If ‘W’ is the percentage of water required for normal consistency of cement, water to be
added for determination of initial setting time is
(a) 0.50 W (b) 0.62 W (c) 0.75 W (d) 0.85 W

1 Answer

Answer :

(d) 0.85 W

Related questions

Description : If is the percentage of water required for normal consistency, water to be added for determination of initial setting time, is (A) 0.70 P (B) 0.75 P (C) 0.80 P (D) 0.85 p

Last Answer : Answer: Option D

Description : For determining the compressive strength test on cement is, the percentage amount of water to be added as (Pa = Percentage of water for required consistency) [ A ] 0.25 Pa + 2.5 [ B ] 0.25 Pa + 3.5 [ C ] 0.35 Pa + 2.5 [ D ] 0.35 Pa + 3.5

Last Answer : [ B ] 0.25 Pa + 3.5

Description : Pick up the incorrect statement from the following. For performing compressive strength test of cement (A) Cement and standard sand mortar are used in the ratio of 1 : 3 (B) Water is added at the ... cm 10 cm is used (D) The prepared moulds are kept in a atmosphere of 50% relative humidity

Last Answer : Answer: Option A

Description : The percentage of water for making a cement paste of normal consistency varies from (a) 15 to 25% (b) 25 to 35% (c) 35 to 50% (d) 50 to 60%

Last Answer : (b) 25 to 35%

Description : Initial setting time of cement for asbestos cement products should be not less than (A) 30 minutes (B) 50 minutes (C) 75 minutes (D) 90 minutes

Last Answer : Answer: Option D

Description : If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is, (A) 20 % (B) 25 % (C) 30 % (D) 35 %

Last Answer : (B) 25 %

Description : The gypsum is added to the cement for (a) Providing high strength to the cement (b) Controlling the initial setting time of cement. (c) Lowering the clinkering temp of cement (d) All the above.

Last Answer : (b) Controlling the initial setting time of cement.

Description : For quality control of Portland cement, the test essentially done is (A) Setting time (B) Tensile strength (C) Consistency (D) All the above

Last Answer : D

Description : If d is the economic designed depth of a slab, the thickness of the cement concrete pavement slab at interior, is kept (A) 1.275 d (B) 1.125 d (C) 0.85 d (D) 0.75 d

Last Answer : Answer: Option C

Description : The normal consistency of ordinary Portland cement is about (A) 10 % (B) 20 % (C) 30 % (D) 40 %

Last Answer : Answer: Option C

Description : The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to ... ) 25 person months (B) 75 person months (C) 62.5 person months (D) 72.5 person months

Last Answer : (C) 62.5 person months 

Description : The basic purpose of a retarder in concrete is (A) To increase the initial setting time of cement paste in concrete (B) To decrease the initial setting time of cement paste in concrete (C) To render the concrete more water tight (D) To improve the workability of concrete mix

Last Answer : Answer: Option A

Description : Tricalcium aluminate (C3A) (A) Reacts fast with water (B) Generates less heat of hydration (C) Causes initial setting and early strength of cement (D) Does not contribute to develop ultimate strength

Last Answer : Answer: Option B

Description : For an ordinary Portland cement (A) Residual does not exceed 10% when sieved through IS Sieve No. 9 (B) Soundness varies from 5 to 10 mm (C) Initial setting time is not less than 30 minutes (D) Compressive stress after 7 days, is not less than 175 kg/cm2

Last Answer : (C) Initial setting time is not less than 30 minutes

Description : As compared to ordinary Portland cement, high alumina cement has (A) Higher initial setting time but lower final setting time (B) Lower initial setting time but higher final setting time (C) Higher initial and final setting times (D) Lower initial and final setting times

Last Answer : Answer: Option A

Description : Pick up the correct statement regarding low heat cement from the following: (A) It possesses less compressive strength (B) Its initial setting time is about one hour (C) Its final setting time is about 10 hours (D) All the above

Last Answer : Answer: Option D

Description : To retard the initial setting time of cement, the compound responsible, is (A) Tri-calcium silicate (B) Gypsum (C) Di-calcium silicate (D) Tri-calcium aluminate

Last Answer : Answer: Option B

Description : The initial setting time for ordinary Portland cement as per IS specifications should not be less than (A) 10 minutes (B) 30 minutes (C) 60 minutes (D) 600 minutes

Last Answer : Answer: Option B

Description : According to IS Code , the requirement of an ordinary Portland cement is (a) The residue does not exceed 10% when sieved through is sieve no .9 (b) Its initial setting time is not less than 30 minutes. (c) its expansion is not morethan 10mm for unaerated cement (d) All the above.

Last Answer : (d) All the above.

Description : Initial setting of cement is caused due to (A) Tri-calcium silicate (B) Di-calcium silicate (C) Tri-calcium aluminate (D) Tetra calcium alumino ferrite

Last Answer : Answer: Option C

Description : Soundness test of cement determines (A) Quality of free lime (B) Ultimate strength (C) Durability (D) Initial setting

Last Answer : Answer: Option A

Description : The main constituent of cement which is responsible for initial setting of cement is (A) Di-calcium silicate (B) Tri-calcium silicate (C) Tri-calcium aluminate (D) All of the above

Last Answer : Answer: Option C

Description : The percentage of water for normal consistency, is (A) 5% to 15% (B) 10% to 25% (C) 15% to 25% (D) 20% to 30%

Last Answer : Answer: Option C

Description : Which of the following cables will have the highest launch power capability? ∙ A. 50/125/0.2 ∙ B. 85/125/0.275 ∙ C. 62.5/125/0.275 ∙ D. 100/140/0.3

