While assessing your project processes, you have identified some 

uncontrolled process variations. Which of the following would be the 

appropriate chart you may use for this purpose?

Select one:

a. Pareto diagram

b. PERT chart

c. Control chart

d. HR personnel chart

e. Critical path

1 Answer

Answer :

c. Control chart

Related questions

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : PERT chart can be used to track the tasks of a project when task time estimates are  fairly uncertain.

Last Answer : Ans: True

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Which one of the following is the most appropriate management control technique for timely completion of a project ? (A) Organisation chart (B) Management by Objectives (C) PERT (D) Span of control

Last Answer : Answer: PERT

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : An example of the risk involved in development is a) Key personnel may resign before the product is complete b) The manufacturer of critical components (e.g. the hardware  associated with a ... a fully functional lower-cost  equivalent package e) All of these are risks involved in development.

Last Answer : e) All of these are risks involved in development.

Description : Which of the following is true about a project manager? Select one: a. Project managers analyze work processes and explore opportunities to make  improvements. b. Project managers are focused ... . d. Project managers are goal oriented. e. Project managers standardize the work processes.

Last Answer : d. Project managers are goal oriented.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : According to Olivier Mesly, the 4 P’s critical for the success of a project are: (A) plan, processes, people, policy (B) plan, processes, people, power (C) plan, processes, potential, policy (D) plan, processes, potential, power

Last Answer : (B) plan, processes, people, power

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Matching people’s skills with the needs of the project, motivating employees, and  minimizing personnel conflict are all part of the staffing process.

Last Answer : Ans: True

Description : What Is Pareto Principle?

Last Answer : Pareto Principle is also known as 80/20 principle. It is a management tool to track problem tracking effectively. This principle says that 20% of the problems lead to 80% of other problems. Hence, in order ... the vital problems. In a project the vital problems are the first 10% and the last 10% .

Description : Define Pareto Principle Or 80/20 Principle?

Last Answer : It is one way of tackling problem in management. It says 20% of the problems lead to other 80% of the problems. According to this principle, we should focus on 20% of the problem. In any software project first 10% and last 10% from the vital part of the project.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : Which of the following terms is given to hypertension in which the blood pressure, which is controlled with therapy, becomes uncontrolled (abnormally high) with the discontinuation of therapy? ... Secondary hypertension denotes high blood pressure from an identified cause, such as renal disease.

Last Answer : a) Rebound Rebound hypertension may precipitate a hypertensive crisis.

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects