. If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.

(A) all

(B) one

(C) at least one

(D) at most one

1 Answer

Answer :

(C) at least one

Related questions

Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Which one of the following is least likely to be a success criterion?  a. A target for the project to receive zero change requests.  b. The date by which the project is to be completed.  c. Delivery of products that meet required specifications.  d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets

Last Answer : D. Salvage value of any sold or disposed assets

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : Configuration management is best described as: a. control in the implementation of changes to project schedules. b. an organization to review proposed changes to the project deliverables ... and documentation. d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : Controlling the changes in the project may affect (A)The progress of the project (B)Stage cost (C)Project scope (D)All of the abov

Last Answer : (D)All of the abov

Description : What are the signs that a project is in trouble? a. The product scope is poorly defined. b. Deadlines are unrealistic. c. Changes are managed poorly. d. All of the above.

Last Answer : d. All of the above.

Description : Project close out check list do not include the followings A. Confirm the customer satisfaction  B. Check that all the project criteria of the project have been met C. Confirm all the deliverables have been given to the customer  D. Changes suggested by Stockholder have not been delivered

Last Answer : D. Changes suggested by Stockholder have not been delivered

Description : Your company has asked you to be the project manager for the product introduction  of its new DeskTop Rock media system. You recently published the project scope  statement. Which ... . Constraints  B. Project specifications  C. Requested changes D. Project configuration management requirements

Last Answer : C. Requested changes

Description : Contract documentation is an input to both the Close Project and Contract Closure  processes. Contract documentation might include all of the following except for which  one?  A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents

Last Answer : D. Procurement audit documents

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Configuration management is best described as:  a. control in the implementation of changes to project schedules.  b. an organisation to review proposed changes to the project deliverables ... and documentation.  d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : )Which of the following fit the category of external risks? 1. Project delays, budget under-runs, movement of city utilities  2. Regulatory, currency changes, taxation  3. Natural disasters, ... , design, social impact  5. Political unrest, budget overruns, size and complexity of the project

Last Answer : 2. Regulatory, currency changes, taxation

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Changes to the project involve moving from: A. Project control stage to project definition stage B. Project control stage to project planning stage C. Project control stage to understanding the project environment stage D. None of the above

Last Answer : A. Project control stage to project definition stage

Description : Which one of the following statements is true? a. An increase in project scope is likely to increase project cost. b. A decrease in the project time is likely to increase project quality. c. ... to decrease project cost. d. A decrease in the project cost is likely to decrease project time.

Last Answer : a. An increase in project scope is likely to increase project cost.

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : Which one of the following statements is true?  a. An increase in project scope is likely to increase project cost.  b. A decrease in the project time is likely to increase project quality.  c. ... to decrease project cost.  d. A decrease in the project cost is likely to decrease project time.

Last Answer : a. An increase in project scope is likely to increase project cost.

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : All of the following statements are true regarding risks except for which one? Choose the least correct answer.  A. Risks might be threats to the objectives of the project.  B. Risks are ... Risks might be opportunities to the objectives of the project.  D. Risks have causes and consequences.

Last Answer : B. Risks are certain events that may be threats or opportunities to the objectives of  the project

Description : )Which form of power is the LEAST effective from the project manager's viewpoint in terms of influencing functional managers? 1. Formal power  2. Expert power  3. Penalty power  4. Referent power

Last Answer : 3. Penalty power

Description : On a project the project manager should strive for a "Quality Level" that : 1. is the highest level possible  2. is as close to the project objectives as possible  3. represents the least cost to the project.  4. Exceeds the specified requirements of the project.

Last Answer : 2. is as close to the project objectives as possible

Description : Scope creep is only a minor factor in projects running over schedule, and every effort  should be made to incorporate any changes into the present system if they would truly be  beneficial.

Last Answer : Ans: False

Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description : Do it because I said to” is the mantra for project managers who use _____ as the  default approach to resolve conflict. Select one: a. collaborating b. compromising c. accommodating d. forcing e. avoiding

Last Answer : d. forcing

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : Adding people to a project team in order to speed up total development time _____.  a. is a standard task in timeboxing  b. is a useful way to meet a tight deadline  c. may actually increase total development time  d. simplifies communication within the team  e. none of the above

Last Answer : c. may actually increase total development time

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____.  a. data communications, time tradeoffs, and ... programming language  d. reports printed and PCA  e. x-rays, extensibility, and operational conversion

Last Answer : b. end-user efficiency, data communications, and reusability

Description : Assume a systems development project effort calculation determines that the system  will require 240 function points. If the developers choose to implement this system in the  C programming language, approximately ... without more information  c. exactly the same  d. much greater  e. much less

Last Answer : e. much less

Description : . A normal system with 400 unadjusted function points would have _____ adjusted  function points when the shortcut method is use to determine the complexity of the  project.

Last Answer : c. 400

Description : . When estimating project time schedules using industry standards, the estimated  project completion time for a systems project would be _____ person-months if the actual  planning phase were completed in 6 person-months.  a. 30  b. 40  c. 17.14  d. 9  e. 50

Last Answer : b. 40

Description : Function points are used to measure the estimated _____ of a project.  a. complexity  b. effort required  c. program size  d. time required

Last Answer : c. program size

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : Project managers can develop task lists for a project with the help of _____.  a. established methodologies  b. system proposals  c. system requests  d. user application hardware  e. user requirements

Last Answer : a. established methodologies

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan

Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan  b. creating the work plan, staffing the project, and controlling ... the deliverables  e. setting the start date, estimating the time, and reading the actual time

Last Answer : b. creating the work plan, staffing the project, and controlling and directing the  project