Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be   removed
a) after hardening of concrete
b) before hardening of concrete
c) during concreting
d) after stressing the cables

1 Answer

Answer :

d) after stressing the cables

Related questions

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : The minimum vertical clearance above R.L. to bottom of ROB near the yard shall be a) 6525 mm* b) 5870 mm c) 2360 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder

Last Answer : a) 25mm above the top flange of girder*

Description : Rail Cluster, as temporary arrangement can be used upto a span of a) 3.66m* b) 6.1m c) 12.2m d) 18.3 m

Last Answer : a) 3.66m*

Description : Which type of following cement is used for mass concrete work a) High Alumina cement b) Quick setting cement c) Rapid hardening cement d) Low heat cement*

Last Answer : d) Low heat cement*

Description : riodicity of recording of camber in PSC girders a) Once in a year* b) Once in two years c) Once in three years d) During the detailed inspection of SE/Br.

Last Answer : a) Once in a year*

Description : The height gauge need to be provided in a) ROB b) RUB* c) FOB d) Fly Over

Last Answer : b) RUB*

Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board

Last Answer : c) Start of the bridge/work spot*

Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m

Last Answer : b) 1200 m*

Description : PSC is the abbreviation of…

Last Answer : Prestressed Concrete

Description : Periodical inspection of PSC & Composite girders a) Once in 3 years b) Once in 5 years * c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 5 years *

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : Bentonite is used in pile driving -- a) to facilitate pile driving b) to enable proper pile concreting c) to stabilize the bore hole walls* d) None of the above

Last Answer : c) to stabilize the bore hole walls*

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : bbreviation of ROB …

Last Answer : Road Over Bridge

Description : What is the carriageway of two lane ROB on National Highway a)10.00m b)8.5 c)9.50* d)10.50

Last Answer : c)9.50*

Description : Which para of Engineering code deals with cost sharing of ROB/RUBs a) 1716 b) 1814 c) 1816* d) 1819

Last Answer : c) 1816*

Description : 1. Which of the statements with regard to formation is correct (1) One of the Functions of the formation is to facilitate drainage (2) Width of bank for double railway line is 12.155 meters (3) Width of cutting for double railway track is 11. ... a) 2, 3, 5 b) 3, 4, 5* c) 2, 3, 4 d) 2, 4, 5

Last Answer : b) 3, 4, 5*

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : Metallising is the process of spraying of …. on the surface prepared girder.

Last Answer : Zinc.. or ..Aluminium.

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : The depth of 19.81 mlong service girder is about……… a)1.67 m b)1.16 m* c)0.95 m d)1.52 m

Last Answer : b)1.16 m*

Description : Shallow type girder can be used in a) ROBs b) RUBs* c) FOBs

Last Answer : b) RUBs*

Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level

Last Answer : b) commencing from bottom of girder towards bed level*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting b) periodical through painting* c) Any of the above d) None of the above

Last Answer : b) periodical through painting*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30 cumecs is a) 300 mm b) 1500 mm c) 1800 mm d) 600 mm*

Last Answer : d) 600 mm*

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder

Last Answer : c) semi-through type girder*

Description : The load transferred from rails to bottom flanges is in a) deck type girder b) through type girder* c) semi-through type girder d) plate girder

Last Answer : b) through type girder*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Depth of construction in a girder bridge means the depth from a) RL to HFL b) RL to top of bed block * c) RL to bottom of bed block d) RL to Bed level

Last Answer : b) RL to top of bed block *

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : How do engineer determine the number of cells for concrete box girder bridges?

Last Answer : If the depth of a box girder bridge exceeds 1/6 or 1/5 of the bridge width, then it is recommended to be designed as a single cell box girder bridge. However, if the bridge depth is ... improvement in transverse load distribution when the number of cells of box girder is increased to three or more.

Description : Are diaphragms necessary in the design of concrete box girder bridges?

Last Answer : Diaphragms are adopted in concrete box girder bridges to transfer loads from bridge decks to bearings. Since the depth of diaphragms normally exceeds the width by two times, they are usually designed ... In fact, diaphragms also contribute to the provision of torsional restraint to the bridge deck.

Description : In Case If Concrete Box Girder Bridges How Is The Number Of Cells Determined?

Last Answer : Answer : When the depth of a box girder bridge exceed 1/6th or 1/5th of the bridge width then the design recommended is that of a single cell box girder bridge. But in case the depth of ... the transverse load distribution when the number of cells of the box girder is higher than three or more.

Description : The setting and hardening of cement after addition of water is due to a) Binding action of water b) Evaporation of water c) Hydration and hydrolysis of some constituent compounds of cement* d) Additional hardening compounds added to cement

Last Answer : c) Hydration and hydrolysis of some constituent compounds of cement*