For high level flush the nominal dia of flush pipe shall be
(a) 32 mm*
(b) 40 mm
(c) 25 mm
(d) None of these

1 Answer

Answer :

a) 32 mm*

Related questions

Description : The diameter of hole for 20 dia rivet shall be a) 23 mm b) 18 mm c) 21.5 mm* d) 22 mm

Last Answer : c) 21.5 mm*

Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm

Last Answer : a) 25 mm*

Description : What is the dia of thimble ? (i) 14-16 mm (ii) 16-18 mm* (iii) 18-20 mm (iv) None of the above

Last Answer : (ii) 16-18 mm*

Description : The length of the countersunk head rivet shank is, when L = length of the rivet, G = length of grip in mm; D = Dia of rivet in mm a) L =G +0.5 D + 1mm for every 4 mm of grip or part thereof * b) b) L =G +0.5 D + 1mm c) L =G +0.5 D d) None of the above

Last Answer : a) L =G +0.5 D + 1mm for every 4 mm of grip or part thereof *

Description : he length of the snap head rivet shank is, when L = length of the rivet, G = length of grip in mm; D = Dia of rivet in mm a) L =G +1.5 D + 1mm for every 4 mm of grip or part thereof * b) b) L =G +0.5 D + 1mm c) L =G +0.5 D d) None of the above

Last Answer : a) L =G +1.5 D + 1mm for every 4 mm of grip or part thereof *

Description : From the distribution main of 40 mm size, number of service pipe of 20 mm size can be taken off are ------- a)3 B) 6* c) 10 d) 12

Last Answer : B) 6*

Description : From distribution main of 40 mm size , number of service pipe of 15 mm size can be taken off are--------- a) 3 b) 6 c) 10 d) 12*

Last Answer : d) 12*

Description : The minimum and maximum clearances of check rails at all BG level crossings shall be a) 51 to 57 mm* b) 44 to 48 mm c) 41 to 45 mm d) 55 to 70 mm

Last Answer : a) 51 to 57 mm*

Description : centre to centre spacing of pile should not be more than __where d is the dia of pile shaft

Last Answer : 4d

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : Facia boards of platform shelters shall have a minimum horizontal clearance of ……. from C.L. of track at a minimum height of 4.61m above RL. a) 2360 mm b) 3660 mm c) 3000 mm d) 1600 mm*

Last Answer : d) 1600 mm*

Description : The embankment width in approach of the bridge shall be a) 5870 mm b) 6525 mm c) 6850 mm* d) 6000 mm

Last Answer : c) 6850 mm*

Description : The minimum vertical clearance in RUB in urban area shall be a) 5870 mm b) 6525 mm c) 5000 mm d) 5500 mm*

Last Answer : d) 5500 mm*

Description : The minimum vertical clearance in RUB in rural area shall be a) 5870 mm b) 6525 mm c) 5000 mm* d) 5500 mm

Last Answer : c) 5000 mm*

Description : The minimum vertical clearance above R.L. to bottom of ROB near the yard shall be a) 6525 mm* b) 5870 mm c) 2360 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Torch is kept at height from top surface of rail head? (i) 30 to 55 mm (ii) 35 to 40 mm (iii) 40 to 45 mm

Last Answer : (iii) 40 to 45 mm

Description : Height of crucible is kept from top surface of mould? (i) 30 mm (ii) 40 mm (iii) 50 mm* (iv) 60 mm

Last Answer : (iii) 50 mm*

Description : .Minimum wing rail clearance opposing nose of crossing on Fan shaped turnout a. 45 mm b. 40 mm c. 41 mm* d. 44 mm

Last Answer : c. 41 mm*

Description : The urinal basin shall be connected with (a) High level floating cistern* (b) Low level floating cistern (c) Automatic floating cistern (d) Any one of the above

Last Answer : (a) High level floating cistern*

Description : Maximum height above rail level of high passenger Platform a. 860 mm b. 900 mm c. 840 mm&* d. 875 mm

Last Answer : c. 840 mm&*

Description : Thickness of Lining/Charge is kept? (i) 20 mm. (ii) 25 mm* (iii) 30 mm (iv) As decided by the site supervisor

Last Answer : (ii) 25 mm*

Description : The depth of frog in a brick is a) 15 mm b) 10 mm c) 6. 25 mm* d) 3 mm

Last Answer : c) 6. 25 mm*

Description : In cement pressure grouting G.I pipes of diameter …… and ……length, should be fixed in drilled holes a) 12 to 20 mm, 200 mm* b) 12 to 20 mm, 300 mm c) 12 to 25 mm, 500 mm d) 20 to 25 mm, 300 mm

Last Answer : a) 12 to 20 mm, 200 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : As per IRCA rules, the rejection limits for wheel flange thickness is - (a) 38mm (b) 25.4mm (c) 16mm* (d) 20 mm

Last Answer : (c) 16mm*

Description : 32 kmph 11.What is the weight per meter length of 52 kg Rail? a. 54.14 kg b. 50.25 kg c. 51.89 kg* d. 53.85 kg

Last Answer : c. 51.89 kg*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : Traffic census at a level crossing shall be done by a) A team of SSE/ P Way and SSE/ Works b) A team of SSE/ P Way and Traffic inspector c) A team of SSE/ P Way and Signal Inspector d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Last Answer : d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : Stop boards on either side of approaches of all unmanned level crossings shall be provided at -------------from the centre line of nearest track. a) 3meters b) 5 meters* c) 6 meters d) 10 meters

Last Answer : b) 5 meters*

Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters

Last Answer : a) 3 meters*

Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters

Last Answer : a) 5 meters*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder

Last Answer : a) 25mm above the top flange of girder*

Description : Height of platform of a flag station in cutting above rail level is (a) Same height as Rail level (b) 305 mm above rail level (c) 455 mm above rail level (d) 840mm above rail level*

Last Answer : (d) 840mm above rail level*

Description : The danger level should be marked with a bright red band …… wide centrally over a white band …… wide for a length of……… a) 5 cm, 10 cm, 60 cms* b) 10 cm, 20 cm, 60 cm c) 15 cm, 30 mm, 60 cm d) None of the above

Last Answer : a) 5 cm, 10 cm, 60 cms*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : The maximum height above rail level for B.G. goods platform is ……. Mm (a) 1000mm (b) 1050mm (c) 1065mm* (d) 1075mm

Last Answer : (c) 1065mm*

Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51 mm (b) 57mm* (c) 65mm (d) 70mm

Last Answer : (b) 57mm*

Description : Minimum depth of space for wheel flange form rail level in B.G. is …… mm (A) 35 (B) 38* (C) 42 (D) 45

Last Answer : (B) 38*

Description : .Minimum check rail clearance at Level crossing a. 45 mm b. 51 mm* c. 50 mm d. 57 mm

Last Answer : b. 51 mm*

Description : The pipe wall thickness is minimum for a pipe of given nominal size having schedule number (A) 160 (B) 120 (C) 80 (D) 40

Last Answer : (D) 40

Description : The minimum clear cover for R.C.C. columns shall be (A) Greater of 40 mm or diameter (B) Smaller of 40 mm or diameter (C) Greater of 25 mm or diameter (D) Smaller of 25 mm or diameter

Last Answer : Answer: Option C

Description : For a longitudinal reinforcing bar in a column, the minimum cover shall neither be less than the diameter of bar nor less than (A) 15 mm (B) 25 mm (C) 30 mm (D) 40 mm

Last Answer : Answer: Option D