Last Answer : A. 50/125/0.2

Description : Which ofthe followingcableswill have the highestlaunch power capability? a. 50/125/0.2 b. 85/125/0.275 c. 62.5/125/0.275 d. 100/140/0.3

Last Answer : d. 100/140/0.3

Description : If the sides o a slab simply supported on its edges and spanning in two way are equal, then the maximum bending moment is multiplied by. (a) 0.25 (b) 0.50 (c) 0.75 (d) 0.85

Last Answer : (b) 0.50

Description : The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawlermounted and pneumatic tyre-mounted machines would be respectively (A) 80 and 90 (B) 90 and 80 (C) 85 and 75 (D) 75 and 83

Last Answer : (D) 75 and 83

Description : Most chemical plants use an initial working capital amounting to 10- 20% of the total capital investment. But this percentage may increase to __________ percent in case of seasonal products manufacturing plant. (A) 30 (B) 50 (C) 75 (D) 95

Last Answer : (B) 50

Description : Is blood pressure 135 over 85 normal for a 62 year old male?

Last Answer : No - but its common. 135/85 is above "normal" - ideal is 120/80or (slightly) lower.

Description : An area is declared drought affected if its mean rainfall is less than (A) 50 % (B) 60 % (C) 75 % (D) 85 %

Last Answer : (D) 85 %

Description : Vicat's apparatus is used for (A) Fineness test (B) Consistency test (C) Setting time test (D) Soundness test

Last Answer : (B) Consistency test

Description : Vicat apparatus is used for (A) Fineness test (B) Consistency test (C) Test for setting time (D) Test for tensile strength

Last Answer : Answer: Option B

Description : If P, Y and Z are the weights of cement, fine aggregates and coarse aggregates respectively and W/C is the water cement ratio, the minimum quantity of water to be added to first batch, is obtained by the equation (A) 0.1P + 0.3Y + 0. ... + 0.2Y + 0.01Z = W/C P (D) 0.5P + 0.3Y + 0.01Z = W/C P

Last Answer : Answer: Option B

Description : Le Chatelier apparatus is used to determine which of the following properties for cement A) Soundness* b) Initial setting time c) Compressive strength d) Tensile strength

Last Answer : A) Soundness*

Description : Explain the method to determine initial and final setting time of cement.

Last Answer : Procedure: i. Take 400 gm. of cement sample and add 0.85 times water required for its standard consistency to prepare homogenous cement paste. Note down the time at which water is added to cement as T1 min. ... a cement surface as T3 min. viii. Calculate final setting time i.e. FST = T3-T1 min.

Description : A simply supported beam 6 m long and of effective depth 50 cm, carries a uniformly distributed load 2400 kg/m including its self weight. If the lever arm factor is 0.85 and permissible tensile stress of steel is 1400 kg/cm2 ... area of steel required, is (A) 14 cm (B) 15 cm2 (C) 16 cm2 (D) 17 cm

Last Answer : Answer: Option C

Description : Pick out the wrong statement. (A) High early strength cement are made from materials having high silica to lime ratio (B) The function of gypsum in cement is to enhance its initial ... cements are known as silicate cement (D) Major component of greyish Portland cement is tricalcium silicate

Last Answer : (A) High early strength cement are made from materials having high silica to lime ratio

Description : The deleterious materials present in the aggregate (a) Prevent normal hydration of cement (b) Reduce the strength and durability of concrete. (c) Modify the setting action and cause efloresecence. (d) All of the above

Last Answer : (d) All of the above

Description : Percentage of water in buffalo milk is:- a. 65-67 % b. 70-75 % c. 80-85 % d. 87-90 %

Last Answer : d. 87-90 %

Description : What is the characteristic impedance of a single wire with a diameter d= 0.25 mm placed at the center between grounded parallel planes separated by 1 mm apart. The wire is held by a material with a velocity factor of 0.75. A. 85 Ω B. 63 Ω C. 50 Ω D. 75 Ω

Last Answer : D. 75 Ω

Description : The setting and hardening of cement after addition of water is due to a) Binding action of water b) Evaporation of water c) Hydration and hydrolysis of some constituent compounds of cement* d) Additional hardening compounds added to cement

Last Answer : c) Hydration and hydrolysis of some constituent compounds of cement*

Description : Pick out the wrong statement. (A) Dry process is used for the manufacture of cement, when the raw material is blast furnace slag (B) Portland cement is made employing wet process (C) Gypsum is added to Portland cement to lengthen its setting time (D) None of these

Last Answer : (D) None of these

Description : Carbon percentage (by weight) in crude petroleum may be about (A) 65 (B) 75 (C) 85 (D) 95

Last Answer : (C) 85

Description : As per IS : 1172-1963, water required per head per day for average domestic purposes, is  (A) 50 litres  (B) 65 litres  (C) 85 litres  (D) 135 litres

Last Answer : (D) 135 litres

Description : The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is (A) 1.00 m3 (B) 1.25 m3 (C) 1.50 m3 (D) 1.75 m3

Last Answer : (B) 1.25 m3

Description : In the method of voids for determination of the quantity of cement paste, it is assumed that (A) Voids in coarse aggregates are filled by fine aggregates (B) Voids in fine aggregates are filled by ... of fine aggregates is equal to total voids in coarse aggregates plus 10% extra (D) All the above

Last Answer : Answer: Option D

Description : For concreting of heavily reinforced sections without vibration, the workability of concrete expressed as compacting factor should be (A) 0.75 - 0.80 (B) 0.80 - 0.85 (C) 0.85 - 0.92 (D) Above 0.92

Last Answer : Answer: Option D

Description : For high degree of workability , the compaction factor is (a) 0.65 (b) 0.75 (c) 0.85 (d) 0.95

Last Answer : (d) 0.95