Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.
Last Answer : d. The awarding of bonuses to senior management.
Description : Which one of the following is least likely to be a success criterion? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.
Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets
Last Answer : D. Salvage value of any sold or disposed assets
Description : A critical success factor for project management is to _____. a. create a work plan b. follow the three steps of project management c. identify most project tasks d. manage the hundreds of tasks
Last Answer : e. start with a realistic assessment of the work
Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers
Last Answer : (B) stakeholders
Description : . It is not wise to identify tasks for a current project using existing methodology, because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.
Last Answer : Ans: False
Description : Configuration management is best described as: a. control in the implementation of changes to project schedules. b. an organization to review proposed changes to the project deliverables ... and documentation. d. creation, maintenance and controlled change of the project deliverables.
Last Answer : d. creation, maintenance and controlled change of the project deliverables.
Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations
Last Answer : A. Define Activities
Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture
Last Answer : b. To reflect new information
Description : Controlling the changes in the project may affect (A)The progress of the project (B)Stage cost (C)Project scope (D)All of the abov
Last Answer : (D)All of the abov
Description : What are the signs that a project is in trouble? a. The product scope is poorly defined. b. Deadlines are unrealistic. c. Changes are managed poorly. d. All of the above.
Last Answer : d. All of the above.
Description : Project close out check list do not include the followings A. Confirm the customer satisfaction B. Check that all the project criteria of the project have been met C. Confirm all the deliverables have been given to the customer D. Changes suggested by Stockholder have not been delivered
Last Answer : D. Changes suggested by Stockholder have not been delivered
Description : Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement. Which ... . Constraints B. Project specifications C. Requested changes D. Project configuration management requirements
Last Answer : C. Requested changes
Description : Contract documentation is an input to both the Close Project and Contract Closure processes. Contract documentation might include all of the following except for which one? A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents
Last Answer : D. Procurement audit documents
Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to make changes to the ... reliability of the project scope and describes the process for verifying and accepting completed deliverables.
Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis for future project decisions.
Description : Configuration management is best described as: a. control in the implementation of changes to project schedules. b. an organisation to review proposed changes to the project deliverables ... and documentation. d. creation, maintenance and controlled change of the project deliverables.
Description : )Which of the following fit the category of external risks? 1. Project delays, budget under-runs, movement of city utilities 2. Regulatory, currency changes, taxation 3. Natural disasters, ... , design, social impact 5. Political unrest, budget overruns, size and complexity of the project
Last Answer : 2. Regulatory, currency changes, taxation
Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated
Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.
Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.
Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated
Description : Changes to the project involve moving from: A. Project control stage to project definition stage B. Project control stage to project planning stage C. Project control stage to understanding the project environment stage D. None of the above
Last Answer : A. Project control stage to project definition stage
Description : Which one of the following statements is true? a. An increase in project scope is likely to increase project cost. b. A decrease in the project time is likely to increase project quality. c. ... to decrease project cost. d. A decrease in the project cost is likely to decrease project time.
Last Answer : a. An increase in project scope is likely to increase project cost.
Description : CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the project is complete? Select one: a. 80% b. 53% c. 45% d. 35% e. 75% Answer - a. 80% 39. As a project manager, John ... paid off the project. d. John's boss is happy. e. John and his team are promoted and get salary increases.
Last Answer : c. John’s client has paid off the project.
Description : PERT (Project Evaluation and Review Technique) analysis is based on A. Optimistic time, Pessimistic time and Most likely time B.Pessimistic time, Optional time, Maximum time C.Optimistic time, Efficient time, Most likely time D.Minimax time, Optimistic time and harmonic time
Last Answer : A. Optimistic time, Pessimistic time and Most likely time
Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30
Last Answer : C. 60
Description : During a new project planning process to sequence activities, the project manager, Nate, decides to use the precedence diagraming method to show the identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers
Last Answer : b. Start-to-finish
Description : The conceptual estimate is developed with the least amount of knowledge. When more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate
Last Answer : c. rough order of magnitude (ROM) estimate
Description : A project budget estimate that is developed with the least amount of knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate
Last Answer : c. Conceptual estimate
Description : All of the following statements are true regarding risk events except which one? Choose the least correct answer. A. Project risks are uncertain events. B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of the risk should be accepted.
Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to plan for them.
Description : All of the following statements are true regarding risks except for which one? Choose the least correct answer. A. Risks might be threats to the objectives of the project. B. Risks are ... Risks might be opportunities to the objectives of the project. D. Risks have causes and consequences.
Last Answer : B. Risks are certain events that may be threats or opportunities to the objectives of the project
Description : )Which form of power is the LEAST effective from the project manager's viewpoint in terms of influencing functional managers? 1. Formal power 2. Expert power 3. Penalty power 4. Referent power
Last Answer : 3. Penalty power
Description : On a project the project manager should strive for a "Quality Level" that : 1. is the highest level possible 2. is as close to the project objectives as possible 3. represents the least cost to the project. 4. Exceeds the specified requirements of the project.
Last Answer : 2. is as close to the project objectives as possible
Description : Scope creep is only a minor factor in projects running over schedule, and every effort should be made to incorporate any changes into the present system if they would truly be beneficial.
Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%
Last Answer : (D) 80 to 95%
Description : Do it because I said to” is the mantra for project managers who use _____ as the default approach to resolve conflict. Select one: a. collaborating b. compromising c. accommodating d. forcing e. avoiding
Last Answer : d. forcing
Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against the potential benefit of the project’s success in order to decide if the project should be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation
Last Answer : e. initiation
Description : According to the Project Management Institute (PMI), project management is defined as the application of knowledge, _____, _____, and techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories
Last Answer : d. skills, tools
Description : Adding people to a project team in order to speed up total development time _____. a. is a standard task in timeboxing b. is a useful way to meet a tight deadline c. may actually increase total development time d. simplifies communication within the team e. none of the above
Last Answer : c. may actually increase total development time
Description : Michelle has decided to use a shortcut to determine the complexity of the project she is currently managing. She has assigned the adjusted project complexity (PCA) a value of .65. She has determined that ... _____. a. bi-lateral b. complex c. microconvergent d. normal e. very simple
Last Answer : e. very simple
Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____. a. data communications, time tradeoffs, and ... programming language d. reports printed and PCA e. x-rays, extensibility, and operational conversion
Last Answer : b. end-user efficiency, data communications, and reusability
Description : Assume a systems development project effort calculation determines that the system will require 240 function points. If the developers choose to implement this system in the C programming language, approximately ... without more information c. exactly the same d. much greater e. much less
Last Answer : e. much less
Description : . A normal system with 400 unadjusted function points would have _____ adjusted function points when the shortcut method is use to determine the complexity of the project.
Last Answer : c. 400
Description : . When estimating project time schedules using industry standards, the estimated project completion time for a systems project would be _____ person-months if the actual planning phase were completed in 6 person-months. a. 30 b. 40 c. 17.14 d. 9 e. 50
Last Answer : b. 40
Description : Function points are used to measure the estimated _____ of a project. a. complexity b. effort required c. program size d. time required
Last Answer : c. program size
Description : The process of assigning values for the time and effort needed to perform a system project is called _____. a. analysis b. estimation c. identifying d. planning
Last Answer : b. estimation
Description : Project managers can develop task lists for a project with the help of _____. a. established methodologies b. system proposals c. system requests d. user application hardware e. user requirements
Last Answer : a. established methodologies
Description : To identify the tasks for a work plan the project manager can _____. a. control and direct the project b. estimate the size, staff the project, and remember technical skills c. establish a ... of the SDLC and the steps that occur in each e. set conservative numbers for the project software
Last Answer : d. list the four phases of the SDLC and the steps that occur in each
Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be accomplished for the length of the project. a. margin of error b. project manager c. project objective d. timebox e. work plan
Last Answer : e. work plan
Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan b. creating the work plan, staffing the project, and controlling ... the deliverables e. setting the start date, estimating the time, and reading the actual time
Last Answer : b. creating the work plan, staffing the project, and controlling and directing the project