the gap of 45 minutes between the two shots. A girl approaching this point in a train heard the second shot 44 minutes after she heard the first shot. What is the speed of train ... travels at 660 m/s? a) 62 km/hr b) 54 km/hr c) 48 km/hr d) 27 km/hr

Last Answer : B Actual time between the two shots being fired = 45 minutes. If a girl was stationary she would have heard the shots after 44 minutes. But since the train was moving towards the source, she heard the second shot after ... = (15 *18/5) km/hr =54 km/hr Hence the speed of the train is 54 km/hr

Description : Speed restrictions is suggested for distressed bridges on Group I a) upto maximum of 15 kmph* b) 25 kmph c) 50 kmph

Last Answer : a) upto maximum of 15 kmph*

Description : Flat tyre causes maximum damage at a speed of (a) 90 to 100 kmph (b) 25 to 30 kmph* (c) 10 to 15 kmph (d) 15 to 20 kmph

Last Answer : (b) 25 to 30 kmph*

Description : Permissible speed of Turnout with 1 in 8.5 curved switches a. 40 kmph b. 25 kmph* c. 15 kmph d. 20 kmph

Last Answer : b. 25 kmph*

Description : Permissible speed of Turnout with 1 in 12 curved switches a. 40 kmph* b. 25 kmph c. 15 kmph d. 20 kmph

Last Answer : a. 40 kmph*

Description : What is the frequency of track recording of the sections having speed more than 110 kmph to 130 kmph a. 4 Months b. 2 Months c. 6 Months d. 3 Months

Last Answer : d. 3 Months

Description : The maximum permissible speed recommended for Indian Railways for 1 in 8 and half crossing is a)16 kmph* b) 20 kmph c)24 kmph

Last Answer : a)16 kmph*

Description : Track structure for private siding with operating speed 50 to 80 kmph is the same as track structure as specified for a)Group A route b) Group B route c) Group D route d)Group E route*

Last Answer : d)Group E route*

Description : Track Structure for private siding with operating speed of 80 to 100 kmph is same as the track structure as specified for a) Group B route b) Group A route c) Group D route* d)Group C route

Last Answer : c) Group D route*

Description : Lowest level of staff/supervisor competent for passing of first train after buckling in LWR/CWR. a. PWI* b. PWS c. Gangmate d. Keyman

Last Answer : a. PWI*

Description : Torch is kept at height from top surface of rail head? (i) 30 to 55 mm (ii) 35 to 40 mm (iii) 40 to 45 mm

Last Answer : (iii) 40 to 45 mm

Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted

Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*

Description : What is speed restriction on deep screening site done by BCM and tamped by machine followed with DGS? (a) 20 (b) 30 (c) 40* (d) 10

Last Answer : (c) 40*

Description : Power required for a train weighing 200 Mg to move at a uniform speed of 60 Kmph up an incline of 1 in 200 is (Resistance due to friction is negligible) a.16.67 KW b.163.5 KW c.1000 KW d.9810 KW e.Tapered bearing

Last Answer : b. 163.5 KW

Description : An accident has taken place at out station and main line is blocked and relief train is to be turned out without medical car. The hooter shall be: a. 3 long b. 4 long* c. 4 long, 1 short d. 3 long, and 1 short

Last Answer : b. 4 long

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*

Description : The gap between probing face and probing shoe should be. (i) 0.4 mm (ii) 0.2mm * (iii) 3mm (iv) 1mm.

Last Answer : (ii) 0.2mm *

Description : On Rajdhani routes testing frequency of rail testing for rail section of 60kg with annual GMT 80, will be. (i) 4 months (ii) 1 1⁄2 months (iii) 1 months* (iv) None of above.

Last Answer : (iii) 1 months*