Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*
Last Answer : d) 100 m
Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block
Last Answer : a) Girder/Slab*
Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls
Last Answer : b) Girder/Slab*
Description : In a single span bridge, the clear span is the distance between a) Centres of Abutments b) Inner faces of Abutments* c) Outer faces of Abutments d) Width of Abutment
Last Answer : b) Inner faces of Abutments*
Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier
Last Answer : a) C.L. of water course/road to C.L. of track*
Description : Skew of a bridge is the angle between a) C.L. of water course to C.L. of track b) C.L. of water course to C.L. of pier c) C.L. of water course/road to normal (perpendicular) of C.L. of track* d) C.L. of abutment to C.L. of pier
Last Answer : c) C.L. of water course/road to normal (perpendicular) of C.L. of track*
Description : At locations where access to the new bridge construction is available by rail, the launching of girders upto 18.3 m which method is ideal. a) slew in slew out method b) gantry method c) Launching of girders with the help of a BFR*: d) Pantoon method
Last Answer : c) Launching of girders with the help of a
Description : In case of Shot Welded Rails the fish plated joint should be avoided on Level Crossings within a distance of --------- from end of level crossing a) 3 meters b) 4 meters c) 5 meters d) 6 meters*
Last Answer : d) 6 meters*
Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters
Last Answer : a) 3 meters*
Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None
Last Answer : b) Lifting*
Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm
Last Answer : a) 6525 mm*
Description : The medium to transfer loads from superstructure to substructure is called a) Abutment b) Bed block c) Bearing d) Pier
Last Answer : c) Bearing
Description : Rail Cluster, as temporary arrangement can be used upto a span of a) 3.66m* b) 6.1m c) 12.2m d) 18.3 m
Last Answer : a) 3.66m*
Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.
Last Answer : c) Level crossing should not fall within the breathing length of LWR*
Description : Periodontal damage to abutment teeth of partial denture with distal extension can best be avoided by, A. Applying Stressbreakers B. Employing bar s on all abutment teeth C. Maintaining tissue support ... area E. Maintaining the clasp arms on all abutment teeth at the ideal degree of tension
Last Answer : C. Maintaining tissue support of the distal extension
Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6
Last Answer : ii) 5.7*
Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters
Last Answer : a) 5 meters*
Description : The rail joint should be located at ----------- from the end of level crossing a) 2 meters b) 3 meters * c) 5 meters d)6 meters
Last Answer : b) 3 meters
Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.
Last Answer : ii) defects in rail. *
Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above
Last Answer : ii) 10 mm below the top surface of rail head.*
Description : In LWR What is the range of Destressing temperature in 52 kg and heavier section a. Mean rail temp+5 0C to Mean rail temp+10 0C* b. Mean rail temp+5 0C to Mean rail temp+15 0C c. Mean rail temp to Mean rail temp+10 0C d. Mean rail temp+2 0C to Mean rail temp+10 0C
Last Answer : a. Mean rail temp+5 0C to Mean rail temp+10 0C*
Description : Painting during night and early morning avoided because of
Last Answer : dew
Description : The size of bridge timber required for the standard spans up to 18.3 m a) 250 x 150mm*. b) 250 x 180mm. c) 250 x 240mm d) 250 x 200mm
Last Answer : a) 250 x 150mm*.
Description : The minimum cushion specified over an arch bridge is -- a) 0.5m b) 0.9m c) 1.0m* d) 1.2 m
Last Answer : c) 1.0m*
Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board
Last Answer : c) Start of the bridge/work spot*
Description : Minimum Free Board required in a bridge is a) 1 m* b) 1.20 m c) 600 mm d) 300 mm
Last Answer : a) 1 m*
Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m
Last Answer : b) 1200 m*
Description : Height of platform of a flag station in cutting above rail level is (a) Same height as Rail level (b) 305 mm above rail level (c) 455 mm above rail level (d) 840mm above rail level*
Last Answer : (d) 840mm above rail level*
Description : For ‘B’ category stations as per minimum essential facility it is necessary to provide (a) High level platform (b) Medium level platform* (c) Rail level platform (d) All the above
Last Answer : (b) Medium level platform*
Description : For ‘A’ category stations it is necessary to provide (a) High level platform* (b) Medium level platform (c) Rail level platform (d) All the above
Last Answer : (a) High level platform*
Description : A new railway line is required to be constructed beaus’ of following reasons (a) Strategic and political considerations (b) Development of backward area (c) To shorten existing rail link (d) Any of them*
Last Answer : d) Any of them*
Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.
Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*
Description : On Rajdhani routes testing frequency of rail testing for rail section of 60kg with annual GMT 80, will be. (i) 4 months (ii) 1 1⁄2 months (iii) 1 months* (iv) None of above.
Last Answer : (iii) 1 months*
Description : Total no. of probes fitted on digital double rail tester for rail testing are (i) 12 (ii) 8 (iii) 14* (iv) 16.
Last Answer : (iii) 14*
Description : 65- Grade of 72 UTS rail is? (i) 880 (ii) 1080 (iii) 710* (iv) None of above
Last Answer : (iii) 710*
Description : Grade of 110 UTS rail is? (i) 880 (ii) 1080* (iii) 710 (iv) None of above
Last Answer : (ii) 1080*
Description : Grade of 90 UTS rail is? (i) 880* (ii) 1080 (iii) 710 (iv) None of above
Last Answer : i) 880*
Description : Which gauge is used to measure the height of rail at the time of aligning of rails for AT welding? (i) Height gauge.* (ii) Vertical gauge (iii) Horizontal gauge (iv) As decided by site supervisor
Last Answer : (iv) As decided by site supervisor
Description : Torch is kept at height from top surface of rail head? (i) 30 to 55 mm (ii) 35 to 40 mm (iii) 40 to 45 mm
Last Answer : (iii) 40 to 45 mm
Description : Colour of rail ends becomes after preheating ? (i) Golden * (ii) Pink Red (iii) Red (iv) Yellow
Last Answer : (i) Golden
Description : To take care of differential cooling rail ends of 72 UTS rails are lifted by? (i) 1 to 1.5 mm (ii) 1 to 2 mm (iii) 2 to 2.5 mm (iv) 3 to 4 mm *
Last Answer : iv) 3 to 4 mm *
Description : To take care of differential cooling rail ends of 90 UTS rails are lifted by? (i) 1 mm (ii) 2 mm (iii) 2 to 2.2 mm.* (iv) 1 to 2 mm
Last Answer : (iii) 2 to 2.2 mm.*
Description : What is Pre Heating Temperature of rail ends in AT Welding? (i) 300 ± 20oC (ii) 400 ± 20oC (iii) 500 ± 20oC (iv) 600 ± 20oC *
Last Answer : (iv) 600 ± 20oC *
Description : How much rail ends are cleaned with Kerosene Oil and steel wire brush? (i) Minimum 100 mm both side (ii) Minimum 50 mm both side.* (iii) No need (iv) As decided by site supervisor
Last Answer : (ii) Minimum 50 mm both side.*
Description : In new Rail as well as second hand rails how much end bends of the rails in lateral direction are permitted when checked with one metre straight edge before welding? (i) ± 0.2 mm in lateral direction (ii) ± 0.3 mm in lateral direction (iii) ± 0.5 mm in latera
Last Answer : (iii) ± 0.5 mm in latera
Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical
Last Answer : (i) +0.5mm, -0 mm in vertical *
Description : Minimum length of check rail for square crossing shall be -------- more than the width of gate a) 1 meters b) 2 meters* c) 3 meters d) 5 meters
Last Answer : b) 2 meters*
Description : Level crossing is classified on the basis of a) Class of road b) TVU* c) Volume of road traffic d) Volume of rail traffic
Last Answer : b) TVU*
Description : Ultrasonic Pulse Velocity test is meant for a) Identifying the integrity of concrete* b) Finding the strength of concrete c) To know the crack in steel structure d) To know the flaw in rail
Last Answer : a) Identifying the integrity of concrete*
Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level
Last Answer : b) commencing from bottom of girder towards bed level*