Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters
Last Answer : a) 5 meters*
Description : The frequency of census at a level crossing having TVU between 75000 to 1 lakh will be once a) In 2 years b) In 3 years* c) In 4 years d) Every year
Last Answer : b) In 3 years*
Description : TVU is abbreviated for a) Track vulnerable unit b) Train vehicle unit * c) Total vehicle unit d) Traffic variation unit
Last Answer : b) Train vehicle unit *
Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000
Last Answer : b) 1, 00,000*
Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.
Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*
Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.
Last Answer : c) Level crossing should not fall within the breathing length of LWR*
Description : The rail joint should be located at ----------- from the end of level crossing a) 2 meters b) 3 meters * c) 5 meters d)6 meters
Last Answer : b) 3 meters
Description : .Minimum check rail clearance at Level crossing a. 45 mm b. 51 mm* c. 50 mm d. 57 mm
Last Answer : b. 51 mm*
Description : Traffic census at a level crossing shall be done by a) A team of SSE/ P Way and SSE/ Works b) A team of SSE/ P Way and Traffic inspector c) A team of SSE/ P Way and Signal Inspector d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.
Last Answer : d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.
Description : Level Crossing beyond the outermost stop signals is called a) Engineering Gate* b) Traffic Gate c) Engineering and Signal Gate d) Signal Gate
Last Answer : a) Engineering Gate
Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted
Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*
Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters
Last Answer : c) 20 meters*
Description : Minimum length of check rail for square crossing shall be -------- more than the width of gate a) 1 meters b) 2 meters* c) 3 meters d) 5 meters
Last Answer : b) 2 meters*
Description : Service life of CMS crossing ( 52 Kg rail) is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT. (d) 150 GMT.*
Last Answer : (d) 150 GMT.*
Description : .Minimum wing rail clearance opposing nose of crossing on Fan shaped turnout a. 45 mm b. 40 mm c. 41 mm* d. 44 mm
Last Answer : c. 41 mm*
Description : Minimum rail section recommended for section having traffic more than 20 GMT is (a) 90 UTS (b) 52 Kg. (c) 60 Kg.* (d) None of the above.
Last Answer : (c) 60 Kg.
Description : Mostly long span rail-cum road bridges are provided with a) rocker & roller bearings b) segmental roller with oil bath* c) Sliding bearings d) centralised bearings
Last Answer : b) segmental roller with oil bath
Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier
Last Answer : a) C.L. of water course/road to C.L. of track*
Description : The place where a railway line and a road cross each other at the same level, is known as A. Level Crossing B. Cross over C. Rail Junction D. Road Junction
Last Answer : A [Level Crossing] Explanation: A level crossing (also called a grade crossing, a railway crossing, or a railroad crossing) is a place where a railway line and a road meet each other on the same level.
Description : .What do you mean by 60 kg rail a. Weight of rail in 1 meter* b. Area of rail of 1 meter c. Weight of rail in 1 feet d. Volume of rail in 1 meter
Last Answer : a. Weight of rail in 1 meter*
Description : Height of platform of a flag station in cutting above rail level is (a) Same height as Rail level (b) 305 mm above rail level (c) 455 mm above rail level (d) 840mm above rail level*
Last Answer : (d) 840mm above rail level*
Description : For ‘B’ category stations as per minimum essential facility it is necessary to provide (a) High level platform (b) Medium level platform* (c) Rail level platform (d) All the above
Last Answer : (b) Medium level platform*
Description : For ‘A’ category stations it is necessary to provide (a) High level platform* (b) Medium level platform (c) Rail level platform (d) All the above
Last Answer : (a) High level platform*
Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None
Last Answer : b) Lifting*
Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level
Last Answer : b) commencing from bottom of girder towards bed level*
Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm
Last Answer : a) 25 mm*
Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm
Last Answer : a) 6525 mm*
Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder
Last Answer : a) 25mm above the top flange of girder*
Description : Vertical Clearance (VC) in water way bridges is the level difference between a) HFL and Formation level b) Bed level and bottom of superstructure c) HFL and bottom of superstructure* d) Rail level and Formation level
Last Answer : c) HFL and bottom of superstructure*
Description : Free Board is the level difference between Formation Level and ……………. a) Rail Level b) HFL* c) Bed Level d) Danger Level
Last Answer : b) HFL*
Description : The maximum height above rail level for B.G. goods platform is ……. Mm (a) 1000mm (b) 1050mm (c) 1065mm* (d) 1075mm
Last Answer : (c) 1065mm*
Description : What is maximum height above rail level for low-level passenger platform for BG? (a) 300mm (b) 455mm* (c) 525mm (d) 550mm
Last Answer : (b) 455mm
Description : Minimum depth of space for wheel flange form rail level in B.G. is …… mm (A) 35 (B) 38* (C) 42 (D) 45
Last Answer : (B) 38*
Description : Maximum height above rail level of high passenger Platform a. 860 mm b. 900 mm c. 840 mm&* d. 875 mm
Last Answer : c. 840 mm&*
Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.
Last Answer : c) Duty hut should be on the outside of the curve.*
Description : On Indian Railways a new level crossing can be provided with the approval of a) Chief engineer b) General Manager c) Commissioner of Railway Safety d) None of the above*
Last Answer : d) None of the above
Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years
Last Answer : c) Every 2 years*
Description : The Height Gauge for a level crossing should be located at least --------- from the gate post a) 3 meters b) 5 meters c) 8 meters* d) 10 meters
Last Answer : c) 8 meters*
Description : There should not be any combination joint on level crossing proper and its approaches up to a) 15 meters b) 30 meters c) 40 meters d) 50 meters
Last Answer : d) 50 meters
Description : In case of Shot Welded Rails the fish plated joint should be avoided on Level Crossings within a distance of --------- from end of level crossing a) 3 meters b) 4 meters c) 5 meters d) 6 meters*
Last Answer : d) 6 meters*
Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters
Last Answer : c) 20 meters
Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters
Last Answer : a) 3 meters*
Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters
Last Answer : b) 600 meters*
Description : The Assistant Divisional Engineer should inspect the equipment at every manned level crossing on the subdivision once in a) 2 months b) 3 months c) 4 months d) 6 months*
Last Answer : d) 6 months
Description : On an unmanned level crossing stop board should be provided at a distance of --------- from the centre of nearest track a) 5 meters * b) 6 meters c) 3 meters d) 7.5 meters
Last Answer : a) 5 meters
Description : For protection of level crossing gate in an emergency on BG double line the Gateman should place one detonator at one place and 3 detonators at a subsequent place at a distance of ------- a) and------ ... c) 500 meters and 1000 meters d) 600 meters and 1200 meters* e) 800 meters in 1500 meters
Last Answer : d) 600 meters and 1200 meters*
Description : Indication post for detonator should be provided at a distance of ---------meter and --------- meter for BG level crossing a) 400 meters in 800 meters b) 500 meters and 1200 meters c) 600 meters and 1200 meter * d)600 meters and 1000 meters
Last Answer : c) 600 meters and 1200 meter *
Description : Minimum clearance of check rails for B.G. at level crossing should be (a) 48mm (b) 57mm (c) 51mm* (d) 44mm
Last Answer : (c) 51mm*
Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51 mm (b) 57mm* (c) 65mm (d) 70mm
Last Answer : (b) 57mm*
Description : Maximum clearance of check rails at level crossing for B.G. should be (a) 48mm (b) 57mm* (c) 51mm (d) 44mm