Pick up the incorrect statement from the following. For performing compressive strength test of
cement
(A) Cement and standard sand mortar are used in the ratio of 1 : 3
(B) Water is added at the rate of (P/4) + 3.0 percentage of water where P is the percentage of
water for standard consistency
(C) A cube mould of 10 cm × 10 cm × 10 cm is used
(D) The prepared moulds are kept in a atmosphere of 50% relative humidity
cement
(A) Cement and standard sand mortar are used in the ratio of 1 : 3
(B) Water is added at the rate of (P/4) + 3.0 percentage of water where P is the percentage of
water for standard consistency
(C) A cube mould of 10 cm × 10 cm × 10 cm is used
(D) The prepared moulds are kept in a atmosphere of 50% relative humidity