Design phase consist of

(A) Input received

(B) Output received

(C) Both (A) and (B)

(D) None of the above

1 Answer

Answer :

(C) Both (A) and (B)

Related questions

Description : Design phase consist of (A)Input received (B)Output received (C)Both (A) and (B) (D)None of the above

Last Answer : (C)Both (A) and (B)

Description : The life cycle can be said to consist of a series of phases. The  classical model is referred to as the waterfall model. Which phase  may be defined as The concept is explored and refined, ... client's requirements are elicited? (a) Requirements (b) Specification (c) Design d) Implementation

Last Answer : (a) Requirements

Description : Each of the following statements is true regarding the risk management plan except  for which one?  A. The risk management plan is an output of the Risk Management Planning process. B. The risk ... and budgets. D. The risk management plan is an input to all the remaining risk-planning processes.

Last Answer : B. The risk management plan includes a description of the responses to risks and  triggers.

Description : For the best model suitable for the project, in which of the phase  the developers decide a roadmap for project plan? a. Design b. System Analysis c. Coding d. Testing

Last Answer : b. System Analysis

Description : Upper CASE tools are used to create diagrams and generate code for database tables  system functionality during the design phase.

Last Answer : Ans: False

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Design Phase consists of ……………………. 1. Identity the functions to be performed 2. Design the input/output and file design 3. Defining basic parameters for system design A) 1 & 2 B) 2 & 3 C) 1 & 3 D) 1, 2 & 3

Last Answer : D) 1, 2 & 3

Description : Most of the project manager's external communication links consist of: 1. Written documents  2. Oral communication  3. Tactile contact  4. Informal contact

Last Answer : 1. Written documents

Description : Contract documentation is an input to both the Close Project and Contract Closure  processes. Contract documentation might include all of the following except for which  one?  A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents

Last Answer : D. Procurement audit documents

Description : Which unit is responsible for converting the data received from the user into computer understandable format? a) Memory Unit b) Arithmetic & Logic Unit c) Input Unit d) Output Unit

Last Answer : Answer: c Explanation: The Input Unit converts the data, which the user enters into a language which the computer understands, i.e. it converts the data into binary format. The ... after immediate results of processing whereas; the ALU is responsible for various arithmetic and bitwise operations

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : Which of the following categories is part of the output of process? a) computer programs b) documents that describe the computer programs c) data d) All of the above

Last Answer : d) All of the above

Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (A) 3-2-1-4

Description : Once project planning is complete, project managers document their plan in A. SPMP document B. SRS document C. Detailed Design document D. Excel Sheet

Last Answer : A. SPMP document

Description : Which property of the rapid prototype is not important? a) The speed with which it can be developed b) The speed with which it can be modified c) Its ability to determine the client's real needs d) The ... from it, even if they are of the how not to do it' variety e) Its internal structure.

Last Answer : c) Its ability to determine the client’s real needs

Description : Which model is used during early stages of the system  design afterthe requirements have been established? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : d) An early design model

Description : Which model assumes that systems are created fromreusable  components, scripting or database programming? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : a) An application-composition model

Description : Which model is used to compute the effort required to  integrate reusable components or program code that is  automatically generated by design or program translation  tools? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : c) A reuse model

Description : Which of the following is a requirement management activity ? a) Investigation b) Design c) Construction and Test d) All of the mentioned

Last Answer : d) All of the mentioned

Description : Which one of the following is not a fundamental activity for processes in engineering ? a) Verification b) Validation c) design and implementation d) evolution e) specification

Last Answer : a) Verification

Description : Arrange the following steps to form a basic Engineering  Process Model. i. Test ii. Design iii. Install iv. Specification v. Manufacture vi. Maintain a) 2, 4, 5, 1, 6, 3 b) 4, 2, 5, 1, 3, 6 c) 2, 4, 5, 1, 3, 6 d) 4, 2, 5, 1, 6, 3

Last Answer : a) 2, 4, 5, 1, 6, 3

Description : Following are the phases of Project Management Life Cycle.  Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery  (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (D) 4-3-2-1

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : When estimating project time schedules using industry standards for a systems project,  the following values are acceptable: 15% for planning, 25% for analysis, 50% for design,  and 10% for implementation.

Last Answer : Ans: False

Description : What are the types of express guarantees? 1. Design/ mechanical  2. Field workmanship  3. Common Work 4. Length of service  5. a and b

Last Answer : 5. a and b

Description : )Which of the following fit the category of external risks? 1. Project delays, budget under-runs, movement of city utilities  2. Regulatory, currency changes, taxation  3. Natural disasters, ... , design, social impact  5. Political unrest, budget overruns, size and complexity of the project

Last Answer : 2. Regulatory, currency changes, taxation

Description : When is the project's amount at stake the lowest 1. conceptual  2. design  3. close-out  4. implementation

Last Answer : 1. conceptual

Description : Which of the following has the greatest effect on product's reliability and maintenance  characteristic? 1. conceptualization  2. product design  3. fabrication  4. a and b

Last Answer : 4. a and b

Description : In which of the following project phases is the project schedule developed? 1. Conceptual  2. Planning  3. Implementation  4. Design

Last Answer : 2. Planning

Description : Design a digital circuit which has one input two output and one select line input should be 1000khz output should be 500khz and 250Khz select line either 0 or 1 if 0 select 250khz if 1 select 500khz

Last Answer : Ans-demux is the circuit which satisfies the given requirement if 0 is given to the selectline 250khz o/p is provided else 500khz o/p is provided.

Description : Design a sequential detector which produces an output 1 every time the input sequence 1011 is detected.

Last Answer : • Construct state diagram • Obtain the flow table • Obtain the flow table & output table • Transition table • Select flip flop • Excitation table

Description : A review undertaken to decide whether a project should proceed into its next phase is known as a: a. gate review. b. feasibility study. c. milestone review. d. evaluation review.

Last Answer : a. gate review.

Description : When a project has completed the handover and closure phase: a. the project deliverables are ready for commissioning. b. the project deliverables are ready for handing over to the users. c. the project ... must be disposed of. d. the capability is now in place for the benefits to be realized.

Last Answer : d. the capability is now in place for the benefits to be realized.

Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase of ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the  project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle.

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : A planning phase for an engineering component generated 80 engineering drawings. The QA team randomly selected 8 drawings for inspection. This exercise can BEST be described as example of: A. Inspection B. Statistical Sampling C. Flowcharting D. Control Charting

Last Answer : B. Statistical Sampling

Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.

Last Answer : a. The cost associated at the beginning of the project is highest.

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : The most important problem faced in the implementation phase of a project is a delay  in execution. (True/False)

Last Answer : Ans. True

Description : In the ____ phase of the project life cycle the work gains momentum.

Last Answer : Ans. Quick Momentum

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : In the maintenance phase the product must be tested against  previous test cases. This is known as testing. (a) Unit (b) Integration (c)Regression (d) Module (e) Beta

Last Answer : (c)Regression