The aggregates required for one kilometre length of water bound macadam road per meter width
and for 10 mm thickness is
(A) 8 cubic meter
(B) 10 cubic meter
(C) 12 cubic meter
(D) 15 cubic meter

1 Answer

Answer :

Answer: Option C

Related questions

Description : Pavement is said to be flexible if it contains (A) Water bound macadam surface (B) Stabilised soil base constructed of lime cement or tar (C) Bitumen-bound stone layer of varying aggregates (D) All the above

Last Answer : Answer: Option D

Description : For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is (A) Dry rolling, wet rolling, application of screening and application of ... of filler (D) Dry rolling, application of screening, application of filler and wet rolling

Last Answer : Answer: Option C

Description : Select the correct statement. (A) Quantity of binder required for tack coat is less than that required for prime coat (B) Prime coat treatment is given for plugging the voids in water ... the final coat over certain previous bituminous pavements (D) A bitumen primer is a high viscosity cutback

Last Answer : Answer: Option D

Description : Following type of pavement is generally known as flexible pavement (A) Water-bound macadam roads (B) Stabilised soil roads (C) Road constructed with various layers of building material well compacted (D) All the above

Last Answer : Answer: Option D

Description : If the velocities of flow of a stream of 10 m depth recorded by a current meter at depths of 2 m and 8 m are 0.7 m and 0.3 m respectively, the discharge per unit width of the stream in cubic metres, is (A) 2 (B) 3 (C) 4 (D) 5

Last Answer : Answer: Option D

Description : In the penetration macadam construction, the bitumen is (A) Sprayed after the aggregates are spread and compacted (B) Premixed with aggregates and then spread (C) Sprayed before the aggregates are spread and compacted (D) None of the above

Last Answer : Answer: Option A

Description : The desirable camber for straight roads with water bound macadam or gravel surface, is (A) 1 in 33 to 1 in 25 (B) 1 in 40 to 1 in 33 (C) 1 in 150 to 1 in 140 (D) 1 in 160 to 1 in 140

Last Answer : Answer: Option B

Description : For Indian conditions, the water bound macadam roads, are suitable if daily traffic does not exceed (A) 2000 tonnes (B) 2500 tonnes (C) 3000 tonnes (D) 3500 tonnes

Last Answer : Answer: Option A

Description : In water bound macadam roads, binding material, is (A) Sand (B) Stone dust (C) Cement (D) Brick dust

Last Answer : Answer: Option B

Description : The camber of shoulders in water bound macadam roads is (A) Equal to the cross slope of pavement (B) Less than the cross slope of pavement (C) Greater than the cross slope of pavement (D) Zero

Last Answer : Answer: Option A

Description : Which of the following premix methods is used for base course? (A) Bituminous carpet (B) Mastic asphalt (C) Sheet asphalt (D) Bituminous bound macadam

Last Answer : Answer: Option D

Description : If the width of a pavement slab is 7.5 m, thickness 20 cm and working stress 1400 kg/cm2 , spacing of 10 mm tie bars for the longitudinal joint, is (A) 10 cm (B) 20 cm (C) 30 cm (D) 40 cm

Last Answer : Answer: Option C

Description : Pick up the incorrect statement from the following: (A) Tresguet did not provide the top camber for the drainage of surface water (B) Tresguet provided the top camber for the drainage of surface ... (D) Macadam provided a camber to the formation at the dug-up state, to drain percolated water

Last Answer : Answer: Option A

Description : Thickness of broken line markings on multi-lane road for lanes is generally kept (A) 10 cm (B) 12 cm (C) 15 cm (D) 18 cm

Last Answer : Answer: Option A

Description : Thickness of broken centre line markings for a four lane road, is generally kept (A) 10 cm (B) 12 cm (C) 15 cm (D) 18 cm

Last Answer : Answer: Option C

Description : The maximum permissible size of aggregates to be used in casting the ribs of a slab, is (A) 5 mm (B) 7.5 mm (C) 10 mm (D) 15 mm

Last Answer : Answer: Option C

Description : Describe stepwise construction procedure for water bound macadam roads.

Last Answer : The construction procedure of W.B.M. road is discussed below: 1. Preparation of subgrade : The subgrade is prepared to the required grade and camber. 2. Preparation of the base course : After preparing ... by rolling or tamping. 5. Open to traffic : After drying, the road is opened to traffic.

