Pick up the PERT event from the following:
(A) Digging of foundation started
(B) Digging of foundation completed
(C) Laying of concrete started
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : Which of the following is not a PERT event? (A) Site investigation started (B) Sessional work completed (C) Bus starts from Jaipur (D) Class is being attended

Last Answer : (D) Class is being attended

Description : For providing a raft foundation, the following activities are involved 1. Ramming the foundation bed 2. Excavation of the soil upto required depth 3. Laying the reinforcement over the foundation bed 4. Curing the cement concrete placed over ... 2, 1 (C) 2, 1, 3, 5, 4 (D) 3, 2, 5, 1, 4

Last Answer : Answer: Option C

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : PERT is (A) An analytic in concept (B) Limited of event oriented diagrams (C) Used for research and development projects (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The operation of removing material from the sea or river bed is known as (B) Dredging (C) Digging (D) None of these

Last Answer : (A) The operation of removing material from the sea or river bed is known as

Description : How long have construction workers been laying sheet of plastic on the ground before laying the foundation?

Last Answer : https://en.wikipedia.org/wiki/Vapor_barrier

Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : b. PERT

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : After pre-stressing process is completed, a loss of stress is due to (A) Shrinkage of concrete (B) Elastic shortening of concrete (C) Creep of concrete (D) All the above

Last Answer : Answer: Option D

Description : If P kg/m2 is the upward pressure on the slab of a plain concrete footing whose projection on either side of the wall is a cm, the depth of foundation D is given by (A) D = 0.00775 aP (B) D = 0.0775 aP (C) D = 0.07775 aP (D) D = 0.775 Pa

Last Answer : Answer: Option A

Description : The measurement is made in square metre in case of (A) Cement concrete in foundation (B) R.C.C. structure (C) Hollow concrete block wall (D) None of these

Last Answer : (D) None of these

Description : Which one of the following represents an activity? (A) Excavation for foundation (B) Curing of concrete (C) Setting of question paper (D) All the above

Last Answer : (D) All the above

Description : The depth of concrete bed of the foundation depends upon (A) The projection of the concrete block beyond the footing over it (B) The upward soil pressure (C) The mix of the concrete (D) All the above

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) If the ratio of depth to width is less than 2, it is shallow foundation (B) If the ratio of depth to width is more than 2, it is deep ... the ratio of the length to width is between 1 and 2, it is spread foundation (D) All the above

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following: (A) The function of foundation is to distribute the load of super structure over a large bearing area (B) No timbering is required for shallow ... can be constructed on made-up soil (D) Black cotton soil is very good for foundation bed

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The cost of square rooms is less (B) The expenditure on the foundation and roof for the double storeyed building is nearly half of that ... cost of construction of a house may be minimised by restricting the height floors (D) All the above

Last Answer : Answer: Option D

Description : Water supply system includes  (A) Digging a well for water  (B) Construction of dams  (C) Construction of canals  (D) Entire arrangement from source to distribution 

Last Answer : (D) Entire arrangement from source to distribution 

Description : Which of the following excavators is most suitable for digging under water? (A) Drag line (B) Hoe (C) Clam shell (D) Dipper shovel

Last Answer : (A) Drag line

Description : Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to ... and 4 (B) 3, 4 and 5 (C) 1, 3 and 4 (D) 1, 2 and 5

Last Answer : (A) 1, 2 and 4

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : PERT technique of network analysis is mainly useful for (A) Small projects (B) Large and complex projects (C) Research and development projects (D) Deterministic activities

Last Answer : (C) Research and development projects

Description : In PERT analysis, the time estimates of activities and probability of their occurrence follow (A) Normal distribution curve (B) Poisson's distribution curve (C) Beta distribution curve (D) None of the above

Last Answer : (C) Beta distribution curve

Description : The probability distribution taken to represent the completion of time in PERT analysis is (a) Normal Distribution (b) Bet Distribution (c) Gamma Distribution (d) Gaussain Distribution

Last Answer : (a) Normal Distribution

Description : How would you feel if your two favorite people who had completed everything in an athletic event many times before were eliminated in the first round?

Last Answer : Disappointed

Description : Which one of the following represents an event? (A) Concrete cured (B) Fixing of door (C) Plastering of walls (D) Selecting sites

Last Answer : (A) Concrete cured

Description : Vani, a class X student has recently completed her HTML course and just started learning XML. Help her in the following: -Technology

Last Answer : (i) Primary purpose of HTML is to design a webpage while XML is used to store and transport the data.(ii) Right(iii) Comments are added as notes or lines for understanding the purpose of an XML ... .Syntax for comments are as follows:(v)An XML document with correct syntax is called 'Well Formed'.

Description : Kathir and Anand can do a work in 20 days and 30 days respectively. Kathir started the work and left after 4 days. Anand took over and completed the work. In how many days was the total work completed? a) 28 days b) 20 days c) 23 days d) 25 days e) 26 days 

Last Answer : a Kathir’s one day’s work= 1/20 Kathir’s 4 day’s work =4* (1/20) = 1/5 Work left= 1-1/5 = 4 /5 Anand’s one day’s work= 1/30 Anand can do work in = (4/5) *(30/ 1) = 24 days So total days = 24+4 = 28 days

Description : 8 men and 4 women-together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men ... more days will the work be completed? a) 7 days b) 6 days c) 5 days d) 8 days e) 4 days 

Last Answer : 1 man = 2 women 8 men + 4 women = 20 women 2 day's work of 20 women = 20 × 6/1 = 20 × 2/x x =1/3 Remaining work = 1 – 1/3 = 2/3 Total number of females = 16 20 × 6/1 = 16 × x ÷2/ 3 x = 5 days Short Cut M1D1=M2D2+M3D3 10x6 =10x2 + 8 x 60-20= 8x x= 5 days Answer: c)

Description : Activities that cannot be started until one or more of the other activities are completed, are called.......................................... a. Dummy activities b. Initial activities c. Successor activities d. Predecessor activities

Last Answer : c. Successor activities

Description : P,Q, & R can complete a piece of job together in 20 days. All the 3 started working at it together and after 8 days P left. Then Q & R together completed a job in 20 more days. P alone could complete the work in. a) 60 b) 50 c) 40 d) 30

Last Answer : B Work done by P,Q & R in 8 days = 1/20 * 8 =2/5 Remaining work = (1 - 2/5) = 3/5 Now 3/5 work is done by Q & R in 20 days Whole work will be done by Q & R in(20*5/3) =100/3 days (P+Q+R ... (Q+R)'s 1 day work =1/20 - 3/100 =5-3/100 =2/100 =1/50 P alone could complete the work in 50 days..

Description : Hanisha can do a work in 25 days, while sudha can do the same work in 50 days. They started the work jointly.Few days sughana also joined them and thus all of them completed the whole work in 12 days. All of them were paid total Rs.900. What is the Share of sughana? a) 252 b) 346 c) 454 d).359

Last Answer : A Efficiency of Hanisha = 1/100*25 =25/100=1/4=>4% Efficiency of sudha = 2% Thus, in 12 days working together they will complete only 72% of the work. [(4+2)*12] =72 Hence, the remaining work will ... which is =(100-72)=28% Thus, sughana will get 28% of Rs. 900, =28/100*900 which is Rs.252

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : What is the total weight of the statue of liberty concrete foundation?

Last Answer : Need answer

Description : Raise Concrete Foundation?

Last Answer : form_title=Raise Concrete Foundation form_header=10603 What is the reason for raising your foundation? (Please check all that apply)*= [] Foundation cracked or broken [] Walls or piers are settling [] Cracks in walls/sheet ... water present in the area of the repair?*= () Yes () No () Don't Know

Description : Concrete Foundation Installation?

Last Answer : form_title=Concrete Foundation Installation form_header=7683 Have there been any completed structural drawings for this project?*= () Yes () No Which kind of concrete foundation would you like?*= ( ... mobile home () Existing foundation is beyond repair () Foundation for addition or small structure

Description : Do I need a concrete slab foundation for a steel storage shed?

Last Answer : No, although that would be great there are other options. You may also build a wooden foundation and it will work just as well.

Description : __________ is used for tying the steel columns to concrete foundation. (A) Grouting (B) Eyebolt (C) Anchor bolts (D) Refractory castables

Last Answer : C) Anchor bolts

Description : 122 ____________ is a campaign started by Bill Gates to encourage wealthy people to contribute a majority of their wealth to philanthropic causes A. Rotary International B. The Giving Pledge C. Bill & Melinda Gates Foundation D. United Nation Organization

Last Answer : ANSWER: B

Description : ____________ is a campaign started by Bill Gates to encourage wealthy people to contribute a majority of their wealth to philanthropic causes A. Rotary International B. The Giving Pledge C. Bill & Melinda Gates Foundation D. United Nation Organization

Last Answer : ANSWER: B

Description : ____________ is a campaign started by Bill Gates to encourage wealthy people to contribute a majority of their wealth to philanthropic causes A. Rotary International B. The Giving Pledge C. Bill & Melinda Gates Foundation D. United Nation Organization

Last Answer : ANSWER: B

Description : ____________ is a campaign started by Bill Gates to encourage wealthy people to contribute a majority of their wealth to philanthropic causes A. Rotary International B. The Giving Pledge C. Bill & Melinda Gates Foundation D. United Nation Organization

Last Answer : ANSWER: B

Description : In case of laying gullies, siphons, intercepting traps, the cost includes (A) Setting and laying (B) Bed concreting (C) Connection to drains (D) All of these

Last Answer : (D) All of these

Description : In brick masonry the bond produced by laying alternate headers and stretchers in each course is known as (A) English bond (B) Double Flemish bond (C) Zigzag bond (D) Single Flemish bond

Last Answer : Answer: Option B

Description : The most important tool in brick laying for lifting and spreading mortar and for forming joints is (A) Trowel (B) Square (C) Bolster (D) Scutch

Last Answer : Answer: Option A

Description : The method of moving each brick through a small horizontal distance before it is finally laid in any brick wall and pressing it by means of brick hammer, is known as (A) Trowelling (B) Laying (C) Grouting (D) Placing

Last Answer : Answer: Option B

Description : Brick nogging type of partition wall, is constructed by (A) Laying bricks as stretchers in cement mortar (B) Laying bricks as headers in cement mortar (C) Reinforcing brick wall with iron straps (D) Constructing brick work within a wooden framework

Last Answer : Answer: Option D

Description : In the construction of arches, sand box method is used for (A) Centring (B) Actual laying of arch work (C) Striking of centring (D) None of the above

Last Answer : Answer: Option C