If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks,
the probability of completing the project in 50 weeks and 65 weeks respectively will be
(A) 2.3% and 84.1%
(B) 97.7% and 84.1%
(C) 97.7 % and 15.9%
(D) 15.9% and 97.7%