Speed restrictions is suggested for distressed bridges on Group II
a) upto maximum of 15 kmph
b) 25 kmph to 50 kmph*
c) 75 kmph
d) 60 kmph

1 Answer

Answer :

b) 25 kmph to 50 kmph*

Related questions

Description : Speed restrictions is suggested for distressed bridges on Group I a) upto maximum of 15 kmph* b) 25 kmph c) 50 kmph

Last Answer : a) upto maximum of 15 kmph*

Description : Special inspection of distressed bridges Group II shall be carried out by Inspector (Concerned) is a) Once in three months* b) Once in two months c) Once in a month d) Once in six months

Last Answer : a) Once in three months*

Description : In arch bridges, Cracks/ lean/ bulge in parapet walls, Bulging or separation of spandrel from arch barrel, are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Flat tyre causes maximum damage at a speed of (a) 90 to 100 kmph (b) 25 to 30 kmph* (c) 10 to 15 kmph (d) 15 to 20 kmph

Last Answer : (b) 25 to 30 kmph*

Description : Special inspection of distressed bridges shall be carried out by Asst. Engineer is a) Once in three months b) Once in two months* c) Once in a month d) Once in six months

Last Answer : b) Once in two months*

Description : Permissible speed of Turnout with 1 in 8.5 curved switches a. 40 kmph b. 25 kmph* c. 15 kmph d. 20 kmph

Last Answer : b. 25 kmph*

Description : Permissible speed of Turnout with 1 in 12 curved switches a. 40 kmph* b. 25 kmph c. 15 kmph d. 20 kmph

Last Answer : a. 40 kmph*

Description : Track structure for private siding with operating speed 50 to 80 kmph is the same as track structure as specified for a)Group A route b) Group B route c) Group D route d)Group E route*

Last Answer : d)Group E route*

Description : Cracks in return walls/ wing walls or Slight tilting/ bulging of abutments are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Settlement of foundations or Tilted piers and abutments will be considered as distressed bridge as a) Group I* b) Group II c) Both of the above d) None of the above

Last Answer : a) Group I*

Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm

Last Answer : a) 25 mm*

Description : 32 kmph 11.What is the weight per meter length of 52 kg Rail? a. 54.14 kg b. 50.25 kg c. 51.89 kg* d. 53.85 kg

Last Answer : c. 51.89 kg*

Description : Minimum speed restriction to be imposed for Track renewal is:- (a) Stop dead & 10 Kmph (b) 10 Kmph (c) 15 Kmph (d) 20 Kmph*

Last Answer : (d) 20 Kmph*

Description : Track Structure for private siding with operating speed of 80 to 100 kmph is same as the track structure as specified for a) Group B route b) Group A route c) Group D route* d)Group C route

Last Answer : c) Group D route*

Description : The maximum permissible speed recommended for Indian Railways for 1 in 8 and half crossing is a)16 kmph* b) 20 kmph c)24 kmph

Last Answer : a)16 kmph*

Description : What is the speed restriction to be observed for train passing? (i) Necessary speed restriction shall be observed until the grinding operation is over.* (ii) 30KMPH (iii) 45 KMPH (iv) Not required

Last Answer : (i) Necessary speed restriction shall be observed until the grinding operation is over.*

Description : The total number of bridges on I.R.is about a)1 Lac b)1.25 Lacs* c)1.50 Lacs d)2 Lacs

Last Answer : b)1.25 Lacs*

Description : In case of distressed bridge category II, ADEN shall inspect the bridge

Last Answer : once in 6 months

Description : Maximum distance apart of trolley refuges on bridges with main spans of 100metre or more is i. 50 mtr j. 100 mtr k. 200 mtr l. a refuge over each pair*

Last Answer : l. a refuge over each pair*

Description : Speed restriction required for using CC cribs as temporary arrangement is a) 20 kmph* b) 40 kmph c) 35 kmph d) 30 kmph

Last Answer : a) 20 kmph*

Description : What is the frequency of track recording of the sections having speed more than 110 kmph to 130 kmph a. 4 Months b. 2 Months c. 6 Months d. 3 Months

Last Answer : d. 3 Months

Description : What is the Highest speed of train in Indian Railway a. 140 KMPH b. 120 kmph c. 160 kmph* d. 130 kmph

Last Answer : c. 160 kmph*

Description : In case of bridge is distressed category I then special restriction of___hall be imposed

Last Answer : 15 kmph

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted

Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : Height of crucible is kept from top surface of mould? (i) 30 mm (ii) 40 mm (iii) 50 mm* (iv) 60 mm

Last Answer : (iii) 50 mm*

Description : A man in a train notices that he can count 21 telephone posts in one minute. If they are known to be 50 meters apart, then at what speed is the train travelling? A.50 kmph B.54 kmph C.60 kmph D.62 kmph E.None of these

Last Answer : Answer – C (60 kmph) Explanation – Number of gaps between 21 telephone posts = 20 Distance traveled in 1 minute = (50 x 20) m = 1000 m = 1 km Speed = 60 km/hr

Description : What is the width of Head of 52 kg Rail section a. 70 mm b. 75 mm c. 67 mm* d. 60 mm

Last Answer : c. 67 mm*

Description : The ratio of maximum cant e and gauge G in India is about a)1 / 100 b) 1 / 50 c)1 /10* d) 1 / 25

Last Answer : c)1 /10*

Description : P.V.C. pipes can withstand pressure bead of water upto  (A) 25 m  (B) 50 m  (C) 75 m  (D) 100 m 

Last Answer : (D) 100 m 

Description : Rise of water table in cohesion-less soils upto ground surface reduces the net ultimate bearing capacity approximately by (A) 25 % (B) 50 % (C) 75 % (D) 90 %

Last Answer : (B) 50 %

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : bridge foundation having less then 2M depth below bed level in case of arch bridges and 1.2M depth below bed level in case of other bridges is termed as

Last Answer : …Shallow foundation..

Description : If the SSE/SE/JE/ Br. working in the section is not readily available, another SSE/SE/JE may be authorised by …………….. to witness payment on the section. a) DEN b) SSE/SE/JE/ c) AEN (Bridges)* d) Office clerk

Last Answer : c) AEN (Bridges)

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Spacing of Trolley refuges a) Every 100m b) If span is more than 100m, on each pier c) Ballasted deck bridges – every 50m d) All the above*

Last Answer : d) All the above*

Description : Flood level gauge to be marked in a) All important bridges* b) All major bridges c) All minor & major bridges d) All bridges

Last Answer : a) All important bridges*

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Mostly long span rail-cum road bridges are provided with a) rocker & roller bearings b) segmental roller with oil bath* c) Sliding bearings d) centralised bearings

Last Answer : b) segmental roller with oil bath