The purpose of reconnaissance survey
(a) To determine technical fenibility of the line*
(b) To assess whether such a line is required or not
(c) To decide the final alignment of the railway line
(d) None of the above

1 Answer

Answer :

(a) To determine technical fenibility of the line*

Related questions

Description : A detailed project report of the proposed railway line is made after (a) Preliminary survey (b) Reconnaissance survey (c) Final location survey* (d) Traffic survey

Last Answer : (c) Final location survey*

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above

Description : Which of the following survey are required to be done before the construction of new railway line. (a) Traffic survey (b) Reconnaessarice survey (c) Preliminary survey (d) Final location survey (e) All the above

Last Answer : e) All the above

Description : The survey instrument used for reconnaissance survey (a) Theodelite & Dumpty level (b) Prismatic compass & Aneriod barometer* (c) All the above (d) None of them

Last Answer : (b) Prismatic compass & Aneriod barometer*

Description : The project report of the reconnaissance survey should be accompanied by Index map area at a scale of 1 cm = ---- km. (a) 2.5 km* (b) 5.0 km (c) 10.0 km (d) 15.0 km (e) 20.0 km

Last Answer : (a) 2.5 km*

Description : The project report of the reconnaissance survey should be accompanied by a map of the area at a scale of 1 cm= --- km. (a) 2.5 km (b) 5.0 km (c) 10.0 km (d) 15.0 km (e) 20.0 km*

Last Answer : (e) 20.0 km*

Description : Which of the instruments is not used in Reconnaissance survey. (a) Prismatic compass (b) Dumpy level * (c) Aneroid Barometer (d) Pedometer

Last Answer : (b) Dumpy level *

Description : The first stage of deciding the alignment of a hill road, is (A) Reconnaissance (B) Detailed survey (C) Trace-out (D) Preliminary survey

Last Answer : Answer: Option A

Description : Traffic survey is done to find out (a) The most promising route for the railway in the area (b) The possible traffic the railway line will carry (c) Standard of railway line to be followed (d) All the above*

Last Answer : d) All the above*

Description : While doing final location survey, the centre line is fully marked with pegs at --- metre distance (a) 10m (b) 20m* (c) 30m (d) 50m

Last Answer : (b) 20m*

Description : Survey of the major projects is done by (a) Chief Engineer (b) Chief Administrative Officer (CAO) construction* (c) Divisional Railway Manager (d) Railway Board

Last Answer : (b) Chief Administrative Officer (CAO) construction*

Description : During last phase of the reconnaissance, details of the grade line is recorded on 2 metre poles to indicate (A) Direction of the proposed alignment (B) Distance between the previous and forward pegs (C) Relative elevations of pegs (D) All the above

Last Answer : Answer: Option D

Description : When the continuing auditor intends to use information about the entity and its environment obtained in prior periods, the auditor should a. Assess control risk as "high" for the assertions ... whether to equitably reduce the audit fee due to lower audit effort expended during the engagement

Last Answer : Determine whether changes have occurred that may affect the relevance of such information in the current audit.

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : A new railway line is required to be constructed beaus’ of following reasons (a) Strategic and political considerations (b) Development of backward area (c) To shorten existing rail link (d) Any of them*

Last Answer : d) Any of them*

Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements  2. a production system  3. an inspection system  4. fitness for purpose

Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements

Description : Pick up the correct statement from the following: (A) During reconnaissance, the general route of the alignment is selected (B) After reconnaissance, a trace is cut for the alignment (C) Last stage is the detailed surveys for desired geometries' of the highway (D) All the above

Last Answer : Answer: Option D

Description : A Railway Stations is provided for the following purpose (a) To entrain or detrain the passengers (b) To load or off load the goods or parcels (c) To enable the faster trains to overtake the slower trains (d) All the above*

Last Answer : d) All the above*

Description : A test cross is carried out to (a) determine the genotype of a plant at F2 (b) predict whether two traits are linked (c) assess the number of alleles of a gene (d) determine whether two species or varieties will breed successfully.

Last Answer : (a) determine the genotype of a plant at F2

Description : Defect of High joint is due to ? (i) Early trimming of weld (ii) Excess provision of height during alignment.* (iii) Early grinding of weld (iv) None of above

Last Answer : (ii) Excess provision of height during alignment.

Description : Defect of low joint is due to? (i) Excess height (ii) Early trimming of weld (iii) Early grinding of weld (iv) Nil/Less provision of height during alignment.

Last Answer : (iv) Nil/Less provision of height during alignment.