Description : If 50 kg of fine aggregates and 100 kg of coarse aggregates are mixed in a concrete whose water cement ratio is 0.6, the weight of water required for harsh mix, is (A) 8 kg (B) 10 kg (C) 12 kg (D) 14 kg

Last Answer : Answer: Option C

Description : A jet of water of cross-sectional area 20 sq. cm impinges on a plate at an angle of 60? with a velocity of 10 m/sec. Neglecting the friction between the jet and plate (density of water 1000/9.81 kgm-1 sec2 per cubic meter), the ... a.15 - 20 kg b.20 - 25 kg c.5 - 10 kg d.25 - 30 kg e.10 - 15 kg

Last Answer : a. 15 - 20 kg

Description : The inventor of road making as a building science, was (A) Sully (B) Tresguet (C) Telford (D) Macadam

Last Answer : Answer: Option A

Description : The statement, regarding the size of stones used at the wearing surface. "The size of a stone used on a road must be in due proportion to the space occupied by a wheel of ordinary dimensions on a smooth ... dimension is mischievous" was made by (A) Telford (B) Macadam (C) Tresguet (D) Sully

Last Answer : Answer: Option B

Description : The road foundation for modern highways construction, was developed by (A) Tresguet (B) Telford (C) Tresguet and Telford simultaneously (D) Telford and Macadam simultaneously

Last Answer : Answer: Option D

Description : The normal road land width for a major district road in open area, is (A) 45 m (B) 25 m (C) 15 m (D) 12 m

Last Answer : Answer: Option B

Description : If w is the weight of water per cubic metre, Q is the discharge in cubic metres per sec and H is the total head, the required water horse power of the pump, is (A) wQH/15 (B) wQH/360 (C) wQH/220 (D) wQH/550

Last Answer : (A) wQH/15

Description : The bulk density of aggregates, is generally expressed as (A) tonnes/cubic metre (B) kg/cubic metre (C) kg/litre (D) g/cm3

Last Answer : (C) kg/litre

Description : The difference in the reservoir level and the lowest point of the water mains is 180 m. The  expected pressure due to water hammer is 7.5 kg/cm2  in a pressure conduit of diameter 1 m.  Assuming the efficiency of the ... , is  (A) 10 mm  (B) 15 mm  (C) 20 mm  (D) 25 mm 

Last Answer : (C) 20 mm

Description : The stem of a cantilever retaining wall which retains earth level with top is 6 m. If the angle of repose and weight of the soil per cubic metre are 30° and 2000 kg respectively, the effective width of the stem at the bottom, is (A) 51.5 (B) 52.5 (C) 53.5 (D) 54.5

Last Answer : Answer: Option C

Description : A leaf spring consists of 3 extra full length leaves and 14 graduated length leaves. The maximum force that can act on the spring is 70kN and the distance between eyes of the spring is 1.2m. Width and thickness of the ... close the nip. (a) 4332.2N (b) 4674.1N (c) 4985.4N (d) Can't be determined

Last Answer : (b) 4674.1N

Description : For determining the ultimate bearing capacity of soil, the recommended size of a square bearing plate to be used in load plate test should be 30 to 75 cm square with a minimum thickness of (A) 5 mm (B) 10 mm (C) 15 mm (D) 25 mm

Last Answer : Answer: Option D

Description : The minimum thickness of the cover at the end of a reinforcing bar should not be less than twice the diameter of the bar subject to a minimum of (A) 10 mm (B) 15 mm (C) 20 mm (D) 25 mm

Last Answer : Answer: Option D

Description : The nominal thickness of an expansion joint in brick walls, is kept more than (A) 5 mm (B) 10 mm (C) 15 mm (D) 20 mm

Last Answer : Answer: Option D

Description : Water flow to a terminal 3 mm diameter and has an average speed of 2 m/s. What is the rate of flow in cubic meter/mm?  a. 0.0001m³/min  b. 0.076 m³/min  c. 0.085 m³/min  d. 0.097 m³/min

Last Answer : 0.085 m³/min

Description : A cantilever of length 2 cm and depth 10 cm tapers in plan from a width 24 cm to zero at its free  end. If the modulus of elasticity of the material is 0.2 × 106  N/mm2 , the deflection of the free end,  is  (A) 2 mm  (B) 3 mm  (C) 4 mm  (D) 5 mm

Last Answer : (D) 5 mm

Description : What is the relative humidity when the absolute humidity is 3 grams per cubic meter and the air has a capacity of 12 grams per cubic meter? w) 4% x) 9% y) 25% z) 400%

