Finishing tolerances are measured by?
 (i) On 30 cm scale
 (ii) 1 MT straightedge or 10 CM straightedge.*
 (iii) On 15 cm straight edge
 (iv) On 30 cm straight edge

1 Answer

Answer :

(ii) 1 MT straightedge or 10 CM straightedge.*

Related questions

Description : Which gauge is used to measure finishing tolerances . (i) Tilted gauge (ii) Filter gauge (iii) Meter gauge (iv) Filler gauge.*

Last Answer : (iv) Filler gauge.*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : Distance between the two detonators should be (i) 15 Mt. (ii) 10 Mt.* (iii) 20 Mt (iv) None of the above

Last Answer : (ii) 10 Mt.*

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Ist detonator is planted at a distance of (i) 1200 Mt. from welding site .* (ii) 600 mtrs from welding site (iii) 30 mtrs from welding site (iv) None of the above

Last Answer : (i) 1200 Mt. from welding site .*

Description : Banner flag is planted at a distance of (i) At the site of work (ii) At 1200 mtrs from welding site (iii) At 30 mtrs from welding site (iv) 600 Mt. from welding site .*

Last Answer : iv) 600 Mt. from welding site .

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : In new Rail as well as second hand rails how much end bends of the rails in lateral direction are permitted when checked with one metre straight edge before welding? (i) ± 0.2 mm in lateral direction (ii) ± 0.3 mm in lateral direction (iii) ± 0.5 mm in latera

Last Answer : (iii) ± 0.5 mm in latera

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : Thickness of Lining/Charge is kept? (i) 20 mm. (ii) 25 mm* (iii) 30 mm (iv) As decided by the site supervisor

Last Answer : (ii) 25 mm*

Description : Height of crucible is kept from top surface of mould? (i) 30 mm (ii) 40 mm (iii) 50 mm* (iv) 60 mm

Last Answer : (iii) 50 mm*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : When was the collar painting done ? (i) After the welding * (ii) after one week of welding (iii) After 15 days of welding (iv) None of the above

Last Answer : (i) After the welding *

Description : Normal Reaction time in SPW technique? (i) 17 ± 3 seconds. (ii) 15 ± 3 seconds (iii) 23 ± 3 seconds (iv) 20 ± 3 seconds*

Last Answer : (iv) 20 ± 3 seconds*

Description : The project report of the reconnaissance survey should be accompanied by Index map area at a scale of 1 cm = ---- km. (a) 2.5 km* (b) 5.0 km (c) 10.0 km (d) 15.0 km (e) 20.0 km

Last Answer : (a) 2.5 km*

Description : The project report of the reconnaissance survey should be accompanied by a map of the area at a scale of 1 cm= --- km. (a) 2.5 km (b) 5.0 km (c) 10.0 km (d) 15.0 km (e) 20.0 km*

Last Answer : (e) 20.0 km*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Addition gain of 10 db is used for testing. (i) ‘D’ marked rails on single lines. (ii) ‘D’ marked rails on double lines. (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.* (iv) None of above.

Last Answer : (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.*

Description : What is the app. Weight of 52 kg portion? (i) 10 kg (ii) 11 kg* (iii) 12 kg (iv) None of the above

Last Answer : (ii) 11 kg*

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : The danger level should be marked with a bright red band …… wide centrally over a white band …… wide for a length of……… a) 5 cm, 10 cm, 60 cms* b) 10 cm, 20 cm, 60 cm c) 15 cm, 30 mm, 60 cm d) None of the above

Last Answer : a) 5 cm, 10 cm, 60 cms*

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*

Description : The gap between probing face and probing shoe should be. (i) 0.4 mm (ii) 0.2mm * (iii) 3mm (iv) 1mm.

Last Answer : (ii) 0.2mm *

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : On Rajdhani routes testing frequency of rail testing for rail section of 60kg with annual GMT 80, will be. (i) 4 months (ii) 1 1⁄2 months (iii) 1 months* (iv) None of above.

Last Answer : (iii) 1 months*

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : Total no. of probes fitted on digital double rail tester for rail testing are (i) 12 (ii) 8 (iii) 14* (iv) 16.

Last Answer : (iii) 14*

Description : Tandem rig test with 450 probe for AT weld detects. (i) Horizontal longitudinal defect in weld. (ii) Vertical oriented defect in AT weld.* (iii) Transverse defect in AT weld. (iv) Defect in flange of AT welds.

Last Answer : (ii) Vertical oriented defect in AT weld.*