The size of bridge timber required for the standard spans up to 18.3 m  a) 250 x 150mm*.
b) 250 x 180mm.
c) 250 x 240mm
d) 250 x 200mm

1 Answer

Answer :

a) 250 x 150mm*.

Related questions

Description : The height of a toe board must be at least? a. 100mm (4 inches) b. 200mm (8 inches) c. 150mm (6 inches) d. 230mm (9 inches)

Last Answer : c. 150mm (6 inches)

Description : What is the maximum distance that bracing can be installed from a node point on a scaffold? a. 200mm (8 inches) b. 300mm (12 inches) c. 150mm (6 inches) d. 250mm (10 inches)

Last Answer : b. 300mm (12 inches)

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : For A Class, the gross clearance of over maximum moving dimension for BG is (a) 100mm (b) 125mm (c) 150mm* (d) 175mm

Last Answer : (c) 150mm*

Description : For A class ODC, the gross clearance over maximum moving dimension of B.G is (a) 150mm (b) 175mm (c) 225 mm* (d) (d) 250mm

Last Answer : (c) 225 mm*

Description : At locations where access to the new bridge construction is available by rail, the launching of girders upto 18.3 m which method is ideal. a) slew in slew out method b) gantry method c) Launching of girders with the help of a BFR*: d) Pantoon method

Last Answer : c) Launching of girders with the help of a

Description : Minimum Free Board required in a bridge is a) 1 m* b) 1.20 m c) 600 mm d) 300 mm

Last Answer : a) 1 m*

Description : Callendar Hamilton spans are normally available maximum up to a) 60 ft. b) 100 ft. c) 150 ft. d) 200 ft.*

Last Answer : d) 200 ft.*

Description : A butt weld has been made by MMA in a 50mm thick impact tested steel plate. The welding electrode used was a basic type, 5mm diameter. The measured welding parameters for one of the runs was 250 amps, 24 volts, using DC ... given to calculate the arc energy b) 1.9 kJ/mm c) 1.87 kJ/mm d) 2.0 kJ/mm

Last Answer : d) 2.0 kJ/mm

Description : For railway bridges with spans in excess of 30.5m, generally provided with a) deck type girders b) open web through girders* c) semi through girders d) shallow type girders

Last Answer : b) open web through girders*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : Maximum distance apart of trolley refuges on bridges with main spans of 100metre or more is i. 50 mtr j. 100 mtr k. 200 mtr l. a refuge over each pair*

Last Answer : l. a refuge over each pair*

Description : In which of the following directions, the strength of timber is maximum a) Parallel to grains* b) 45 degree to grains c) Perpendicular to grains d) same in all directions

Last Answer : a) Parallel to grains*

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : Rail joints should be avoided within ……………of a bridge abutment. a) 6 m b) 3 m* c) 4 m d) 10 m

Last Answer : b) 3 m*

Description : The minimum cushion specified over an arch bridge is -- a) 0.5m b) 0.9m c) 1.0m* d) 1.2 m

Last Answer : c) 1.0m*

Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board

Last Answer : c) Start of the bridge/work spot*

Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m

Last Answer : b) 1200 m*

Description : Tamron 18-270mm vs Canon 18-200mm vs Canon 18-135mm vs Canon 18-55mm+Canon 55-250mm --Which should I get?

Last Answer : answer:270 needs more light. As does the 250. IE Slower shutter speed and/or larger aperture.

Description : A guardrail system must be fitted if the distance between a working platform a wall is more than? a. 100mm (4 inches) b. 360mm (14 inches) c. 200mm (8 inches) d. 460mm (18 inches)

Last Answer : b. 360mm (14 inches)

Description : A T-section beam having flange 180mm wide and 20 mm thick and web 150 mm long and 20 mm thick carries a udl of 80 kN/m over an effective span of 8 m. Calculate the maximum bending stress.

Last Answer : Solution :

Description : Rail Cluster, as temporary arrangement can be used upto a span of a) 3.66m* b) 6.1m c) 12.2m d) 18.3 m

Last Answer : a) 3.66m*

Description : The number of standard rails (13 m) for one km. BG section single line section is (a) 120 (b) 154* (c) 168 (d) 196

Last Answer : (b) 154*

Description : Size of cubicle of a booking office is kept as (a) 1.20 x 1.50 m (b) 1.50 x 1.20 m (c) 1.50 x 1.80 m (d) 1.80 x 1.50 m*

Last Answer : (d) 1.80 x 1.50 m*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : The gradient of a platform is generally (a) 1 in 1000 (b) 1 in 750 (c) 1 in 500* (d) 1 in 250

Last Answer : (c) 1 in 500*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : Which bridge, one of the oldest roadway bridges in the United States, was completed in 1883 and spans the East River? -Geography

Last Answer : The Brooklyn Bridge

Description : What is the weight of a bridge that spans 35 centimeters?

Last Answer : weight of a bridge that spans 35 centimeters

Description : An animal drawn seed drill has k number of furrow openers 180mm apart. If the speed of operation is 2.0kmph, the area covered (ha), in 8-11day is given by: A. 1.85/1000k B. 28.8 x 10-2k C. k/6.56 D. 1.762k

Last Answer : B. 28.8 x 10-2k

Description : Number of sleepers required having sleeper density of M+7 for one Km of BG single line is (a) 1360 (b) 1540* (c) 1660 (d) None of the above

Last Answer : (b) 1540*

Description : Foot over bridge must be provided on the following type of stations as per minimum essential facility criteria (a) A, B, C, & D class station (b) A,B & C class station* (c) A, & B class station (d) Only A class station

Last Answer : b) A,B & C class station*

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : Which of the following stone is best suited for construction of piers and abutments of Railway Bridge a) Granite* b) Sandstone c) Limestone d) Quartzite

Last Answer : a) Granite*

Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000

Last Answer : b) 1, 00,000*

Description : In case of bridge is distressed category I then special restriction of___hall be imposed

Last Answer : 15 kmph

Description : In case of distressed bridge category II, ADEN shall inspect the bridge

Last Answer : once in 6 months

Description : In important bridge the total linear waterway is

Last Answer : 300 m or the total water way is 1000 sq.m.

Description : The URN of minor bridge shall be represented by its

Last Answer : ORN

Description : bridge foundation having less then 2M depth below bed level in case of arch bridges and 1.2M depth below bed level in case of other bridges is termed as

Last Answer : …Shallow foundation..

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : While finalizing the IRBM, which of the following have been taken into account. a) Indian RailwaysGeneral Rules 1976 b) Indian Railways Code for Engineering Department 1993 c) Bridge Rules and Substructure d) All the above*

Last Answer : d) All the above*

Description : Payment to bridge staff on the section will be made by the pay clerk in the presence of a) SSE/SE/JE/ P.Way b) SSE/SE/JE/ Br.* c) SSE/SE/JE/ Works d) Office clerk

Last Answer : b) SSE/SE/JE/ Br.*

Description : Which cement should not be used for bridge slabs ro RCC frames a) OPC b) Portland Pozzolana cement * c) Portland furnace slag cement d) Rapid hardening cement

Last Answer : b) Portland Pozzolana cement *

Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None

Last Answer : b) Lifting*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : Permitted wind velocity for running of trains on the bridge a) 72 km/h* b) 58 km/h c) 64 km/h d) No limits

Last Answer : a) 72 km/h*

Description : Definition of minor bridge e) Single span less than 12m f) Total linear water way less than 18m g) Both a) & b)* h) None of the above

Last Answer : g) Both a) & b)*