Last Answer : ANSWER: Y -- 25%

Description : I.S. Sieve Nos. 10 mm and 4.75 mm are generally used for grading of (A) Coarse aggregates (B) Fine aggregates (C) Neither (a) nor (b) (D) Both (a) and (b)

Last Answer : Answer: Option D

Description : If a grading curve is horizontal between the portions of 20 mm I.S. Sieve and 4.75 mm I.S. Sieve, the graded aggregates do not contain (A) 20 mm particles (B) 10 mm particles (C) 4.75 mm particles (D) All the above

Last Answer : Answer: Option D

Description : In a cross joint tensile test the following observations were made: Specimen width 20mm, Material thickness 20mm, Max Load: 180kN, Break position: Parent Plate. What is the UTS? a) 45 kN/mm b) 450 N/mm2c) 39 kN/mm2d) 39 N/mm2

Last Answer : b) 450 N/mm2

Description : The thickness of the topping of a ribbed slab, varies between (A) 3 cm to 5 cm (B) 5 cm to 8 cm (C) 8 cm to 10 cm (D) 12 cm to 15 cm

Last Answer : Answer: Option B

Description : Consider a CSMA/CD network that transmits data at a rate of 100 Mbps (108 bits per second) over a 1 km (kilometre) cable with no repeaters. If the minimum frame size required for this network is 1250 bytes, what is the signal speed (km/sec) in the cable? a. 8000 b. 10000 c. 16000 d. 20000

Last Answer : d. 20000

Description : In a reservoir the average volume of sediment deposition is 0.15 million cubic per year. If the dead storage and total capacity of the reservoir are 8 million cubic metres and 36 million cubic metres respectively, (A) The ... reducing after 60 years (C) Both (a) and (b) (D) Neither (a) nor (b)

Last Answer : (C) Both (a) and (b)

Description : A structure is erected on an impervious clay whose thickness is 12 m. Drainage is possible both at upper and lower surfaces. Coefficient of consolidation is 0.015 cm2 per minute. For attaining 50% consolidation with a ... 20, the number of days required (A) 3233 (B) 3123 (C) 33331 (D) 3313

Last Answer : Answer: Option C

Description : Area of steel required per metre width of pavement for a length of 20 m for design wheel load 6300 kg and permissible stress in steel 1400 kg/cm2 , is (A) 70 kg/sq cm (B) 80 kg/sq cm (C) 90 kg/sq cm (D) 100 kg/sq cm

Last Answer : Answer: Option C

Description : The least thickness of class B cast iron (spun) pipe, is (A) 7.2 mm (B) 7.9 mm (C) 8.6 mm (D) 10 mm

Last Answer : (C) 8.6 mm

Description : A current of 2 A is flowing through a wire of length 4 m and cross-sectional area `1 mm^(2)`. If each cubic metre of the wire contains `10^(29)` free

Last Answer : A current of 2 A is flowing through a wire of length 4 m and cross-sectional area `1 mm^(2)` ... taken by an electron to cross the length of the wire.

Description : To prevent movement of moisture from sub-grade to road pavement at the same level as that of water-table, thickness of a cut off layer of coarse sand, is (A) 15 cm (B) 20 cm (C) 30 cm (D) 45 cm

Last Answer : Answer: Option A

Description : To prevent movement of moisture from sub-grade to road pavement on embankments about 0.6 m to 1 m higher than water table, the thickness of cut off layer of coarse sand used, is (A) 15 cm (B) 20 cm (C) 30 cm (D) None of these

Last Answer : Answer: Option D

Description : Super-elevation on roads in snow bound areas, should generally not exceed (A) 15 % (B) 12 % (C) 10 % (D) 7 %

Last Answer : Answer: Option D

Description : For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are: (A) 70 litres of sand and 120 litres of aggregates (B) 70 kg of sand and 140 litres of ... C) 105 litres of sand and 140 litres of aggregates (D) 105 litres of sand and 210 litres of aggregates

Last Answer : Answer: Option D

Description : If average volume of sediment deposits is one-tenth million cubic metres per year in a reservoir of total capacity 10 million cubic metres, the dead storage will be filled up, in (A) 10 years (B) 15 years (C) 20 years (D) 25 years

Last Answer : (D) 25 years

Description : If longitudinally spanning stairs are casted along with their landings, the maximum bending moment per metre width, is taken as (A) wl²/4 (B) wl²/8 (C) wl²/10 (D) wl²/12

Last Answer : Answer: Option B