A horizontal bar chart that shows project tasks against a calendar is called

(A) milestone

(B) goal

(C) Gantt chart

(D) PERT chart

1 Answer

Answer :

(C) Gantt chart

Related questions

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : PERT chart can be used to track the tasks of a project when task time estimates are  fairly uncertain.

Last Answer : Ans: True

Description : If you would like to see a list of resources and the tasks that people are assigned to.  What view best displays this information?  A.Resource Sheet  B. Task Usage  C. Gantt Chart  D.: Resource Usage

Last Answer : C. Gantt Chart

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle

Description : A Gantt chart is used to show a project timeline diagrammatically. A. True B. Fa lse

Last Answer : A. True

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : What Is A Gantt Chart?

Last Answer : A Gantt Chart is a way of illustrating multiple, time-based activities on a horizontal time-line.

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : What is the default view of a new project in MS project?  A. Gantt View B. Resource Graph  C. Network View  D.: Workbook View

Last Answer : A. Gantt View

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : Gantt chart (or Bar chart) is helpful in (A) Efficient utilisation of manpower and machines (B) Preparing production schedule (C) Efficient despatching of products (D) Inventory control

Last Answer : (B) Preparing production schedule

Description : Time and progress chart of a construction, is also known as (A) Bar chart (B) Gantt chart (C) Modified Mile stone chart (D) All the above

Last Answer : (D) All the above

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : A review undertaken to decide whether a project should proceed into its next phase is known as a: a. gate review. b. feasibility study. c. milestone review. d. evaluation review.

Last Answer : a. gate review.

Description : Which one of the following is a valid project Key Performance Indicator (KPI)? a. Staff appraisals. b. Management buy in. c. Milestone achievement. d. Master schedule.

Last Answer : c. Milestone achievement.

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : A review undertaken to decide whether a project should proceed into its next phase is known  as a:  a. gate review.  b. feasibility study.  c. milestone review.  d. evaluation review.

Last Answer : a. gate review.

Description : Which one of the following is a valid project Key Performance Indicator (KPI)?  a. Staff appraisals.  b. Management buy in.  c. Milestone achievement.

Last Answer : c. Milestone achievement.

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : Explain how Gantt chart is used in project planning with proper example. 

Last Answer : Use of Gantt Chart in Project Planning: Gantt Chart is a project planning tool that can be used to represent the timing of tasks required to complete a project. Because Gantt chats are simple to ... a chart, which are used to record the actual operating times and delays of workers and machines.

Description : Explain GANTT chart and its application for project tracking with an example. 

Last Answer : When creating software project schedule, we begin with a set of tasks. If automated tools are used, the work breakdown is input as a task network or task outline. Effort, duration and start date are then ... can also use Gantt charts to get an overview of how things are rolling on the work front. 

Description : Which one of the following is the most appropriate management control technique for timely completion of a project ? (A) Organisation chart (B) Management by Objectives (C) PERT (D) Span of control

Last Answer : Answer: PERT

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : . A key aspect of managing a project involves: a. defining which operational systems to put in place. b. identifying routine tasks. c. ensuring ongoing operations are maintained. d. planning to achieve defined objectives

Last Answer : d. planning to achieve defined objectives.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Project management is the job of organising, coordinating, and controlling the various  tasks and resources in order to successfully complete a project. (True/False

Last Answer : Ans. True

Description : The methods and regulation used to define goals, plan and monitor tasks and resources, identify and resolve issues, and control costs and budgets for a specific project is known as … a. project management. b. Process Management c. Process d. Activities

Last Answer : a. project management.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : CASE tool is a popular graphic depiction of the work plan that lists project tasks along a y-axis, time along an x-axis, and uses shaded boxes to represent tasks.

Last Answer : Ans: False

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan

Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan  b. creating the work plan, staffing the project, and controlling ... the deliverables  e. setting the start date, estimating the time, and reading the actual time

Last Answer : b. creating the work plan, staffing the project, and controlling and directing the  project

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : A key aspect of managing a project involves:  a. defining which operational systems to put in place. b. identifying routine tasks.  c. ensuring ongoing operations are maintained.  d. planning to achieve defined objectives.