The minimum cushion specified over an arch bridge is --
a) 0.5m
b) 0.9m
c) 1.0m*
d) 1.2 m

1 Answer

Answer :

c) 1.0m*

Related questions

Description : .Minimum earth cushion required over RCC Box is a) 300 mm b) 600 mm c) 0* d) 1000 mm

Last Answer : c) 0*

Description : Height gauges should be located at a minimum distance of….. from gate post. (a) 5 m (b) 7.5m (c) 8m* (d)10m

Last Answer : (c) 8m*

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : enght of cutter bar for the tractor operated mower or vertical conveyor reaper is..... (a) 1.5-3.0m (b) 3.0-4.5m (c)4.5-5.5m (d) >5.5m

Last Answer : (a) 1.5-3.0m

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : bridge foundation having less then 2M depth below bed level in case of arch bridges and 1.2M depth below bed level in case of other bridges is termed as

Last Answer : …Shallow foundation..

Description : In arch bridges, Cracks/ lean/ bulge in parapet walls, Bulging or separation of spandrel from arch barrel, are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Diminishing returns for a single year on TQM budgets become noticeable at a. $3.0M. b. $1.5M. c. $2.0M. d. $5.0M. e. $1.0M.

Last Answer : c. $2.0M.

Description : hat is the horizontal spacing between tie? a. No more than 5m (16 feet) b. No more than 9m (30 feet) c. No more than 7m (23 feet) d. No more than 38m (125 feet)

Last Answer : b. No more than 9m (30 feet)

Description : A bridge is generally specified as “Br. No. 180 (5x9.10m G) at km 345/5-6”. a) Effective Span b) Width of bridge c) Clear Span* d) Overall length of bridge

Last Answer : c) Clear Span*

Description : For taking track measurement at accident site stations shall be marked at …….. Apart. (a) 1 m (b) 2m (c) 3m* (d) 5m

Last Answer : (c) 3m*

Description : Minimum Free Board required in a bridge is a) 1 m* b) 1.20 m c) 600 mm d) 300 mm

Last Answer : a) 1 m*

Description : For laying a Railway track the prepared surface ready to receive the ballast is called a) Sub ballast b) Formation* c) Blanket d) Cushion

Last Answer : b) Formation*

Description : Foot over bridge must be provided on the following type of stations as per minimum essential facility criteria (a) A, B, C, & D class station (b) A,B & C class station* (c) A, & B class station (d) Only A class station

Last Answer : b) A,B & C class station*

Description : The minimum vertical clearance of foot over bridge gangway is a) 2100 mm b) 3660 mm c) 6525 mm d) 2710 mm

Last Answer : d) 2710 mm

Description : For railway bridges with spans in excess of 30.5m, generally provided with a) deck type girders b) open web through girders* c) semi through girders d) shallow type girders

Last Answer : b) open web through girders*

Description : At locations where access to the new bridge construction is available by rail, the launching of girders upto 18.3 m which method is ideal. a) slew in slew out method b) gantry method c) Launching of girders with the help of a BFR*: d) Pantoon method

Last Answer : c) Launching of girders with the help of a

Description : Rail joints should be avoided within ……………of a bridge abutment. a) 6 m b) 3 m* c) 4 m d) 10 m

Last Answer : b) 3 m*

Description : The size of bridge timber required for the standard spans up to 18.3 m a) 250 x 150mm*. b) 250 x 180mm. c) 250 x 240mm d) 250 x 200mm

Last Answer : a) 250 x 150mm*.

Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board

Last Answer : c) Start of the bridge/work spot*

Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m

Last Answer : b) 1200 m*

Description : eFor design of sewers for sullage, minimum velocity of ---- metres per second is taken. (a) 1.0 m sec* (b) 1.5 m/sec (c) 2.0 m/sec (d) 2.5 m/sec

Last Answer : (a) 1.0 m sec*

Description : The wash hand basin shall be fixed at a height of (a) 75-80 cm* (b) 75 cm (c) 80 cm (d) Not specified

Last Answer : (a) 75-80 cm*

Description : Maximum tilt specified during sinking of well foundation is a) 1 in 10 b) 1 in 50 c) 1 in 100* d) 1 in 150

Last Answer : c) 1 in 100*

Description : Track structure for private siding with operating speed 50 to 80 kmph is the same as track structure as specified for a)Group A route b) Group B route c) Group D route d)Group E route*

Last Answer : d)Group E route*

Description : Track Structure for private siding with operating speed of 80 to 100 kmph is same as the track structure as specified for a) Group B route b) Group A route c) Group D route* d)Group C route

Last Answer : c) Group D route*

Description : Solve : `(9m+4)/(5) - (27 m + 1)/(8) - (1)/(2) = 0`

Last Answer : Solve : `(9m+4)/(5) - (27 m + 1)/(8) - (1)/(2) = 0`

Description : Calculate the Polar moment of inertia in m 4 of a single motor system from the following data: C = 8 GN/m 2 , L=9m, I = 600 Kg-m 2 , f=10 Hz a) 0.00027b) 0.00032 c) 0.00045 d) 0.00078

Last Answer : a) 0.00027

Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000

Last Answer : b) 1, 00,000*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : The horizontal clearance of edge of foot over bridge structure from face of platform is a) 6525 mm b) 3660 mm* c) 5330 mm d) 5300 mm

Last Answer : b) 3660 mm*

Description : The concrete under water minimum grade of cement recommended by IS code a) M 10 b) M 15 c) M 20* d) M 25

Last Answer : c) M 20*

Description : Calculate the free torsional vibrations of a single motor system from the following data: C = 8 GN/m 2 , L=9m, I = 600 Kg-m 2 , J = 8×10 4 m 4 a) 162,132 b) 172,132 c) 182,132 d) 192,132

Last Answer : b) 172,132

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : Which of the following stone is best suited for construction of piers and abutments of Railway Bridge a) Granite* b) Sandstone c) Limestone d) Quartzite

Last Answer : a) Granite*

Description : In case of bridge is distressed category I then special restriction of___hall be imposed

Last Answer : 15 kmph

Description : In case of distressed bridge category II, ADEN shall inspect the bridge

Last Answer : once in 6 months

Description : In important bridge the total linear waterway is

Last Answer : 300 m or the total water way is 1000 sq.m.

Description : The URN of minor bridge shall be represented by its

Last Answer : ORN

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : While finalizing the IRBM, which of the following have been taken into account. a) Indian RailwaysGeneral Rules 1976 b) Indian Railways Code for Engineering Department 1993 c) Bridge Rules and Substructure d) All the above*

Last Answer : d) All the above*

Description : Payment to bridge staff on the section will be made by the pay clerk in the presence of a) SSE/SE/JE/ P.Way b) SSE/SE/JE/ Br.* c) SSE/SE/JE/ Works d) Office clerk

Last Answer : b) SSE/SE/JE/ Br.*

Description : Which cement should not be used for bridge slabs ro RCC frames a) OPC b) Portland Pozzolana cement * c) Portland furnace slag cement d) Rapid hardening cement

Last Answer : b) Portland Pozzolana cement *

Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None

Last Answer : b) Lifting*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Permitted wind velocity for running of trains on the bridge a) 72 km/h* b) 58 km/h c) 64 km/h d) No limits

Last Answer : a) 72 km/h*

Description : Definition of minor bridge e) Single span less than 12m f) Total linear water way less than 18m g) Both a) & b)* h) None of the above

Last Answer : g) Both a) & b)*

Description : Definition of major bridge a) Single span of 12m & above b) Total linear water way more than 18m c) Both a) & b)* d) None of the above

Last Answer : c) Both a) & b)*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*