Description : Centre to Centre spacing of formation for double railway line for Broad Gauge is a) 1676 mm b) 4725 mm c) 4265mm d) 5300 mm*

Last Answer : d) 5300 mm*

Description : 1. Which of the statements with regard to formation is correct (1) One of the Functions of the formation is to facilitate drainage (2) Width of bank for double railway line is 12.155 meters (3) Width of cutting for double railway track is 11. ... a) 2, 3, 5 b) 3, 4, 5* c) 2, 3, 4 d) 2, 4, 5

Last Answer : b) 3, 4, 5*

Description : Reconnaissance is best done with the help of (A) Aerial photographic survey (B) Cadastral surveys (C) Topographical surveys (D) Triangulation surveys

Last Answer : Answer: Option A

Description : “Composite sleeper index” is employed to determine a) sleeper density requirement b) number of fixtures required for a particular type of sleeper c) durability of sleeper d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Last Answer : d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Description : Which of the following statements refer to correct purpose as regards testing of concrete by ultrasonic pulse velocity method? 1. To assess the quality of concrete in-situ. 2. To determine the dynamic modulus of elasticity of concrete. 3 ... and 2 only (b) 1 and 3 only (c) 2 and 3 only (d)1, 2 and 3

Last Answer : (d)1, 2 and 3

Description : What are the three phases of a security evaluation plan? (Choose three answers.) A. Conduct Security Evaluation B. Preparation C. Conclusion D. Final E. Reconnaissance F. Design Security G. Vulnerability Assessment

Last Answer : A. Conduct Security Evaluation B. Preparation C. Conclusion

Description : What are the three phases of a security evaluation plan? (Choose three answers.) A. Conduct Security Evaluation B. Preparation C. Conclusion D. Final E. Reconnaissance F. Design Security G. Vulnerability Assessment

Last Answer : A. Conduct Security Evaluation B. Preparation C. Conclusion

Description : What are the three phases of a security evaluation plan? (Choose three answers.) ∙ A. Conduct Security Evaluation ∙ B. Preparation ∙ C. Conclusion ∙ D. Final ∙ E. Reconnaissance ∙ F. Design Security ∙ G. Vulnerability Assessment

Last Answer : A. Conduct Security Evaluation B. Preparation C. Conclusion

Description : Which of the following statements about a Money Bill is not correct? (1) A Money Bill can be tabled in either House of Parliament. (2) The Speaker of sLok Sabha is the final authority to decide ... within 14 days. (4) The President cannot return a Money Bill to the Lok Sabha for reconsideration.

Last Answer : (1) A Money Bill can be tabled in either House of Parliament Explanation : As per Article 110, a Money Bill can be introduced in Lok Sabha only. If any question arises whether a Bill is a Money Bill ... consult any one in coming to a decision or in giving his certificate that a Bill is a Money Bill.

Description : What is the full form UTS of rails a. Ultimate technical Strength b. Ultimate tensile Strength* c. Upper Top surface d. None of above

Last Answer : b. Ultimate tensile Strength*

Description : The audit work performed by each assistant should be reviewed to determine whether it was adequately performed and to evaluate whether the a. Results are consistent with the conclusions to be presented in the ... as auditors. d. Auditor's system of quality control has been maintained at a high leve

Last Answer : Results are consistent with the conclusions to be presented in the auditor's report.

Description : Which of the instruments is not used in Preliminary survey. (a) Theodelite (b) Tacheometer (c) Dumpy level (d) Plane table (e) None of them*

Last Answer : (e) None of them*

Description : Urinals & Latrines for A & B stations as norms for recommended level of facilities for railway station (a) Ndb/500 (b) Ndb/300 (c) Ndb/200* (d) None of the above

Last Answer : (c) Ndb/200*

Description : Sewerage system of a railway colony may be (a) Combined system (b) Separate system (c) Partially combined system (d) Any of them*

Last Answer : (d) Any of them*

Description : Which of the following stone is best suited for construction of piers and abutments of Railway Bridge a) Granite* b) Sandstone c) Limestone d) Quartzite

Last Answer : a) Granite*

Description : Stone generally preferred for railway ballast is a) Sandstone b) Dolomite c) Marble d) Basalt or trap granite*

Last Answer : d) Basalt or trap granite*

Description : For laying a Railway track the prepared surface ready to receive the ballast is called a) Sub ballast b) Formation* c) Blanket d) Cushion

Last Answer : b) Formation*

Description : arthwork in embankment for railway with manual compaction should be done in layers not exceeding-------------- a) 15 centimeter b) 20 centimeters c) 25 centimeters d) 30 centimeters*

Last Answer : d) 30 centimeters*

Description : On Indian Railways a new level crossing can be provided with the approval of a) Chief engineer b) General Manager c) Commissioner of Railway Safety d) None of the above*

Last Answer : d) None of the above

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters

Last Answer : c) 20 meters*

Description : When the railway crosses a deep vally without perinial water,it is called……. a)Aqueduct * b)Cause way c)Via-duct d)River crossing

Last Answer : a)Aqueduct *

Description : RBG loading stands for a)Revised Broad gauge loading b) Rolling Broad gauge loading c)Railway Broad gauge loading d) None of above

Last Answer : a)Revised Broad gauge loading

Description : For railway bridges with spans in excess of 30.5m, generally provided with a) deck type girders b) open web through girders* c) semi through girders d) shallow type girders

Last Answer : b) open web through girders*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : tructural steel for railway loading above 0oC temperature conforms to -- a) IS 2062 grade A b) IS 2062 grade B* c) IS 2062 grade C d) None of the above

Last Answer : b) IS 2062 grade B*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : With regard to standard of quality of drinking water as laid down by Indian Railway , the requirement (desirable) limit of total dissolved solids should not be more than---------- mg/l a)200 b) 300 c) 400

Last Answer : d) 500*